| Environment |
| Table of Contents | Next |
Stormwater Best Management Practices in an Ultra-Urban Setting: Selection and MonitoringMonitoring Case Study-Delaware Sand Filter BMPs At Airpark, Alexandria, VirginiaThis case study is based on an evaluation of Delaware sand filter BMPs by Bell et al. (1995). Two large Delaware sand filter (DSF) BMPs were constructed to treat the runoff from AirPark, a 0.7 ha (1.7 ac) commercial parking lot near National Airport in Alexandria, Virginia. Construction was completed in the fall of 1992 with funding from a grant by the Virginia Chesapeake Bay Local Assistance Department. The performance of these BMPs were monitored for six months to establish the actual pollutant removal efficiency of a DSF treating northern Virginia's acid rainfall with locally available sands. Confirmation that efficiencies in the range experienced by other jurisdictions (namely, the city of Austin, Texas) can be attained in northern Virginia would allow economic use of a greater amount of property and substantially reduce the cost of compliance by developers with the Chesapeake Bay Preservation Act. Study Objectives
Design and OperationThe South Filter was one of the first large stormwater intermittent sand filter BMPs constructed in northern Virginia, one of two filters treating stormwater runoff from a 0.8 ha (1.95 ac) commercial parking lot located just south of National Airport. Impervious surfaces cover 95 percent of the site. Following the original DSF design with steel grates and covers, the cost of the filters exceeded $100,000 due to the high cost of the grates and covers. By modifying the original design and using a slotted curb design, the actual cost of the two filters was just over $40,000. The 0.8 ha (1.95 ac) paved lot is graded so that runoff sheet flow enters the West Filter; both sheet flow and flow along the curb line enter the South Filter (Figure 56). Reversed sloped curbs are provided at the lower ends of each filter to act as flow-splitters; once the storage capacity of the filter shell is exceeded, runoff backs up on the pavement until it flows around the nose of the reverse sloped curb and on into a curb inlet. The wedge of water stored on the pavement is part of the storage capacity of the overall BMP. Figure 56. General layout of AirPark filters (adapted from Bell et al., 1995)
After construction, both filters were found to take an inordinate amount of time to drain down. Two flat plastic drain tiles were installed along the entire length of the South Filter to decrease flow-through time and decrease the time that vehicles parked along the filter were inaccessible due to pooling of water to be treated. The outflow drain of the South Filter was also found to be approximately 5 cm (2 in) above the invert of the filter box rather than at the invert. With a bottom slope of 0.5 percent, approximately 10 m (33 ft) of the bottom filter sand remains continually saturated, creating potential anaerobic conditions. Other design parameters are provided in Table 30; where design values differ from the actual system, both values are provided.
MonitoringMonitoring problems with the West Filter required the team to shift their focus to the South Filter, where input samples could be collected from a sloping curb line uphill of the filter, and the underdrain system provided a flow rate that was much easier to monitor. Severe weather between December 1993 and April 1994, causing freezing problems in the sedimentation pools in the filters and freeze-up of the automatic monitoring equipment delayed the start of the monitoring study. Rainfall totalling 105 mm (4.13 in) fell at the airport (just across U.S. Route 1 from AirPark) immediately preceding the first sample taken for this study, so the filters had been saturated for almost two weeks immediately prior to the beginning of the monitoring effort. Active monitoring was resumed on April 4, 1994, and continued for 20 storm events through September 23, 1994. Input and output samples for the AirPark South Filter were collected utilizing a purpose-built monitoring manhole with Palmer-Bolus flume installed in the outflow pipe for the output samples; input samples were collected from the concrete gutter that conveys the runoff from the upper part of the parking lot to the filter. Both samplers were activated by transducer-type flowmeters. Rainfall data were collected directly at the AirPark site by an American Sigma rainfall gauge. Composite sampling was utilized to obtain a relatively unbiased approximation of the mass loads of pollutants processed by the filter by multiplying the event mean concentration for each storm by the volume of runoff treated; total sampling time was adjusted to approximate the time during which the "first-flush" of the filter was processed. The storm outflows measured by the flow meter in the outflow monitoring unit were originally intended to be used to compute mass balance efficiencies of the filter. However, volumes recorded by the meter were far short of the estimates of volume treated obtained from hydrological calculations. The outflow drain was found to be installed 5 cm (2 in) above the bottom of the filter box, and the outflow pipe directly above the Palmer-Bolus flume was found to have a slope of 3.4 percent (rather than the specified 0.76 percent), which fell outside the requirements for accurate flow measurement (maximum slope 2.2 percent) for the flume and flow meter computer program. The project team decided to use the calculated treatment volumes for calculating weighted mean concentrations and mass balance removal efficiencies. Table 31 presents the results of the monitoring study.
Monitoring results for the fourteenth storm on the South Filter led the project team to reassess the work plan due to radically different outcomes than had been previously experienced. Phosphorous and orthophosphorous removal fell to negative values, while the rates of nitrogen components fluctuated widely. It was suspected that the anaerobic zone had suddenly expanded to encompass the majority of the filter; precipitation records at National Airport showed rainfall during 12 of the 18 days immediately preceding the incident. Monitoring of the South Filter was continued until all results indicated the filter had returned to a predominantly aerobic condition. Conclusions
ReferencesBell, W., L. Stokes, L.J. Gavan, and T.N. Nguyen. 1995. Assessment of the Pollutant Removal Efficiencies of Delaware Sand Filter BMPs. City of Alexandria, Department of Transportation and Environmental Services, Alexandria, VA. |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Table of Contents | Next |