23 CFR Chapter 1 (2001)

This archived guidanace was obtained from the National Archives and Records Administration Electronic CFR and was current as of October 16, 2001. For current guidance, see the online eCFR.

23 CFR Highways CHAPTER I
FEDERAL HIGHWAY ADMINISTRATION, DEPARTMENT OF TRANSPORTATION


CHAPTER TABLE OF CONTENTS


SUBCHAPTER A -- GENERAL MANAGEMENT AND ADMINISTRATION
Part

1   General


SUBCHAPTER B -- PAYMENT PROCEDURES
140   Reimbursement
172   Administration of engineering and design related service contracts
180   Credit assistance for Surface Transportation projects
190   Incentive payments for controlling outdoor advertising on the interstate system
192   Drug offender's driver's license suspension


SUBCHAPTER C -- CIVIL RIGHTS
200   Title VI program and related statutes -- implementation and review procedures
230   External programs


SUBCHAPTER D -- NATIONAL HIGHWAY INSTITUTE
260   Education and training programs


SUBCHAPTER E -- PLANNING AND RESEARCH
420   Planning and research program administration
450   Planning assistance and standards
460   Public road mileage for apportionment of highway safety funds
470   Highway systems
476   Interstate highway system


SUBCHAPTER F -- TRANSPORTATION INFRASTRUCTURE MANAGEMENT
500   Management and monitoring systems
511   [Reserved]


SUBCHAPTER G -- ENGINEERING AND TRAFFIC OPERATIONS
620   Engineering
625   Design standards for highways
626   Pavement policy
627   Value engineering
630   Preconstruction procedures
633   Required contract provisions
635   Construction and maintenance
637   Construction inspection and approval
640   Certification acceptance
645   Utilities
646   Railroads
650   Bridges, structures, and hydraulics
652   Pedestrian and bicycle accommodations and projects
655   Traffic operations
656   Carpool and vanpool projects
657   Certification of size and weight enforcement
658   Truck size and weight, route designations -- length, width and weight limitations
660   Special programs (Direct Federal)
661   Indian Reservation Road Bridge Program
667   [Reserved]
?   Emergency relief program
669   Enforcement of heavy vehicle use tax


SUBCHAPTER H -- RIGHT-OF-WAY AND ENVIRONMENT
710   Right-of-way and real estate
750   Highway beautification
751   Junkyard control and acquisition
752   Landscape and roadside development
771   Environmental impact and related procedures
772   Procedures for abatement of highway traffic noise and construction noise
777   Mitigation of environmental impacts to privately owned wetlands


SUBCHAPTER I -- PUBLIC TRANSPORTATION
810   Mass transit and special use highway projects


SUBCHAPTER J -- HIGHWAY SAFETY
924   Highway safety improvement program


SUBCHAPTER K -- INTELLIGENT TRANSPORTATION SYSTEMS
940   Intelligent transportation system architecture and standards


SUBCHAPTER A -- GENERAL MANAGEMENT AND ADMINISTRATION




PART 1 -- GENERAL


Sec.
1.1   Purpose.
1.2   Definitions.
1.3   Federal-State cooperation; authority of State highway departments.
1.5   Information furnished by State highway departments.
1.7   Urban area boundaries.
1.8   [Reserved]
1.9   Limitation on Federal participation.
1.11   Engineering services.
1.23   Rights-of-way.
1.27   Maintenance.
1.28   Diversion of highway revenues.
1.32   Issuance of directives.
1.33   Conflicts of interest.
1.35   Bonus program.
1.36   Compliance with Federal laws and regulations.

Authority: 23 U.S.C. 315; 49 CFR 1.48(b).

Source: 25 FR 4162, May 11, 1960, unless otherwise noted.


§1.1   Purpose.

The purpose of the regulations in this part is to implement and carry out the provisions of Federal law relating to the administration of Federal aid for highways.


§1.2   Definitions.

(a) Terms defined in 23 U.S.C. 101(a), shall have the same meaning where used in the regulations in this part, except as modified herein.

(b) The following terms where used in the regulations in this part shall have the following meaning:

Administrator. The Federal Highway Administrator.

Advertising policy. The national policy relating to the regulation of outdoor advertising declared in title 23 U.S.C. 131.

Advertising standards. The "National Standards for Regulation by States of Outdoor Advertising Signs, Displays and Devices Adjacent to the National System of Interstate and Defense Highways" promulgated by the Secretary (part 20 of this chapter).

Federal laws. The provisions of title 23 U.S.C., and all other Federal laws, heretofore or hereafter enacted, relating to Federal aid for highways.

Latest available Federal census. The latest available Federal decennial census, except for the establishment of urban area.

Project. An undertaking by a State highway department for highway construction, including preliminary engineering, acquisition of rights-of-way and actual construction, or for highway planning and research, or for any other work or activity to carry out the provisions of the Federal laws for the administration of Federal aid for highways.

Secondary road plan. A plan for administration of Federal aid for highways on the Federal-aid secondary highway system pursuant to 23 U.S.C. 117.

Secretary. The Secretary of Transportation.

State. Any State of the United States, the District of Columbia and Puerto Rico.

Urban area. An area including and adjacent to a municipality or other urban place having a population of five thousand or more, as determined by the latest available published official Federal census, decennial or special, within boundaries to be fixed by a State highway department, subject to the approval of the Administrator.

[25 FR 4162, May 11, 1960, as amended at 35 FR 18719, Dec. 10, 1970]



§1.3   Federal-State cooperation; authority of State highway departments.

The Administrator shall cooperate with the States, through their respective State highway departments, in the construction of Federal-aid highways. Each State highway department, maintained in conformity with 23 U.S.C. 302, shall be authorized, by the laws of the State, to make final decisions for the State in all matters relating to, and to enter into, on behalf of the State, all contracts and agreements for projects and to take such other actions on behalf of the State as may be necessary to comply with the Federal laws and the regulations in this part.


§1.5   Information furnished by State highway departments.

At the request of the Administrator the State highway department shall furnish to him such information as the Administrator shall deem desirable in administering the Federal-aid highway program.


§1.7   Urban area boundaries.

Boundaries of an urban area shall be submitted by the State highway department and be approved by the Administrator prior to the inclusion in a program of any project wholly or partly in such area involving funds authorized for and limited to urban areas.


§1.8   [Reserved]


§1.9   Limitation on Federal participation.

(a) Federal-aid funds shall not participate in any cost which is not incurred in conformity with applicable Federal and State law, the regulations in this title, and policies and procedures prescribed by the Administrator. Federal funds shall not be paid on account of any cost incurred prior to authorization by the Administrator to the State highway department to proceed with the project or part thereof involving such cost.

(b) Notwithstanding the provisions of paragraph (a) of this section the Administrator may, upon the request of a State highway department, approve the participation of Federal-aid funds in a previously incurred cost if he finds:

(1) That his approval will not adversely affect the public,

(2) That the State highway department has acted in good faith, and that there has been no willful violation of Federal requirements,

(3) That there has been substantial compliance with all other requirements prescribed by the Administrator, and full compliance with requirements mandated by Federal statute,

(4) That the cost to the United States will not be in excess of the cost which it would have incurred had there been full compliance, and

(5) That the quality of work undertaken has not been impaired.

(c) Any request submitted under paragraph (b) of this section shall be accompanied by a detailed description of the relevant circumstances and facts, and shall explain the necessity for incurring the costs in question.

[38 FR 18368, July 10, 1973]



§1.11   Engineering services.

(a) Federal participation. Costs of engineering services performed by the State highway department or any instrumentality or entity referred to in paragraph (b) of this section may be eligible for Federal participation only to the extent that such costs are directly attributable and properly allocable to specific projects. Expenditures for the establishment, maintenance, general administration, supervision, and other overhead of the State highway department, or other instrumentality or entity referred to in paragraph (b) of this section shall not be eligible for Federal participation.

(b) Governmental engineering organizations. The State highway department may utilize, under its supervision, the services of well-qualified and suitably equipped engineering organizations of other governmental instrumentalities for making surveys, preparing plans, specifications and estimates, and for supervising the construction of any project.

(c) Railroad and utility engineering organizations. The State highway department may utilize, under its supervision, the services of well-qualified and suitably equipped engineering organizations of the affected railroad companies for railway-highway crossing projects and of the affected utility companies for projects involving utility installations.

(d) [Reserved]

(e) Responsibility of the State highway department. The State highway department is not relieved of its responsibilities under Federal law and the regulations in this part in the event it utilizes the services of any engineering organization under paragraphs (b), (c) or (d) of this section.

[25 FR 4162, May 11, 1960, as amended at 53 FR 18276, May 23, 1988; 57 FR 60728, Dec. 22,1992]



§1.23   Rights-of-way.

(a) Interest to be acquired. The State shall acquire rights-of-way of such nature and extent as are adequate for the construction, operation and maintenance of a project.

(b) Use for highway purposes. Except as provided under paragraph (c) of this section, all real property, including air space, within the right-of-way boundaries of a project shall be devoted exclusively to public highway purposes. No project shall be accepted as complete until this requirement has been satisfied. The State highway department shall be responsible for preserving such right-of-way free of all public and private installations, facilities or encroachments, except (1) those approved under paragraph (c) of this section; (2) those which the Administrator approves as constituting a part of a highway or as necessary for its operation, use or maintenance for public highway purposes and (3) informational sites established and maintained in accordance with §1.35 of the regulations in this part.

(c) Other use or occupancy. Subject to 23 U.S.C. 111, the temporary or permanent occupancy or use of right-of-way, including air space, for nonhighway purposes and the reservation of subsurface mineral rights within the boundaries of the rights-of-way of Federal-aid highways, may be approved by the Administrator, if he determines that such occupancy, use or reservation is in the public interest and will not impair the highway or interfere with the free and safe flow of traffic thereon.


§1.27   Maintenance.

The responsibility imposed upon the State highway department, pursuant to 23 U.S.C. 116, for the maintenance of projects shall be carried out in accordance with policies and procedures issued by the Administrator. The State highway department may provide for such maintenance by formal agreement with any adequately equipped county, municipality or other governmental instrumentality, but such an agreement shall not relieve the State highway department of its responsibility for such maintenance.


§1.28   Diversion of highway revenues.

(a) Reduction in apportionment. If the Secretary shall find that any State has diverted funds contrary to 23 U.S.C. 126, he shall take such action as he may deem necessary to comply with said provision of law by reducing the first Federal-aid apportionment of primary, secondary and urban funds made to the State after the date of such finding. In any such reduction, each of these funds shall be reduced in the same proportion.

(b) Furnishing of information. The Administrator may require any State to submit to him such information as he may deem necessary to assist the Secretary in carrying out the provisions of 23 U.S.C. 126 and paragraph (a) of this section.


§1.32   Issuance of directives.

(a) The Administrator shall promulgate and require the observance of policies and procedures, and may take other action as he deems appropriate or necessary for carrying out the provisions and purposes of Federal laws, the policies of the Federal Highway Administration, and the regulations of this part.

(b) The Administrator or his delegated representative, as appropriate, is authorized to issue the following type of directives:

(1) Federal Highway Administration Regulations are issued by the Administrator or his delegate, as necessary, to implement and carry out the provisions of title 23 U.S.C., relating to the administration of Federal aid for highways, direct Federal programs and State and community safety programs; and title 49 U.S.C., relating to motor carrier safety; and other applicable laws and programs under his jurisdiction.

(2) Notices are temporary issuances transmitting one-time or short-term instructions or information which is expected to remain in effect for less than 90 days or for a predetermined period of time normally not to exceed one year.

(3) Orders are directives limited in volume and contain permanent or longlasting policy, instructions, and procedures. FHWA Orders are to be used primarily as internal FHWA directives.

(4) Joint Interagency Orders and Notices are used by FHWA and the National Highway Traffic Safety Administration (NHTSA) to issue joint policies, procedures, and information pertaining to the joint administration of the State and Community Highway Safety Program. Where necessary, other joint directives may be issued with other modal administrations within the Department of Transportation.

(5) Manuals are generally designed for use in issuing permanent or long-lasting detailed policy and procedure. Some of the major manuals recognized by the FHWA Directives System follow:

(i) The Federal-Aid Highway Program Manual has been established to assemble and organize program material of the type previously contained in the Policy and Procedure and Instructional Memoranda which will continue in effect until specifically revoked or published in the new manual. Regulatory material is printed in italics in the manual and also appears in this code. Nonregulatory material is printed in delegate type.

(ii) The Administrative Manual covers all internal FHWA administrative support functions.

(iii) The Highway Planning Program Manual covers the methods and procedures necessary to conduct the highway planning functions.

(iv) The Research and Development Manual series entitled, "The Federally Coordinated Program of Research and Development in Highway Transportation" describes the FHWA research and development program.

(v) The External Audit Manual provides guidance to FHWA auditors in their review of State programs and processes.

(vi) The Civil Rights and Equal Opportunity Manual provides guidance to FHWA and State Civil Rights and Equal Employment Opportunity Officers.

(vii) The BMCS Operations Manual provides program guidance for all field employees assigned to the motor carrier safety program.

(viii) The Highway Safety Program Manual, issued jointly by FHWA and NHTSA, contains volumes relating to the joint administration of the program.

(6) Handbooks are internal operating instructions published in book form where, because of the program area covered, it is desirable to provide greater detail of administrative and technical instructions.

(7) Transmittals identify and explain the original issuance or page change, provide background information, and provide filing instructions for insertion of new pages and removal of changed pages, or both. 49 U.S.C. 1655)

[39 FR 1512, Jan. 10, 1974]



§1.33   Conflicts of interest.

No official or employee of a State or any other governmental instrumentality who is authorized in his official capacity to negotiate, make, accept or approve, or to take part in negotiating, making, accepting or approving any contract or subcontract in connection with a project shall have, directly or indirectly, any financial or other personal interest in any such contract or subcontract. No engineer, attorney, appraiser, inspector or other person performing services for a State or a governmental instrumentality in connection with a project shall have, directly or indirectly, a financial or other personal interest, other than his employment or retention by a State or other governmental instrumentality, in any contract or subcontract in connection with such project. No officer or employee of such person retained by a State or other governmental instrumentality shall have, directly or indirectly, any financial or other personal interest in any real property acquired for a project unless such interest is openly disclosed upon the public records of the State highway department and of such other governmental instrumentality, and such officer, employee or person has not participated in such acquisition for and in behalf of the State. It shall be the responsibility of the State to enforce the requirements of this section.


§1.35   Bonus program.

(a) Any agreement entered into by a State pursuant to the provisions of section 12 of the Federal-Aid Highway Act of 1958, Pub. L. 85-381, 72 Stat. 95, as amended, shall provide for the control or regulation of outdoor advertising, consistent with the advertising policy and standards promulgated by the Administrator, in areas adjacent to the entire mileage of the Interstate System within that State, except such segments as may be excluded from the application of such policy and standards by section 12.

(b) Any such agreement for the control of advertising may provide for establishing publicly owned informational sites, whether publicly or privately operated, within the limits of or adjacent to the right-of-way of the Interstate System on condition that no such site shall be established or maintained except at locations and in accordance with plans, in furtherance of the advertising policy and standards, submitted to and approved by the Administrator.

(c) No advertising right in the acquisition of which Federal funds participated shall be disposed of without the prior approval of the Administrator.

[39 FR 28628, Aug. 9, 1974]



§1.36   Compliance with Federal laws and regulations.

If the Administrator determines that a State has violated or failed to comply with the Federal laws or the regulations in this part with respect to a project, he may withhold payment to the State of Federal funds on account of such project, withhold approval of further projects in the State, and take such other action that he deems appropriate under the circumstances, until compliance or remedial action has been accomplished by the State to the satisfaction of the Administrator.


SUBCHAPTER B -- PAYMENT PROCEDURES




PART 140 -- REIMBURSEMENT



Subpart A [Reserved]


Subpart B -- Construction Engineering Costs


   Sec.
140.201   Purpose.
140.203   Policy.
140.205   Limitation.
140.207   Application of limitation.

Subparts C-D [Reserved]


Subpart E -- Administrative Settlement Costs -- Contract Claims

140.501   Purpose.
140.503   Definition.
140.505   Reimbursable costs.

Subpart F -- Reimbursement for Bond Issue Projects

140.601   Purpose.
140.602   Requirements and conditions.
140.603   Programs.
140.604   Reimbursable schedule.
140.605   Approval actions.
140.606   Project agreements.
140.607   Construction.
140.608   Reimbursable bond interest costs of Interstate projects.
140.609   Progress and final vouchers.
140.610   Conversion from bond issue to funded project status.
140.611   Determination of bond retirement.
140.612   Cash management.
Appendix to Subpart F -- Reimbursable Schedule for Converted "‘E" (Bond Issue) Projects (Other Than Interstate Projects)

Subpart G [Reserved]


Subpart H -- State Highway Agency Audit Expense

140.801   Purpose.
140.803   Policy.
140.805   Definitions.
140.807   Reimbursable costs.

Subpart I -- Reimbursement for Railroad Work

140.900   Purpose.
140.902   Applicability.
140.904   Reimbursement basis.
140.906   Labor costs.
140.907   Overhead and indirect construction costs.
140.908   Materials and supplies.
140.910   Equipment.
140.912   Transportation.
140.914   Credits for improvements.
140.916   Protection.
140.918   Maintenance and extended construction.
140.920   Lump sum payments.
140.922   Billings.

Authority: 23 U.S.C. 101(e), 106, 109(e), 114(a), 120(g), 121, 122, 130, and 315; and 49 CFR 1.48(b).



Subpart A [Reserved]

Subpart B -- Construction Engineering Costs


Source: 58 FR 39143, July 22, 1993, unless otherwise noted.


§140.201   Purpose.

The purpose of this subpart is to prescribe policies for claiming reimbursement for eligible construction engineering (CE) costs.


§140.203   Policy.

(a) State highway agencies (SHA) may be reimbursed for the Federal share of CE costs incurred as described in §140.703.

(b) Reimbursement for CE costs for Federal-aid construction projects shall be subject to the limitation set forth in §140.205.


§140.205   Limitation.

(a) The estimated CE costs for a SHA for a fiscal year shall not exceed, in the aggregate, 15 percent of the total estimated costs of all projects financed within the boundaries of the State with Federal-aid highway funds in such fiscal year, exclusive of the costs of rights-of-way, preliminary engineering, and CE.

(b) For control purposes, a SHA's estimated CE costs percentage will be determined by the ratio of the total amount obligated for CE to the total amount obligated for all projects financed with Federal-aid highway funds during the fiscal year, after excluding from such totals, the obligations for rights-of-way, preliminary engineering, and CE. This percentage shall not exceed 15 percent at the end of the fiscal year. The CE limitation may be applied on either a Federal or State fiscal year basis.

(1) Amounts to be included in the determination for CE will be the aggregate total of all obligations of CE, including original project obligations at the authorization stage, all subsequent adjustments during the fiscal year, and all adjustments (debits or credits) to projects authorized in previous fiscal years.

(2) The CE limitation determination for each fiscal year will be treated separately and may not be adjusted after the end of that fiscal year.

(c) Projects which are closed (final voucher processed) as of December 18, 1991, may be reopened to accept adjustments and additional eligible project charges. All obligation/deobligation adjustments must be included in the current fiscal year calculation. However, the CE cost for each of these projects shall be limited to 15 percent of each project construction cost in accordance with the provisions in effect prior to December 18, 1991.

(d) If the SHA claims CE costs as an average percentage of the actual construction costs in accordance with 23 U.S.C. 120(g), the average rate shall be determined based upon reimbursable CE costs and shall not exceed 15 percent, exclusive of the costs of rights-of-way, preliminary engineering, and CE.


§140.207   Application of limitation.

The limitation applies to all projects financed with Federal-aid highway funds.

Subparts C-D [Reserved]

Subpart E -- Administrative Settlement Costs -- Contract Claims


Source: 44 FR 59233, Oct. 15, 1979, unless otherwise noted.


§140.501   Purpose.

This regulation establishes the criteria for eligibility for reimbursement of administrative settlement costs in defense of contract claims on projects performed by a State under Federal-aid procedures.


§140.503   Definition.

Administrative settlement costs are costs related to the defense and settlement of contract claims including, but not limited to, salaries of a contracting officer or his/her authorized representative, attorneys, and/or members of State boards of arbitration, appeals boards, or similar tribunals, which are allocable to the findings and determinations of contract claims, but not including administrative or overhead costs.


§140.505   Reimbursable costs.

(a) Federal funds may participate in administrative settlement costs which are:

(1) Incurred after notice of claim,

(2) Properly supported,

(3) Directly allocable to a specific Federal-aid or Federal project,

(4) For employment of special counsel for review and defense of contract claims, when

(i) Recommended by the State Attorney General or State Highway Agency (SHA) legal counsel and

(ii) Approved in advance by the FHWA Division Administrator, with advice of FHWA Regional Counsel, and

(5) For travel and transportation expenses, if in accord with established policy and practices.

(b) No reimbursement shall be made if it is determined by FHWA that there was negligence or wrongdoing of any kind by SHA officials with respect to the claim.

Subpart F -- Reimbursement for Bond Issue Projects


Source: 48 FR 54971, Dec. 8, 1983, unless otherwise noted.


§140.601   Purpose.

To prescribe policies and procedures for the use of Federal funds by State highway agencies (SHAs) to aid in the retirement of the principal and interest of bonds, pursuant to 23 U.S.C. 122 and the payment of interest on bonds of eligible Interstate projects.


§140.602   Requirements and conditions.

(a) An SHA that uses the proceeds of bonds issued by the State, a county, city or other political subdivision of the State, for the construction of projects on the Federal-aid primary or Interstate system, or extensions of any of the Federal-aid highway systems in urban areas, or for substitute highway projects approved under 23 U.S.C. 103(e)(4), may claim payment of any portion of such sums apportioned to it for expenditures on such system to aid in the retirement of the principal of bonds at their maturities, to the the extent that the proceeds of bonds have actually been expended in the construction of projects.

(b) Any interest earned and payable on bonds, the proceeds of which were expended on Interstate projects after November 6, 1978, is an eligible cost of construction. The amount of interest eligible for participation will be based on (1) the date the proceeds were expended on the project, (2) amount expended, and (3) the date of conversion to a regularly funded project. As provided for in section 115(c), Pub. L. 95-599, November 6, 1978, interest on bonds issued in any fiscal year by a State after November 6, 1978, may be paid under the authority of 23 U.S.C. 122 only if such SHA was eligible to obligate Interstate Discretionary funds under the provisions of 23 U.S.C. 118(b) during such fiscal year, and the Administrator certifies that such eligible SHA has utilized, or will utilize to the fullest extent possible during such fiscal year, its authority to obligate funds under 23 U.S.C. 118(b).

(c) The Federal share payable at the time of conversion, as provided for in §140.610 shall be the legal pro rata in effect at the time of execution of the project agreement for the bond issue project.

(d) The authorization of a bond issue project does not constitute a commitment of Federal funds until the project is converted to a regular Federal-aid project as provided for in §140.610.

(e) Reimbursements for the redemption of bonds may not precede, by more than 60 days, the scheduled date of the retirement of the bonds.

(f) Federal funds are not eligible for payment into sinking funds created and maintained for the subsequent retirement of bonds.


§140.603   Programs.

Programs covering projects to be financed from the proceeds of bonds shall be prepared and submitted to FHWA. Project designations shall be the same as for regular Federal-aid projects except that the prefix letter "B" for bond issue shall be used as the first letter of each project designation, e.g., "BI" for Bond Issue Projects -- Interstate.


§140.604   Reimbursable schedule.

Projects to be financed from other than Interstate funds shall be subject to a 36-month reimbursable schedule upon conversion to regular Federal-aid financing (See appendix). FHWA will consider requests for waiver of this provision at the time of conversion action. Waivers are subject to the availability of liquidating cash.


§140.605   Approval actions.

(a) Authorization to proceed with preliminary engineering and acquisition of rights-of-way shall be issued in the same manner as for regularly financed Federal-aid projects.

(b) Authorization of physical construction shall be given in the same manner as for regularly financed Federal-aid projects. The total cost and Federal funds required, including interest, shall be indicated in the plans, specifications, and estimates.

(c) Projects subject to the reimbursable schedule shall be identified as an "E" project when the SHA is authorized to proceed with all or any phase of the work.

(d) Concurrence in the award of contracts shall be given.


§140.606   Project agreements.

Project Agreements, Form PR-2, shall be prepared and executed. Agreement provision 8 on the reverse side of Form PR-2 1 shall apply for bond issue projects.

1The text of FHWA Form PR-2 is found in 23 CFR part 630, subpart C, appendix A.


§140.607   Construction.

Construction shall be supervised by the SHA in the same manner as for regularly financed Federal-aid projects. The FHWA will make construction inspections and reports.


§140.608   Reimbursable bond interest costs of Interstate projects.

(a) Bond interest earned on bonds actually retired may be reimbursed on the Federal pro rata basis applicable to such projects in accordance with §140.602(b) and (c).

(b) No interest will be reimbursed for bonds issued after November 6, 1978, used to retire or otherwise refinance bonds issued prior to that date.


§140.609   Progress and final vouchers.

(a) Progress vouchers may be submitted for the Federal share of bonds retired or about to be retired, including eligible interest on Interstate Bond Issue Projects, the proceeds of which have actually been expended for the construction of the project.

(b) Upon completion of a bond issue project, a final voucher shall be submitted by the SHA. After final review, the SHA will be advised as to the total cost and Federal fund participation for the project.


§140.610   Conversion from bond issue to funded project status.

(a) At such time as the SHA elects to apply available apportioned Federal-aid funds to the retirement of bonds, including eligible interest earned and payable on Interstate Bond Projects, subject to available obligational authority, its claim shall be supported by appropriate certifications as follows:

I hereby certify that the following bonds, (list), the proceeds of which have been actually expended in the construction of bond issue projects authorized by title 23 U.S.C., section 122, (1) have been retired on -- -- -- , or (2) mature and are scheduled for retirement on -- -- -- , which is -- -- days in advance of the maturity date of -- -- -- .

Eligible interest claimed on Interstate Bond Projects shall be shown for each bond and the certification shall include the statement:

I also certify that interest earned and paid or payable for each bond listed has been determined from the date on and after which the respective bond proceeds were actually expended on the project.

(b) The SHA's request for full conversion of a completed projects), or partial conversion of an active or completed project(s), may be made by letter, inclusive of the appropriate certification as described in §140.610(a) making reference to any progress payments received or the final voucher(s) previously submitted and approved in accordance with §140.609.

(c) Approval of the conversion action shall be by the Division Administrator.

(d) The SHA's request for partial conversion of an active or completed bond issue project shall provide for: (1) Conversion to funded project status of the portion to be financed out of the balance of currently available apportioned funds, and (2) retention of the unfunded portion of the project in the bond program.

(e) Where the SHA's request involves the partial conversion of a completed bond issue project, payment of the Federal funds made available under the conversion action shall be accomplished through use of Form PR-20, Voucher for Work Performed under Provisions of the Federal-aid and Federal Highway Acts, prepared in the division office and appropriately cross-referenced to the Bond Issue Project final voucher previously submitted and approved. The final voucher will be reduced by the amount of the approved reimbursement.


§140.611   Determination of bond retirement.

Division Administrators shall be responsible for the prompt review of the SHA's records to determine that bonds issued to finance the projects and for which reimbursement has been made, including eligible bond interest expense, have been retired pursuant to the State's certification required by §140.610(a), and that such action is documented in the project file.


§140.612   Cash management.

By July 1 of each year the SHA will provide FHWA with a schedule, including the anticipated claims for reimbursement, of bond projects to be converted during the next two fiscal years. The data will be used by FHWA in determining liquidating cash required to finance such conversions.

Appendix to Subpart F -- Reimbursable Schedule for Converted "E" (Bond Issue) Projects (other than Interstate Projects)

------------------------------------------------------------------------
               Cumulative
                amount
              reimbursable
Time in months following conversion from ``E'' (bond   (percent of
issue) project to regular project         Federal
                funds
               obligated)
------------------------------------------------------------------------
1.........................................................       1
2.........................................................       2
3.........................................................       5
4.........................................................       9
5.........................................................      13
6.........................................................      18
7.........................................................      23
8.........................................................      29
9.........................................................      34
10........................................................      39
11........................................................      44
12........................................................      49
13........................................................      54
14........................................................      58
15........................................................      61
16........................................................      64
17........................................................      67
18........................................................      70
19........................................................      73
20........................................................      75
21........................................................      77
22........................................................      79
23........................................................      81
24........................................................      83
25........................................................      85
26........................................................      87
27........................................................      89
28........................................................      91
29........................................................      93
30........................................................      94
31........................................................      95
32........................................................      96
34........................................................      97
35........................................................      99
36........................................................      100
------------------------------------------------------------------------


Subpart G [Reserved]

Subpart H -- State Highway Agency Audit Expense


Source: 49 FR 45578, Nov. 19, 1984, unless otherwise noted.


§140.801   Purpose.

To establish the reimbursement criteria for Federal participation in project related audit expenses.


§140.803   Policy.

Project related audits performed in accordance with generally accepted auditing standards (as modified by the Comptroller General of the United States) and applicable Federal laws and regulations are eligible for Federal participation. The State highway agency (SHA) may use other State, local public agency, and Federal audit organizations as well as licensed or certified public accounting firms to augment its audit force.


§140.805   Definitions.

(a) Project related audits. Audits which directly benefit Federal-aid highway projects. Audits performed in accordance with the requirements of 23 CFR part 12, audits of third party contract costs, and other audits providing assurance that a recipient has complied with FHWA regulations are all considered project related audits. Audits benefiting only nonfederal projects, those performed for SHA management use only, or those serving similar nonfederal purposes are not considered project related.

(b) Third party contract costs. Project related costs incurred by railroads, utilities, consultants, governmental instrumentalities, universities, nonprofit organizations, construction contractors (force account work), and organizations engaged in right-of-way studies, planning, research, or related activities where the terms of a proposal or contract (including lump sum) necessitate an audit. Construction contracts (except force account work) are not included in this group.


§140.807   Reimbursable costs.

(a) Federal funds may be used to reimburse an SHA for the following types of project related audit costs:

(1) Salaries, wages, and related costs paid to public employees in accordance with subpart G of this part,

(2) Payments by the SHA to any Federal, State, or local public agency audit organization, and

(3) Payments by the SHA to licensed or certified public accounting firms.

(b) Audit costs incurred by an SHA shall be equitably distributed to all benefiting parties. The portion of these costs allocated to the Federal-Aid Highway Program which are not directly related to a specific project or projects shall be equitably distributed, as a minimum, to the major FHWA funding categories in that State.

Subpart I -- Reimbursement for Railroad Work


Source: 40 FR 16057, Apr. 9, 1975, unless otherwise noted.


§140.900   Purpose.

The purpose of this subpart is to prescribe policies and procedures on reimbursement to the States for railroad work done on projects undertaken pursuant to the provisions of 23 CFR part 646, subpart B.


§140.902   Applicability.

This subpart, and all references hereinafter made to "projects," applies to Federal-aid projects involving railroad facilities, including projects for the elimination of hazards of railroad-highway crossings, and other projects which use railroad properties or which involve adjustments required by highway construction to either railroad facilities or facilities that are jointly owned or used by railroad and utility companies.


§140.904   Reimbursement basis.

(a) General. On projects involving the elimination of hazards of railroad-highway crossings, and on other projects where a railroad company is not obligated to move or to change its facilities at its own expense, reimbursement will be made for the costs incurred by the State in making changes to railroad facilities as required in connection with a Federal-aid highway project, in accordance with the provisions of this subpart.

(b) Eligibility. To be eligible, the costs must be:

(1) For work which is included in an approved statewide transportation improvement program.

(2) Incurred subsequent to the date of authorization by the Federal Highway Administration (FHWA),

(3) Incurred in accordance with the provisions of 23 CFR, part 646, subpart B, and

(4) Properly attributable to the project.

[40 FR 16057, Apr. 9, 1975, as amended at 53 FR 18276, May 23, 1988; 62 FR 45328, Aug. 27, 1997]



§140.906   Labor costs.

(a) General. (1) Salaries and wages, at actual or average rates, and related expenses paid by a company to individuals, for the time they are working on the project, are reimbursable when supported by adequate records. This shall include labor costs associated with preliminary engineering, construction engineering, right-of-way, and force account construction.

(2) Salaries and expenses paid to individuals who are normally part of the overhead organization of the company may be reimbursed for the time they are working directly on the project, such as for accounting and bill preparation, when supported by adequate records and when the work performed by such individuals is essential to the project and could not have been accomplished as economically by employees outside the overhead organization.

(3) Amounts paid to engineers, architects and others for services directly related to projects may be reimbursed.

(b) Labor surcharges. (1) Labor surcharges include worker compensation insurance, public liability and property damage insurance, and such fringe benefits as the company has established for the benefit of its employees. The cost of labor surcharges will be reimbursed at actual cost to the company or a company may, at its option, use an additive rate or other similar technique in lieu of actual costs provided that (i) the rate is based on historical cost data of the company, (ii) such rate is representative of actual costs incurred, (iii) the rate is adjusted at least annually taking into consideration known anticipated changes and correcting for any over or under applied costs for the preceding period, and (iv) the rate is approved by the SHA and FHWA.

(2) Where the company is a self-insurer there may be reimbursement:

(i) At experience rates properly developed from actual costs, not to exceed the rates of a regular insurance company for the class of employment covered, or

(ii) At the option of the company, a fixed rate of 8 percent of direct labor costs for worker compensation and public liability and property damage insurance together.

[40 FR 16057, Apr. 9, 1975, as amended at 47 FR 33955, Aug. 5, 1982; 56 FR 56578, Nov. 6, 1991]



§140.907   Overhead and indirect construction costs.

(a) A State may elect to reimburse the railroad company for its overhead and indirect construction costs.

(b) The FHWA will participate in these costs provided that:

(1) The costs are distributed to all applicable work orders and other functions on an equitable and uniform basis in accordance with generally accepted accounting principles;

(2) The costs included in the distribution are limited to costs actually incurred by the railroad;

(3) The costs are eligible in accordance with the Federal Acquisition Regulation (48 CFR), part 31, Contract Cost Principles and Procedures, relating to contracts with commercial organizations;

(4) The costs are considered reasonable;

(5) Records are readily available at a single location which adequately support the costs included in the distribution, the method used for distributing the costs, and the basis for determining additive rates;

(6) The rates are adjusted at least annually taking into consideration any overrecovery or underrecovery of costs; and

(7) The railroad maintains written procedures which assure proper control and distribution of the overhead and indirect construction costs.

[53 FR 18276, May 23, 1988]



§140.908   Materials and supplies.

(a) Procurement. Materials and supplies, if available, are to be furnished from company stock, except they may be obtained from other sources near the project site when available at less cost. Where not available from company stock, they may be purchased either under competitive bids or existing continuing contracts, under which the lowest available prices are developed. Minor quantities and proprietary products are excluded from these requirements. The company shall not be required to change its existing standards for materials used in permanent changes to its facilities.

(b) Costs. (1) Materials and supplies furnished from company stock shall be billed at current stock price of such new or used material at time of issue.

(2) Materials and supplies not furnished from company stock shall be billed at actual costs to the company delivered to the point of entry on the railroad company's line nearest the source of procurement.

(3) A reasonable cost of plant inspection and testing may be included in the costs of materials and supplies where such expense has been incurred. The computation of actual costs of materials and supplies shall include the deduction of all offered discounts, rebates and allowances.

(c) Materials recovered. (1) Materials recovered from temporary use and accepted for reuse by the company shall be credited to the project at prices charged to the job, less a consideration for loss in service life at 10 percent for rails, angle bars, tie plates and metal turnout materials and 15 percent for all other materials. Materials recovered from the permanent facility of the company that are accepted by the company for return to stock shall be credited to the project at current stock prices of such used material.

(2) Materials recovered and not accepted for reuse by the company, if determined to have a net sale value, shall be sold by the State or railroad following an opportunity for State inspection and appropriate solicitation for bids, to the highest bidder; or if the company practices a system of periodic disposal by sale, credit to the project shall be at the going prices supported by the records of the company. Where applicable, credit for materials recovered from the permanent facility in length or quantities in excess of that being placed should be reduced to reflect any increased cost of railroad operation resulting from the adjustment.

(d) Removal costs. Federal participation in the costs of removing, salvaging, transporting, and handling recovered materials will be limited to the value of materials recovered, except where FHWA approves additional measures for restoration of affected areas as required by the physical construction or by reason of safety or aesthetics.

(e) Handling costs. The actual and direct costs of handling and loading out of materials and supplies at and from company stores or material yards and of unloading and handling of recovered materials accepted by the company at its stores or material yards, are reimbursable. At the option of the company, 5 percent of the amounts billed for the materials and supplies which are issued from company stores and material yards will be reimbursable in lieu of actual costs.

(f) Credit losses. On projects where a company actually suffers loss by application of credits, the company shall have the opportunity of submitting a detailed statement of such loss as a basis for further adjustment.


§140.910   Equipment.

(a) Company owned equipment. Cost of company-owned equipment may be reimbursed for the average or actual cost of operation, light and running repairs, and depreciation, or at industry rates representative of actual costs as agreed to by the railroad, SHA, and FHWA. Reimbursement for company-owned vehicles may be made at average or actual costs or at rates of recorded use per mile which are representative of actual costs and agreed to by the company, SHA, and FHWA.

(b) Other equipment. Where company owned equipment is not available, reimbursement will be limited to the amount of rental paid (1) to the lowest qualified bidder, (2) under existing continuing contracts at reasonable cost, or (3) as an exception, by negotiation where (b) (1) and (2) are impractical due to project location or schedule.

[40 FR 16057, Apr. 9, 1975, as amended at 47 FR 33955, Aug. 5, 1982]



§140.912   Transportation.

(a) Employees. The company's cost of necessary employee transportation and subsistence directly attributable to the project, which is consistent with overall policy of the company, is reimbursable.

(b) Materials, supplies, and equipment. The most economical movement of materials, supplies and equipment to the project and necessary return to storage, including the associated costs of loading and unloading equipment, is reimbursable. Transportation by a railroad company over its own lines in a revenue train is reimbursable at average or actual costs, at rates which are representative of actual costs, or at rates which the company charges its customers for similar shipments provided the rate structure is documented and available to the public. These rates are to be agreed to by the company, SHA, and FHWA. No charge will be made for transportation by work train other than the operating expenses of the work train. When it is more practicable or more economical to move equipment on its own wheels, reimbursement may be made at average or actual costs or at rates which are representative of actual costs and are agreed to by the railroad, SHA, and FHWA.

[40 FR 16057, Apr. 9, 1975, as amended at 47 FR 33955, Aug. 5, 1982]



§140.914   Credits for improvements.

(a) Credit shall be made to the project for additions or improvements which provide for higher quality or increased service capability of the operating facility and which are provided solely for the benefit of the company.

(b) Where buildings and other depreciable structures of a company which are integral to operation of rail traffic must be replaced, credit shall be made to the project as set forth in 23 CFR 646.216(c)(2).

(c) No credit is required for additions or improvements which are:

(1) Necessitated by the requirements of the highway project.

(2) Replacements which, although not identical, are of equivalent standard.

(3) Replacements of devices or materials no longer regularly manufactured and the next highest grade or size is used.

(4) Required by governmental and appropriate regulatory commission requirements.


§140.916   Protection.

The cost of essential protective services which, in the opinion of a railroad company, are required to ensure safety to railroad operations during certain periods of the construction of a project, is reimbursable provided an item for such services is incorporated in the State-railroad agreement or in a work order issued by the State and approved by FHWA.


§140.918   Maintenance and extended construction.

The cost of maintenance and extended construction is reimbursable to the extent provided for in 23 CFR 646.216(f)(4), and where included in the State-Railroad Agreement or otherwise approved by the State and FHWA.


§140.920   Lump sum payments.

Where approved by FHWA, pursuant to 23 CFR 646.216(d)(3), reimbursement may be made as a lump sum payment, in lieu of actual costs.


§140.922   Billings.

(a) After the executed State-Railroad Agreement has been approved by FHWA, the company may be reimbursed on progress billings of incurred costs. Costs for materials stockpiled at the project site or specifically purchased and delivered to the company for use on the project may be reimbursed on progress billings following approval of the executed State-Railroad Agreement or the written agreement under 23 CFR 646.218(c).

(b) The company shall provide one final and complete billing of all incurred costs, or of the agreed-to lump sum, within one year following completion of the reimbursable railroad work. Otherwise, previous payments to the company may be considered final, except as agreed to between the SHA and the railroad.

(c) All company cost records and accounts relating to the project are subject to audit by representatives of the State and/or the Federal Government for a period of three years from the date final payment has been received by the company.

(d) A railroad company must advise the State promptly of any outstanding obligation of the State's contractor for services furnished by the company such as protective services.

[40 FR 16057, Apr. 9, 1975, as amended at 40 FR 29712, July 15, 1975; 62 FR 45328, Aug. 27, 1997]






PART 172 -- ADMINISTRATION OF ENGINEERING AND DESIGN RELATED SERVICE CONTRACTS



Subpart A -- Procurement Procedures


   Sec.
172.1   Purpose and applicability.
172.3   Definitions.
172.5   General principles.
172.7   Methods of procurement.
172.9   Compensation.
172.11   Contract modifications.
172.13   Monitoring the contract work.
172.15   Alternate procedures.

Subpart B -- Private Sector Involvement Program

172.21   Purpose and applicability.
172.23   Evaluation and selection.
172.25   Funding.

Authority: 23 U.S.C. 112(b), 114(a), 302, 315, and 402; 49 CFR 1.48(b) and 18; 48 CFR 12 and 31; 41 U.S.C. 253 and 259; and sec. 1060, Pub. L. 102-240, 105 Stat. 1914, 2003 (1991).

Source: 56 FR 19802, Apr. 30, 1991, unless otherwise noted.

Subpart A -- Procurement Procedures



§172.1   Purpose and applicability.

(a) To prescribe policies and procedures for contracting to ensure that a qualified consultant is obtained through an equitable selection process, and that prescribed work is properly accomplished in a timely manner, at a reasonable cost.

(b) This regulation applies to all engineering and design related service contracts financed with Federal-aid highway funds. Agencies with approved Certification Acceptance Plans (CA), Secondary Road Plans (SRP) and/or Combined Road Plans (CRP) shall submit for the Federal Highway Administration's (FHWA) approval, procedures consistent with this regulation if they intend to utilize Federal-aid highway funds for any of the above contract types. The use of procedures codified in State statutes to select consultant firms is also acceptable. Other types of negotiated contracts should be administered under the requirements of the common grant management rule, 49 CFR 18.


§172.3   Definitions.

As used in this part:

Competitive negotiation. Any form of negotiations that utilizes, (1) qualifications-based procedures complying with title IX of the Federal Property and Administrative Services Act of 1949 (Pub. L. 92-582, 86 Stat. 1278 (1972)), (2) equivalent State qualifications-based procedures or (3) a formal procedure permitted by State statute.

Consultant. The individual or firm providing engineering and design related services as a party to the contract.

Contract modification. An agreement modifying the existing contract, such as an agreement to accomplish work beyond the scope of the original contract.

Contracting agency. The State highway agency or local governmental agencies which have responsibility for the procurement.

Engineering and design services. Program management, construction management, feasibility studies, preliminary engineering, design, engineering, surveying, mapping, or architectural related services.

Extra work. Any services or actions required of the consultant above and beyond the obligations of the original or modified contract.

Fixed fee. A dollar amount established to cover the consultant's profit and business expenses not allocable to overhead.

Prenegotiation audit. An examination of a consultant's records made in accordance with generally accepted auditing standards.

Private sector engineering and design firms. Any individual or private firm (including small business concerns and small businesses owned and controlled by socially and economically disadvantaged individuals as defined in 49 CFR part 23) contracting with a State to provide engineering and design services.

Scope of work. All services and actions required of the consultant by the obligations of the contract.

[56 FR 19802, Apr. 30, 1991, as amended at 59 FR 64848, Dec. 16, 1994]



§172.5   General principles.

(a) Need for consultant services in management roles. When Federal-aid highway funds participate in the contract, the contracting agency shall receive approval from the FHWA before hiring a consultant to act in a "management" role for the contracting agency. This concept should be limited to situations where unique or unusual circumstances exist and where the contracting agency has provided adequate justification to explain its reason for using a consultant in this role and the reason it cannot perform the work.

(b) Written procedures. The contracting agency shall prepare written procedures for each method of procurement it proposes to utilize. These procedures and all revisions shall be approved by the FHWA and describe, as appropriate to the particular method of procurement, each step used:

(1) In preparing a scope of work, evaluation factors and cost estimate for selecting a consultant,

(2) In soliciting proposals from prospective consultants,

(3) In the evaluation of proposals and the ranking/selection of a consultant,

(4) In negotiation of the reimbursement to be paid to the selected consultant,

(5) In monitoring the consultant's work and in preparing a consultant's performance evaluation when completed, and

(6) In determining the extent to which the consultant, who is responsible for the professional quality, technical accuracy, and coordination of services, may be reasonably liable for costs resulting from errors or deficiencies in design furnished under its contract.

(c) Prenegotiation audits. The contracting agencies shall prepare prenegotiation audits to provide the necessary data to assure that the consultant has an acceptable accounting system, adequate and proper justification of the various rates charged to perform work and is aware of the FHWA's cost eligibility and documentation requirements.

(1) Prenegotiation audits and the resultant audit opinions are required for all contracts expected to exceed $250,000 and for contracts of less than $250,000 where:

(i) There is insufficient knowledge of the consultant's accounting system,

(ii) There is previous unfavorable experience regarding the reliability of the consultant's accounting system, or

(iii) The contract involves procurement of new equipment or supplies for which cost experience is lacking.

(2) The use of an independent audit, an audit performed by another State/Federal agency or an audit performed by another local governmental agency is acceptable if the information is current and of sufficient detail.

(3) Prenegotiation audits may be waived when sufficient audited consultant data is available to permit reasonable comparisons with the cost proposal.

(d) State responsibility in local agency contracts. The State highway agency shall ensure that procurement actions by or through other State agencies or local agencies comply with this regulation. When Federal-aid highway funds participate in the contract, a local agency shall use the same procedures as used by the State to administer contracts not under CA, the SRP or the CRP. These contracts shall be subject to the prior approval of the State highway agency and the FHWA. Nothing herein shall be taken as relieving the State of its responsibility under Federal-aid highway laws and regulations for the work to be performed under any agreements entered into by a local agency.

(e) Disadvantaged Business Enterprise (DBE) program. The contracting agency shall give consideration to DBE firms in the procurement of engineering and design related service contracts subject to 23 U.S.C. 112(b)(2).

(f) Contractual responsibilities. The contracting agency or State highway agency shall be responsible for the settlement of all contractual/administrative issues. All settlements shall be reviewed and approved by the FHWA before Federal-aid highway funds can participate in any additional costs.


§172.7   Methods of procurement.

This regulation addresses three methods of procurement for the hiring of consultants to perform engineering and design related services specified in 23 U.S.C. 112(b)(2). These methods are: competitive negotiations which follows qualifications-based selection procedures or another selection procedure permitted by State statutes; small purchase procedures for small dollar value contracts; and non-competitive negotiations where specific conditions exist allowing negotiations to take place with a single firm.

(a) Competitive negotiation. Competitive negotiation should be used for the selection of a consultant to provide engineering and design related services. The following procedures shall apply to the competitive negotiation process:

(1) Scope, evaluation factors and cost estimate development. The contracting agency shall prepare:

(i) A scope of work before issuing a Request for Proposal that reflects a clear, accurate, and detailed description of the technical requirements for the services to be rendered and a list identifying the evaluation factors and their relative importance.

(ii) A detailed cost estimate, except for contracts awarded under small purchase procedures, with an appropriate breakdown of specific types of labor required, work hours, and an estimate of the consultant's fixed fee (considering the risk and complexity of the project) for use during negotiations.

(2) Soliciting proposals -- (i) Solicitation. The solicitation process shall be by advertisement (project, task or service), by mailing Requests for Proposals to certified/prequalified consultants, or any other method that ensures qualified in-State and out-of-State consultants are given the opportunity to be considered for award of a contract. It shall include a process where either:

(A) General interest is solicited for performing the work; responding consultants are ranked based on an evaluation of their qualification statements (submitted with their letters of interest or on file with the contracting agency); and proposals are requested from three or more firms starting with the highest ranked firm, or

(B) Proposals are solicited from all consultants that are interested in being considered for the work.

(ii) Request for proposal. The request for proposal shall:

(A) Provide a description of the scope of work and identification of the evaluation factors including their relative importance as included in paragraph (a)(1) of this section.

(B) Specify the method(s) of payment (lump sum, cost plus a fixed fee, cost per unit of work, or specific rate(s) of compensation).

(C) Request the submission of a proposal. Priced proposals may be used in the selection phase if allowed for under a State statute, but shall not be used in the selection phase when qualifications-based procedures are used.

(D) Allow sufficient time for the consultant to prepare and submit the proposal.

(3) Analysis and selection -- (i) The consultants' proposals, containing the information required by paragraph (a)(2) of this section, shall be evaluated and ranked by the contracting agency. This process shall include an analysis of the proposals in comparison to the evaluation factors. In addition, the consultants' applicable work experience, present workload, past performance, staffing capabilities, etc., should be evaluated and included in the ranking process.

(ii) The award of engineering and design related services shall:

(A) Utilize qualifications-based procedures that either comply with the provisions of Title IX of the Federal Property and Administrative Services Act of 1949 (Pub. L. 92-582, 86 Stat. 1278 (1972), as amended) or utilize equivalent State qualifications-based procedures, or

(B) Utilize a formal procurement procedure that is established by State statute or is subsequently established by State statute.

(iii) The contracting agency shall retain acceptable documentation of the proposal, evaluation and selection of the consultant. Records shall be maintained in accordance with the provisions of 49 CFR 18.42.

(4) Negotiation responsibilities. (i) The negotiator shall use all resources available to conduct effective negotiations, including but not limited to, the refined scope of work, the evaluation factors and their relative importance, the agency's cost estimate as required in paragraph (a)(1) of this section and the audit opinion issued as a result of the prenegotiation audit required in §172.5(c) of this part.

(ii) The negotiator shall separately negotiate the dollar amounts for elements of cost and a fixed fee except for services normally negotiated on a per unit (includes costs and fees) cost.

(iii) The contracting agency shall maintain records of negotiations to document negotiation activities and set forth the resources considered by the negotiator. Records shall be maintained in accordance with the provisions of 49 CFR 18.42.

(5) Execution of contracts. The proposed contract including the agreed upon cost figures shall be submitted to the FHWA for approval prior to its execution.

(b) Small purchases. Contracting agencies may use small purchase procedures for the procurement of engineering and design related services when the contract cost does not exceed $25,000.

(c) Noncompetitive negotiation. Noncompetitive negotiation may be used to obtain engineering and design related services when the award of a contract is not feasible under small purchase or competitive negotiation procedures. The contracting agency shall submit justification and receive approval from the FHWA before using this form of contracting when Federal-aid highway funds are used in the contract.

(1) Circumstances under which a contract may be awarded by noncompetitive negotiation are limited to the following:

(i) The service is available only from a single source, or

(ii) There is an emergency which will not permit the time necessary to conduct competitive negotiations, or

(iii) After solicitation of a number of sources, competition is determined inadequate.

(2) The contracting agency shall comply with the following procedures for noncompetitive negotiations:

(i) Establish a process to determine when noncompetitive negotiation will be used,

(ii) Develop an adequate scope of work, evaluation factors and cost estimate as required in paragraph (a)(1) of this section,

(iii) Conduct negotiations as required in paragraph (a)(4) of this section, and

(iv) Submit the proposed contract and cost estimate to the FHWA for approval.


§172.9   Compensation.

(a) Contracting agencies may establish cost principles for determining the reasonableness and allowability of costs. Federal reimbursement shall be limited to the Federal share of the costs allowable under the cost principles in 48 CFR part 31 (Federal Acquisition Regulations). Any references included in 48 CFR part 31 to other parts of 48 CFR do not apply to these contracts.

(b) Applicable cost principles shall be referenced in each contractual document.

(c) Methods of payment. (1) The method of payment to compensate the consultant for all work required shall be set forth in the original contract and in any contract modifications thereto. It may be a single method for all work or may involve different methods for different elements of work. The methods of payment which shall be used are: lump sum, cost plus fixed fee, cost per unit of work or specific rates of compensation.

(2) Compensation based on cost plus a percentage of cost or percentage of construction cost shall not be used.

(3) When the method of payment is other than a lump sum, the contract shall specify a maximum amount payable which shall not be exceeded unless adjusted by a contract modification.

(4) The lump sum method shall not be used to compensate a consultant for construction engineering and inspection services except when the agency has established the extent, scope, complexity, character and duration of the work to be required to a degree that fair and reasonable compensation including a fixed fee can be determined.

(d) Fixed fees. (1) The determination of the amount of the fixed fee shall take into account the size, complexity, duration, and degree of risk involved in the work. The establishment of the fixed fee shall be project specific.

(2) Fixed fees normally range from 6 to 15 percent of the total direct and indirect cost. Subject to the approval of the FHWA, a fixed fee over 15 percent may be justified when exceptional circumstances exist.


§172.11   Contract modifications.

(a) Contract modifications are required for any modification in the terms of the original contract that change the cost of the contract; significantly change the character, scope, complexity, or duration of the work; or significantly change the conditions under which the work is required to be performed.

(b) A contract modification shall clearly outline the changes made and determine a method of compensation. FHWA approval of contract modifications shall be obtained prior to beginning the work except as discussed in paragraph (d) of this section.

(c) Overruns in the costs of the work shall not warrant an increase in the fixed fee portion of a cost plus fixed fee contract. Significant changes to the Scope of Work may require adjustment of the fixed fee portion in a cost plus fixed fee contract or in a lump sum contract.

(d) In unusual circumstances, the consultant may be authorized to proceed with work prior to agreement on the amount of compensation and execution of the contract modification, provided the FHWA has previously approved the work and has concurred that additional compensation is warranted.


§172.13   Monitoring the contract work.

(a) A public employee qualified to ensure that the work being pursued is complete, accurate and consistent with the terms, conditions, and specifications of the contract shall be in responsible charge of each contract or project. The employee's responsibilities include:

(1) Scheduling and attending progress meetings with the consultant and being involved in decisions leading to change orders or supplemental agreements,

(2) Being familiar with the qualifications and responsibilities of the consultant's staff,

(3) Visiting the project and/or consultant's offices on a frequency that is commensurate with the magnitude, complexity and type of work. This includes being aware of the day-to-day operations for Construction Engineering Service contracts, and

(4) Assuring that costs billed are consistent with the acceptability and progress of the consultant's work.

(b) A final performance evaluation report, except for contracts awarded under small purchase procedures shall be prepared by the public employee in responsible charge of the contract and shall be submitted to the State highway agency's contracting office. The report should include, but not be limited to, an evaluation of such items as timely completion of work, conformance with contract cost and the quality of work. A copy of the report shall be sent to the firm for its review and/or comments and any written comments submitted to the contracting agency by the firm shall be attached to the final report.

(c) Contracting agencies should include a clause in engineering contracts requiring the consultant to perform such additional work as may be necessary to correct errors in the work required under the contract without undue delays and without additional cost to the owner. However, in general, a consultant should not be held responsible for additional costs in subsequent related construction resulting from errors or omissions which are not a result of gross negligence or carelessness.


§172.15   Alternate procedures.

(a) This is a process whereby the contracting agency can be authorized to substitute its contract review and approval actions for those of the FHWA. Before a contracting agency can operate under the alternate procedures concept, it shall submit procedures to the FHWA that include the following:

(1) A formal request to operate under the alternate procedure concept.

(2) The written procedures, as required by §172.5(b) of this part, it will follow, and

(3) A statement signed by the chief administrative officer of the contracting agency certifying that it will conform with its written procedures, the provisions of this regulation, and all applicable Federal and State laws and administrative requirements.

(b) The alternate procedures and all revisions shall be approved by the FHWA.

(c) The alternate procedures concept may apply to all Federal-aid highway funded contracts.

(d) A copy of the original executed contract and all contract modifications shall be submitted to the FHWA.

Subpart B -- Private Sector Involvement Program


Source: 59 FR 64848, Dec. 16, 1994, unless otherwise noted.


§172.21   Purpose and applicability.

(a) The purpose of this subpart is to implement a program to encourage States to contract for engineering and design services with the private sector whenever such contracts would be cost effective.

(b) This subpart applies to all engineering and design services contracts financed with Federal-aid highway funds.


§172.23   Evaluation and selection.

(a) When funds are appropriated for this program, the FHWA will invite States to submit applications to participate in the program. The FHWA will use the applications to make the program allocations under the program.

(b) The FHWA will make a comparison of the applicants based on the amount of Federal-aid highway funds each State has expended on contracts for engineering and design services. In assessing the amount of funds a State spent in procuring engineering and design services, the FHWA will also consider the amounts expended by States on 100 percent State-funded engineering and design services contracts involving projects to be constructed with Federal-aid highway funds to the extent the State provides such information with its application.

(c) The FHWA will select not less than three States each fiscal year to receive funds under this program.

(1) Selection of the States to receive funding under this program will be made by determining which States were the most effective in increasing the percentage of funds expended on engineering and design services contracts in the year preceding the fiscal year in which funds are to be allocated. In the selection process, the FHWA will evaluate each State's program of contracting for engineering and design services. The evaluation will primarily consider such information as the amount and percentage of Federal-aid highway funds and State funds expended on engineering and design services contracts, the number of contracts awarded for such services, the relative size of the State's Federal-aid highway program and the increases in use of private sector firms during the preceding year and the preceding five years.

(2) Upon the FHWA's request for applications, each State interested in being considered should submit its application through its appropriate FHWA Division Office. The application may be in letter form and should include current information on the extent of the State's use of consultants for engineering and design on Federal-aid highway projects. In addition, the State may provide data on the amount of 100 percent State-funded engineering and design services contracts involving projects to be built with Federal-aid highway funds and any other information demonstrating the State's effectiveness in increasing the percentage of funds expended on engineering and design services contracts in the past five years.


§172.25   Funding.

(a) Funds received by a State under this program may only be used for awarding engineering and design services contracts with the private sector. These contracts shall carry out services and activities eligible for Federal-aid funding under title 23, United States Code.

(b) The Federal share of any project obligated with funds allocated under this program shall be the same as the Federal share applicable to the type of work or project being developed or the system on which the project is located. Funds allocated under this program shall remain available until expended.

(c) Funds will be allocated to the States each fiscal year from 1995 through 1997 to the extent funds are appropriated.




PART 180 -- CREDIT ASSISTANCE FOR SURFACE TRANSPORTATION PROJECTS


Authority: Secs. 1501 et seq., Pub. L. 105-178, 112 Stat. 107, 241, as amended; 23 U.S.C. 181-189 and 315; 49 CFR 1.48.

Source: 64 FR 29750, June 2, 1999, unless otherwise noted.


§180.1   Cross-reference to credit assistance.

The regulations in 49 CFR part 80 shall be followed in complying with the requirements of this part. Title 49 CFR part 80 implements the Transportation Infrastructure Finance and Innovation Act of 1998, secs. 1501 et seq., Pub. L. 105-178, 112 Stat. 107, 241.




PART 190 -- INCENTIVE PAYMENTS FOR CONTROLLING OUTDOOR ADVERTISING ON THE INTERSTATE SYSTEM


Sec.
190.1   Purpose.
190.3   Agreement to control advertising.
190.5   Bonus project claims.
190.7   Processing of claims.

Authority: 23 U.S.C. 131(j) and 315; 49 CFR 1.48(b).

Source: 43 FR 42742, Sept. 21, 1978, unless otherwise noted.


§190.1   Purpose.

The purpose of this regulation is to prescribe project procedures for making the incentive payments authorized by 23 U.S.C. 131(j).


§190.3   Agreement to control advertising.

To qualify for the bonus payment, a State must have entered into an agreement with the Secretary to control outdoor advertising. It must fulfill, and must continue to fulfill its obligations under such agreement consistent with 23 CFR 750.101.


§190.5   Bonus project claims.

(a) The State may claim payment by submitting a form PR-20 voucher, supported by strip maps which identify advertising control limits and areas excluded from the claim and form FHWA-1175, for the one-half percent bonus claim.

(b) The bonus payment computation is based on projects or portions thereof for which (1) the section of highway on which the project is located has been opened to traffic, and (2) final payment has been made. A bonus project may cover an individual project, a part thereof, or a combination of projects, on a section of an Interstate route.

(c) The eligible system mileage to be shown for a bonus project is that on which advertising controls are in effect. The eligible system mileage reported in subsequent projects on the same Interstate route section should cover only the additional system mileage not previously reported. Eligible project cost is the total participating cost (State and Federal share of approved preliminary engineering (PE), right-of-way (R-O-W), and construction) exclusive of any ineligible costs. The amount of the bonus payment is to be based on the eligible total costs of the supporting projects included in each claim.

(d) Progress vouchers for route sections on which additional one-half percent bonus payments are to be claimed are to be so identified, and the final claim for each route section is to be identified as the final voucher.


§190.7   Processing of claims.

Audited and approved PR-20 vouchers with form FHWA-1175 shall be forwarded to the regional office for submission to the Finance Division, Washington Headquarters, for payment. The associated strip maps shall be retained with the division office copies of the PR-20 vouchers.




PART 192 -- DRUG OFFENDER'S DRIVER'S LICENSE SUSPENSION


Sec.
192.1   Scope.
192.2   Purpose.
192.3   Definitions.
192.4   Adoption of drug offender's driver's license suspension.
192.5   Certification requirements.
192.6   Period of availability of withheld funds.
192.7   Apportionment of withheld funds after compliance.
192.8   Period of availability of subsequently apportioned funds.
192.9   Effect of noncompliance.
192.10   Procedures affecting States in noncompliance.

Authority: 23 U.S.C. 159 and 315.

Source: 57 FR 35999, Aug. 12, 1992, unless otherwise noted. Redesignated at 60 FR 50100, Sept. 28, 1995.


§192.1   Scope.

This part prescribes the requirements necessary to implement 23 U.S.C. §159, which encourages States to enact and enforce drug offender's driver's license suspensions.


§192.2   Purpose.

The purpose of this part is to specify the steps that States must take in order to avoid the withholding of Federal-aid highway funds for noncompliance with 23 U.S.C. 159.


§192.3   Definitions.

As used in this part:

(a) Convicted includes adjudicated under juvenile proceedings.

(b) Driver's license means a license issued by a State to any individual that authorizes the individual to operate a motor vehicle on highways.

(c) Drug offense means:

(1) The possession, distribution, manufacture, cultivation, sale, transfer, or the attempt or conspiracy to possess, distribute, manufacture, cultivate, sell, or transfer any substance the possession of which is prohibited under the Controlled Substances Act, or

(2) The operation of a motor vehicle under the influence of such a substance.

(d) Substance the possession of which is prohibited under the Controlled Substances Act or substance means a controlled or counterfeit chemical, as those terms are defined in subsections 102 (6) and (7) of the Comprehensive Drug Abuse Prevention and Control Act of 1970 (21 U.S.C. 802 (6) and (7) and listed in 21 CFR 1308.11-.15.

[57 FR 35999, Aug. 12, 1992; 58 FR 62415, Nov. 26, 1993; 59 FR 39256, Aug. 2, 1994]



§192.4   Adoption of drug offender's driver's license suspension.

(a) The Secretary shall withhold five percent of the amount required to be apportioned to any State under each of sections 104(b)(1), 104(b)(3), and 104(b)(5) of title 23 of the United States Code on the first day of fiscal years 1994 and 1995 if the States does not meet the requirements of this section on that date.

(b) The Secretary shall withhold ten percent of the amount required to be apportioned to any State under each of sections 104(b)(1), 104(b)(3), and 104(b)(5) of title 23 of the United States Code on the first day of fiscal year 1996 and any subsequent fiscal year if the State does not meet the requirements of this section on that date.

(c) A State meets the requirements of this section if:

(1) The State has enacted and is enforcing a law that requires in all circumstances, or requires in the absence of compelling circumstances warranting an exception:

(i) The revocation, or suspension for at least 6 months, of the driver's license of any individual who is convicted, after the enactment of such law, of

(A) Any violation of the Controlled Substances Act, or

(B) Any drug offense, and

(ii) A delay in the issuance or reinstatement of a driver's license to such an individual for at least 6 months after the individual otherwise would have been eligible to have a driver's license issued or reinstated if the individual does not have a driver's license, or the driver's license of the individual is suspended, at the time the individual is so convicted, or

(2) The Governor of the State:

(i) Submits to the Secretary no earlier than the adjournment sine die of the first regularly scheduled session of the State's legislature which begins after November 5, 1990, a written certification stating that he or she is opposed to the enactment or enforcement in the State of a law described in paragraph (c)(1) of this section relating to the revocation, suspension, issuance, or reinstatement of driver's licenses to convicted drug offenders; and

(ii) Submits to the Secretary a written certification that the legislature (including both Houses where applicable) has adopted a resolution expressing its opposition to a law described in paragraph (c)(1) of this section.

(d) A State that makes exceptions for compelling circumstances must do so in accordance with a State law, regulation, binding policy directive or Statewide published guidelines establishing the conditions for making such exceptions and in exceptional circumstances specific to the offender.


§192.5   Certification requirements.

(a) Each State shall certify to the Secretary of Transportation by April 1, 1993 and by January 1 of each subsequent year that it meets the requirements of 23 U.S.C. 159 and this regulation.

(b) If the State believes it meets the requirements of 23 U.S.C. 159 and this regulation on the basis that it has enacted and is enforcing a law that suspends or revokes the driver's license of drug offenders, the certification shall contain:

(1) A statement by the Governor of the State that the State has enacted and is enforcing a Drug Offender's Driver's License Suspension law that conforms to 23 U.S.C. 159(a)(3)(A). The certifying statement may be worded as follows: I, (Name of Governor), Governor of the (State or Commonwealth) of ______, do hereby certify that the (State or Commonwealth) of ______, has enacted is enforcing a Drug Offender's Driver's License Suspension law that conforms to section 23 U.S. C. 159(a)(3)(A).

(2) Until a State has been determined to be in compliance with the requirements of 23 U.S.C. 159 and this regulation, the certification shall include also:

(i) A copy of the State law, regulation, or binding policy directive implementing or interpreting such law or regulation relating to the suspension, revocation, issuance or reinstatement or driver's licenses of drug offenders, and

(ii) A statement describing the steps the State is taking to enforce its law with regard to within State convictions, out-of-State convictions, Federal convictions and juvenile adjudications. The statement shall demonstrate that, upon receiving notification that a State driver has been convicted of a within State, out-of-State or Federal conviction or juvenile adjudication, the State is revoking, suspending or delaying the issuance of that drug offender's driver's license; and that, when the State convicts an individual of a drug offense, it is notifying the appropriate State office or, if the offender is a non-resident driver, the appropriate office in the driver's home State. If the State is not yet making these notifications, the State may satisfy this element by submitting a plan describing the steps it is taking to establish notification procedures.

(c) If the State believes it meets the requirements of 23 U.S.C. 159(a)(3)(B) on the basis that it opposes a law that requires the suspension, revocation or delay in issuance or reinstatement of the driver's license of drug offenders that conforms to 23 U.S.C. 159(a)(3)(A), the certification shall contain:

(1) A statement by the Governor of the State that he or she is opposed to the enactment or enforcement of a law that conforms to 23 U.S.C. 159(a)(3)(A) and that the State legislature has adopted a resolution expressing its opposition to such a law. The certifying statement may be worded as follows: I, (Name of Governor), Governor of the (State or Commonwealth of ______, do hereby certify that I am opposed to the enactment or enforcement of a law that conforms to 23 U.S.C. 159(a)(3)(A) and that the legislature of the (State or Commonwealth) of ______, has adopted a resolution expressing its opposition to such a law.

(2) Until a State has been determined to be in compliance with the requirements of 23 U.S.C. 159(a)(3)(B) and this regulation, the certification shall include a copy of the resolution.

(d) The Governor each year shall submit the original and three copies of the certification to the local FHWA Division Administrator. The FHWA Division Administrator shall retain the original and forward one copy each to the FHWA Regional Administrator, FHWA Chief Counsel, and the Director of the Office of Highway Safety.

(e) Any changes to the original certification or supplemental information necessitated by the review of the certifications as they are forwarded, State legislative changes or changes in State enforcement activity (including failure to make progress in a plan previously submitted) shall be submitted in the same manner as the original.

[57 FR 35999, Aug. 12, 1992. Redesignated and amended at 60 FR 50100, Sept. 28, 1995]



§192.6   Period of availability of withheld funds.

(a) Funds withheld under §1212.4 from apportionment to any State on or before September 30, 1995, will remain available for apportionment as follows:

(1) If the funds would have been apportioned under 23 U.S.C. 104(b)(5)(A) but for this section, the funds will remain available until the end of the fiscal year for which the funds are authorized to be appropriated.

(2) If the funds would have been apportioned under 23 U.S.C. 104(b)(5)(B) but for this section, the funds will remain available until the end of the second fiscal year following the fiscal year for which the funds are authorized to be appropriated.

(3) If the funds would have been apportioned under 23 U.S.C. 104(b)(1) or 104(b)(3) but for this section, the funds will remain available until the end of the third fiscal year following the fiscal year for which the funds are authorized to be appropriated.

(b) Funds withheld under §1212.4 from apportionment to any State after September 30, 1995 will not be available for apportionment to the State.


§192.7   Apportionment of withheld funds after compliance.

Funds withheld under §1212.4 from apportionment, which remain available for apportionment under §1212.6(a), will be made available to any State that conforms to the requirements of §1212.4 before the last day of the period of availability as defined in §1212.6(a).

[57 FR 35999, Aug. 12, 1992, as amended at 59 FR 39256, Aug. 2, 1994]



§192.8   Period of availability of subsequently apportioned funds.

(a) Funds apportioned pursuant to §1212.7 will remain available for expenditure as follows:

(1) Funds originally apportioned under 23 U.S.C. 104(b)(5)(A) will remain available until the end of the fiscal year succeeding the fiscal year in which the funds are apportioned.

(2) Funds originally apportioned under 23 U.S.C. 104(b)(1), 104(b)(2), 104(b)(5)(B), or 104(b)(6) will remain available until the end of the third fiscal year succeeding the fiscal year in which the funds are apportioned.

(b) Sums apportioned to a State pursuant to §1212.7 and not obligated at the end of the periods defined in §1212.8(a), shall lapse or, in the case of funds apportioned under 23 U.S.C. 104(b)(5), shall lapse and be made available by the Secretary for projects in accordance with 23 U.S.C. 118(b).


§192.9   Effect of noncompliance.

If a State has not met the requirements of 23 U.S.C. 159(a)(3) at the end of the period for which funds withheld under §1212.4 are available for apportionment to a State under §1212.6, then such funds shall lapse or, in the case of funds withheld from apportionment under 23 U.S.C. 104(b)(5), shall lapse and be made available by the Secretary for projects in accordance with 23 U.S.C. 118(b).


§192.10   Procedures affecting States in noncompliance.

(a) Each fiscal year, each State determined to be in noncompliance with 23 U.S.C. 159, based on FHWA's preliminary review of its statutes, will be advised of the funds expected to be withheld under §1212.4 from apportionment, as part of the advance notice of apportionments required under 23 U.S.C. 104(e), normally not later than ninety days prior to final apportionment.

(b) If FHWA determines that the State is not in compliance with 23 U.S.C. 159 based on the agencies' preliminary review, the State may, within 30 days of its receipt of the advance notice of apportionments, submit documentation showing why it is in compliance. Documentation shall be submitted to the Federal Highway Administration, 400 Seventh Street, SW., Washington, DC 20590.

(c) Each fiscal year, each State determined not to be in compliance with 23 U.S.C. 159(a)(3), based on FHWA's final determination, will receive notice of the funds being withheld under §1212.4 from apportionment, as part of the certification of apportionments required under 23 U.S.C. 104(e), which normally occurs on October 1 of each fiscal year.

[57 FR 35999, Aug. 12, 1992. Redesignated and amended at 60 FR 50100, Sept. 28, 1995]





SUBCHAPTER C -- CIVIL RIGHTS




PART 200 -- TITLE VI PROGRAM AND RELATED STATUTES -- IMPLEMENTATION AND REVIEW PROCEDURES


Sec.
200.1   Purpose.
200.3   Application of this part.
200.5   Definitions.
200.7   FHWA Title VI policy.
200.9   State highway agency responsibilities.
200.11   Procedures for processing Title VI reviews.
200.13   Certification acceptance.

Authority: Title VI of the Civil Rights Act of 1964, 42 U.S.C. 2000d to 2000d-4; Title VIII of the Civil Rights Act of 1968, 42 U.S.C. 3601-3619; 42 U.S.C. 4601 to 4655; 23 U.S.C. 109(h); 23 U.S.C. 324.

Source: 41 FR 53982, Dec. 10, 1976, unless otherwise noted.


§200.1   Purpose.

To provide guidelines for: (a) Implementing the Federal Highway Administration (FHWA) Title VI compliance program under Title VI of the Civil Rights Act of 1964 and related civil rights laws and regulations, and (b) Conducting Title VI program compliance reviews relative to the Federal-aid highway program.


§200.3   Application of this part.

The provisions of this part are applicable to all elements of FHWA and provide requirements and guidelines for State highway agencies to implement the Title VI Program requirements. The related civil rights laws and regulations are listed under §200.5(p) of this part. Title VI requirements for 23 U.S.C. 402 will be covered under a joint FHWA/NHTSA agreement.


§200.5   Definitions.

The following definitions shall apply for the purpose of this part:

(a) Affirmative action. A good faith effort to eliminate past and present discrimination in all federally assisted programs, and to ensure future nondiscriminatory practices.

(b) Beneficiary. Any person or group of persons (other than States) entitled to receive benefits, directly or indirectly, from any federally assisted program, i.e., relocatees, impacted citizens, communities, etc.

(c) Citizen participation. An open process in which the rights of the community to be informed, to provide comments to the Government and to receive a response from the Government are met through a full opportunity to be involved and to express needs and goals.

(d) Compliance. That satisfactory condition existing when a recipient has effectively implemented all of the Title VI requirements or can demonstrate that every good faith effort toward achieving this end has been made.

(e) Deficiency status. The interim period during which the recipient State has been notified of deficiencies, has not voluntarily complied with Title VI Program guidelines, but has not been declared in noncompliance by the Secretary of Transportation.

(f) Discrimination. That act (or action) whether intentional or unintentional, through which a person in the United States, solely because of race, color, religion, sex, or national origin, has been otherwise subjected to unequal treatment under any program or activity receiving financial assistance from the Federal Highway Administration under title 23 U.S.C.

(g) Facility. Includes all, or any part of, structures, equipment or other real or personal property, or interests therein, and the provision of facilities includes the construction, expansion, renovation, remodeling, alternation or acquisition of facilities.

(h) Federal assistance. Includes:

(1) Grants and loans of Federal funds,

(2) The grant or donation of Federal property and interests in property,

(3) The detail of Federal personnel,

(4) The sale and lease of, and the permission to use (on other than a casual or transient basis), Federal property or any interest in such property without consideration or at a nominal consideration, or at a consideration which is reduced for the purpose of assisting the recipient, or in recognition of the public interest to be served by such sale or lease to the recipient, and

(5) Any Federal agreement, arrangement, or other contract which has, as one of its purposes, the provision of assistance.

(i) Noncompliance. A recipient has failed to meet prescribed requirements and has shown an apparent lack of good faith effort in implementing all of the Title VI requirements.

(j) Persons. Where designation of persons by race, color, or national origin is required, the following designations ordinarily may be used: "White not of Hispanic origin", "Black not of Hispanic origin", "Hispanic", "Asian or Pacific Islander", "American Indian or Alaskan Native." Additional subcategories based on national origin or primary language spoken may be used, where appropriate, on either a national or a regional basis.

(k) Program. Includes any highway, project, or activity for the provision of services, financial aid, or other benefits to individuals. This includes education or training, work opportunities, health, welfare, rehabilitation, housing, or other services, whether provided directly by the recipient of Federal financial assistance or provided by others through contracts or other arrangements with the recipient.

(l) State highway agency. That department, commission, board, or official of any State charged by its laws with the responsibility for highway construction. The term State would be considered equivalent to State highway agency if the context so implies.

(m) Program area officials. The officials in FHWA who are responsible for carrying out technical program responsibilities.

(n) Recipient. Any State, territory, possession, the District of Columbia, Puerto Rico, or any political subdivision, or instrumentality thereof, or any public or private agency, institution, or organization, or other entity, or any individual, in any State, territory, possession, the District of Columbia, or Puerto Rico, to whom Federal assistance is extended, either directly or through another recipient, for any program. Recipient includes any successor, assignee, or transferee thereof. The term recipient does not include any ultimate beneficiary under any such program.

(o) Secretary. The Secretary of Transportation as set forth in 49 CFR 21.17(g)(3) or the Federal Highway Administrator to whom the Secretary has delegated his authority in specific cases.

(p) Title VI Program. The system of requirements developed to implement Title VI of the Civil Rights Act of 1964. References in this part to Title VI requirements and regulations shall not be limited to only Title VI of the Civil Rights Act of 1964. Where appropriate, this term also refers to the civil rights provisions of other Federal statutes to the extent that they prohibit discrimination on the grounds of race, color, sex, or national origin in programs receiving Federal financial assistance of the type subject to Title VI itself. These Federal statutes are:

(1) Title VI of the Civil Rights Act of 1964, 42 U.S.C. 2000d-d4 (49 CFR part 21; the standard DOT Title VI assurances signed by each State pursuant to DOT Order 1050.2; Executive Order 11764; 28 CFR 50.3);

(2) Uniform Relocation Assistance and Real Property Acquisition Policies Act of 1970 (42 U.S.C. 4601-4655) (49 CFR part 25; Pub. L. 91-646);

(3) Title VIII of the Civil Rights Act of 1968, amended 1974 (42 U.S.C. 3601- 3619);

(4) 23 U.S.C. 109(h);

(5) 23 U.S.C. 324;

(6) Subsequent Federal-Aid Highway Acts and related statutes.


§200.7   FHWA Title VI policy.

It is the policy of the FHWA to ensure compliance with Title VI of the Civil Rights Act of 1964; 49 CFR part 21; and related statutes and regulations.


§200.9   State highway agency responsibilities.

(a) State assurances in accordance with Title VI of the Civil Rights Act of 1964.

(1) Title 49, CFR part 21 (Department of Transportation Regulations for the implementation of Title VI of the Civil Rights Act of 1964) requires assurances from States that no person in the United States shall, on the grounds of race, color, or national origin, be excluded from participation in, be denied the benefits of, or be otherwise subjected to discrimination under any program or activity for which the recipient receives Federal assistance from the Department of Transportation, including the Federal Highway Administration.

(2) Section 162a of the Federal-Aid Highway Act of 1973 (section 324, title 23 U.S.C.) requires that there be no discrimination on the ground of sex. The FHWA considers all assurances heretofore received to have been amended to include a prohibition against discrimination on the ground of sex. These assurances were signed by the 50 States, the District of Columbia, Puerto Rico, the Virgin Islands, Guam, and American Samoa. The State highway agency shall submit a certification to the FHWA indicating that the requirements of section 162a of the Federal-Aid Highway Act of 1973 have been added to its assurances.

(3) The State highway agency shall take affirmative action to correct any deficiencies found by the FHWA within a reasonable time period, not to exceed 90 days, in order to implement Title VI compliance in accordance with State-signed assurances and required guidelines. The head of the State highway agency shall be held responsible for implementing Title VI requirements.

(4) The State program area officials and Title VI Specialist shall conduct annual reviews of all pertinent program areas to determine the effectiveness of program area activities at all levels.

(b) State actions. (1) Establish a civil rights unit and designate a coordinator who has a responsible position in the organization and easy access to the head of the State highway agency. This unit shall contain a Title VI Equal Employment Opportunity Coordinator or a Title VI Specialist, who shall be responsible for initiating and monitoring Title VI activities and preparing required reports.

(2) Adequately staff the civil rights unit to effectively implement the State civil rights requirements.

(3) Develop procedures for prompt processing and disposition of Title VI and Title VIII complaints received directly by the State and not by FHWA. Complaints shall be investigated by State civil rights personnel trained in compliance investigations. Identify each complainant by race, color, sex, or national origin; the recipient; the nature of the complaint; the dates the complaint was filed and the investigation completed; the disposition; the date of the disposition; and other pertinent information. Each recipient (State) processing Title VI complaints shall be required to maintain a similar log. A copy of the complaint, together with a copy of the State's report of investigation, shall be forwarded to the FHWA division office within 60 days of the date the complaint was received by the State.

(4) Develop procedures for the collection of statistical data (race, color, religion, sex, and national origin) of participants in, and beneficiaries of State highway programs, i.e., relocatees, impacted citizens and affected communities.

(5) Develop a program to conduct Title VI reviews of program areas.

(6) Conduct annual reviews of special emphasis program areas to determine the effectiveness or program area activities at all levels.

(7) Conduct Title VI reviews of cities, counties, consultant contractors, suppliers, universities, colleges, planning agencies, and other recipients of Federal-aid highway funds.

(8) Review State program directives in coordination with State program officials and, where applicable, include Title VI and related requirements.

(9) The State highway agency Title VI designee shall be responsible for conducting training programs on Title VI and related statutes for State program and civil rights officials.

(10) Prepare a yearly report of Title VI accomplishments for the past year and goals for the next year.

(11) Beginning October 1, 1976, each State highway agency shall annually submit an updated Title VI implementing plan to the Regional Federal Highway Administrator for approval or disapproval.

(12) Develop Title VI information for dissemination to the general public and, where appropriate, in languages other than English.

(13) Establishing procedures for pregrant and postgrant approval reviews of State programs and applicants for compliance with Title VI requirements; i.e., highway location, design and relocation, and persons seeking contracts with the State.

(14) Establish procedures to identify and eliminate discrimination when found to exist.

(15) Establishing procedures for promptly resolving deficiency status and reducing to writing the remedial action agreed to be necessary, all within a period not to exceed 90 days.


§200.11   Procedures for processing Title VI reviews.

(a) If the regional Title VI review report contains deficiencies and recommended actions, the report shall be forwarded by the Regional Federal Highway Administrator to the Division Administrator, who will forward it with a cover letter to the State highway agency for corrective action.

(b) The division office, in coordination with the Regional Civil Rights Officer, shall schedule a meeting with the recipient, to be held not later than 30 days from receipt of the deficiency report.

(c) Recipients placed in a deficiency status shall be given a reasonable time, not to exceed 90 days after receipt of the deficiency letter, to voluntarily correct deficiencies.

(d) The Division Administrator shall seek the cooperation of the recipient in correcting deficiencies found during the review. The FHWA officials shall also provide the technical assistance and guidance needed to aid the recipient to comply voluntarily.

(e) When a recipient fails or refuses to voluntarily comply with requirements within the time frame allotted, the Division Administrator shall submit to the Regional Administrator two copies of the case file and a recommendation that the State be found in noncompliance.

(f) The Office of Civil Rights shall review the case file for a determination of concurrence or noncurrence with a recommendation to the Federal Highway Administrator. Should the Federal Highway Administrator concur with the recommendation, the file is referred to the Department of Transportation, Office of the Secretary, for appropriate action in accordance with 49 CFR.


§200.13   Certification acceptance.

Title VI and related statutes requirements apply to all State highway agencies. States and FHWA divisions operating under certification acceptance shall monitor the Title VI aspects of the program by conducting annual reviews and submitting required reports in accordance with guidelines set forth in this document.




PART 230 -- EXTERNAL PROGRAMS



Subpart A -- Equal Employment Opportunity on Federal and Federal-Aid Construction Contracts (Including Supportive Services)


   Sec.
230.101   Purpose.
230.103   Definitions.
230.105   Applicability.
230.107   Policy.
230.109   Implementation of specific Equal Employment Opportunity requirements.
230.111   Implementation of special requirements for the provision of on-the-job training.
230.113   Implementation of supportive services.
230.115   Special contract requirements for "Hometown" or "Imposed" Plan areas.
230.117   Reimbursement procedures (Federal-aid highway construction projects only).
230.119   Monitoring of supportive services.
230.121   Reports.
Appendix A to Subpart A -- Special Provisions
Appendix B to Subpart A -- Training Special Provisions
Appendix C to Subpart A -- Federal-Aid Highway Contractors Annual EEO Report (Form PR-1391)
Appendix D to Subpart A -- Federal-Aid Highway Construction Summary of Employment Data (Form PR-1392)
Appendixes E-F to Subpart A [Reserved]
Appendix G to Subpart A -- Special Reporting Requirements for "Hometown" or "Imposed" Plan Areas

Subpart B -- Supportive Services for Minority, Disadvantaged, and Women Business Enterprises

230.201   Purpose.
230.202   Definitions.
230.203   Policy.
230.204   Implementation of supportive services.
230.205   Supportive services funds obligation.
230.206   Monitoring supportive services.
230.207   Sources of assistance.

Subpart C -- State Highway Agency Equal Employment Opportunity Programs

230.301   Purpose.
230.303   Applicability.
230.305   Definitions.
230.307   Policy.
230.309   Program format.
230.311   State responsibilities.
230.313   Approval procedure.
Appendix A to Subpart C -- State Highway Agency Equal Employment Opportunity Programs

Subpart D -- Construction Contract Equal Opportunity Compliance Procedures

230.401   Purpose.
230.403   Applicability.
230.405   Administrative responsibilities.
230.407   Definitions.
230.409   Contract compliance review procedures.
230.411   Guidance for conducting reviews.
230.413   Review reports.
230.415   Consolidated compliance reviews.
Appendix A to Subpart D -- Sample Show Cause Notice
Appendix B to Subpart D -- Sample Corrective Action Plan
Appendix C to Subpart D -- Sample Show Cause Rescission
Appendix D to Subpart D -- Equal Opportunity Compliance Review Process Flow Chart

Authority: 23 U.S.C. 101, 140, and 315; 42 U.S.C. 2000d et seq.; 49 CFR 1.48 and 60-1.

Source: 40 FR 28053, July 3, 1975, unless otherwise noted.

Subpart A -- Equal Employment Opportunity on Federal and Federal-Aid Construction Contracts (Including Supportive Services)



§230.101   Purpose.

The purpose of the regulations in this subpart is to prescribe the policies, procedures, and guides relative to the implementation of an equal employment opportunity program on Federal and Federal-aid highway construction contracts, except for those contracts awarded under 23 U.S.C. 117, and to the preparation and submission of reports pursuant thereto.


§230.103   Definitions.

For purposes of this subpart --

Administrator means the Federal Highway Administrator.

Areawide Plan means an affirmative action plan to increase minority utilization of crafts in a specified geographical area pursuant to Executive Order 11246, and taking the form of either a "Hometown" or an "Imposed" plan.

Bid conditions means contract requirements which have been issued by OFCC for purposes of implementing a Hometown Plan.

Division Administrator means the chief Federal Highway Administration (FHWA) official assigned to conduct FHWA business in a particular State, the District of Columbia, or the Commonwealth of Puerto Rico.

Division Equal Opportunity Officer means an individual with staff level responsibilities and necessary authority by which to operate as an Equal Opportunity Officer in a Division office. Normally the Equal Opportunity Officer will be a full-time civil rights specialist serving as staff assistant to the Division Administrator.

Hometown Plan means a voluntary areawide plan which was developed by representatives of affected groups (usually labor unions, minority organizations, and contractors), and subsequently approved by the Office of Federal Contract Compliance (OFCC), for purposes of implementing the equal employment opportunity requirements pursuant to Executive Order 11246, as amended.

Imposed Plan means an affirmative action requirement for a specified geographical area made mandatory by OFCC and, in some areas, by the courts.

Journeyman means a person who is capable of performing all the duties within a given job classification or craft.

State highway agency means that department, commission, board, or official of any State charged by its laws with the responsibility for highway construction. The term State should be considered equivalent to State highway agency.

Suggested minimum annual training goals means goals which have been assigned to each State highway agency annually for the purpose of specifying training positions on selected Federal-aid highway construction projects.

Supportive services means those services provided in connection with approved on-the-job training programs for highway construction workers and highway contractors which are designed to increase the overall effectiveness of training programs through the performance of functions determined to be necessary in connection with such programs, but which are not generally considered as comprising part of actual on-the-job craft training.

Trainee means a person who received on-the-job training, whether through an apprenticeship program or other programs approved or accepted by the FHWA.

[40 FR 28053, July 3, 1975, as amended at 41 FR 3080, Jan. 21, 1976]



§230.105   Applicability.

(a) Federal-aid highway construction projects. This subpart applies to all Federal-aid highway construction projects and to Appalachian highway construction projects and other State supervised cooperative highway construction projects except:

(1) Federal-aided highway construction projects being constructed pursuant to 23 U.S.C. 117; and

(2) Those projects located in areas where the Office of Federal Contract Compliance has implemented an "Imposed" or a "Hometown" Plan, except for those requirements pertaining to specific provisions involving on-the-job training and those provisions pertaining to supportive services and reporting requirements.

(b) Direct Federal highway construction projects. This subpart applies to all direct Federal highway construction projects except:

(1) For those provisions relating to the special requirements for the provision of supportive services; and

(2) For those provisions relating to implementation of specific equal employment opportunity requirements in areas where the Office of Federal Contract Compliance has implemented an "Imposed" or "Hometown" plan.


§230.107   Policy.

(a) Direct Federal and Federal-aid highway construction projects. It is the policy of the FHWA to require that all direct Federal and Federal-aid highway construction contracts include the same specific equal employment opportunity requirements. It is also the policy to require that all direct Federal and Federal-aid highway construction subcontracts of $10,000 or more (not including contracts for supplying materials) include these same requirements.

(b) Federal-aid highway construction projects. It is the policy of the FHWA to require full utilization of all available training and skill-improvement opportunities to assure the increased participation of minority groups and disadvantaged persons and women in all phases of the highway construction industry. Moreover, it is the policy of the Federal Highway Administration to encourage the provision of supportive services which will increase the effectiveness of approved on-the-job training programs conducted in connection with Federal-aid highway construction projects.


§230.109   Implementation of specific Equal Employment Opportunity requirements.

(a) Federal-aid highway construction projects. The special provisions set forth in appendix A shall be included in the advertised bidding proposal and made part of the contract for each contract and each covered Federal-aid highway construction subcontract.

(b) Direct Federal highway construction projects. Advertising, award and contract administration procedures for direct Federal highway construction contracts shall be as set forth in Federal Acquisition Regulations (48 CFR, chapter 1, section 22.803(c)). In order to obtain information required by 48 CFR, chapter 1, §22.804-2(c), the following requirement shall be included at the end of the bid schedule in the proposal and contract assembly:

I expect to employ the following firms as subcontractors on this project: (Naming subcontractors at this time does not constitute a binding commitment on the bidder to retain such subcontractors, nor will failure to enter names affect the contract award): Name _____ Address_____ Name_____ Address_____

[40 FR 28053, July 3, 1975, as amended at 51 FR 22800, June 23, 1986]



§230.111   Implementation of special requirements for the provision of on-the-job training.

(a) The State highway agency shall determine which Federal-aid highway construction contracts shall include the "Training Special Provisions" (appendix B) and the minimum number of trainees to be specified therein after giving appropriate consideration to the guidelines set forth in §230.111(c). The "Training Special Provisions" shall supersede section 7(b) of the Special Provisions (appendix A) entitled "Specific Equal Employment Opportunity Responsibilities." Minor wording revisions will be required to the "Training Special Provisions" in areas having "Hometown" or "Imposed Plan" requirements.

(b) The Washington Headquarters shall establish and publish annually suggested minimum training goals. These goals will be based on the Federal-aid apportioned amounts and the minority population. A State will have achieved its goal if the total number of training slots on selected federally aided highway construction contracts which have been awarded during each 12-month period equals or exceeds the State's suggested minimum annual goal. In the event a State highway agency does not attain its goal during a calendar year, the State highway agency at the end of the calendar year shall inform the Administrator of the reasons for its inability to meet the suggested minimum number of training slots and the steps to be taken to achieve the goal during the next calendar year. The information is to be submitted not later than 30 days from the end of the calendar year and should be factual, and should not only indicate the situations occurring during the year but show the project conditions at least through the coming year. The final determination will be made on what training goals are considered to be realistic based on the information submitted by a State.

(c) The following guidelines shall be utilized by the State highway agency in selecting projects and determining the number of trainees to be provided training therein:

(1) Availability of minorities, women, and disadvantaged for training.

(2) The potential for effective training.

(3) Duration of the contract.

(4) Dollar value of the contract.

(5) Total normal work force that the average bidder could be expected to use.

(6) Geographic location.

(7) Type of work.

(8) The need for additional journeymen in the area.

(9) Recognition of the suggested minimum goal for the State.

(10) A satisfactory ratio of trainees to journeymen expected to be on the contractor's work force during normal operations (considered to fall between 1:10 and 1:4).

(d) Training programs which are established shall be approved only if they meet the standards set forth in appendix B with regard to:

(1) The primary objectives of training and upgrading minority group workers, women and disadvantaged persons.

(2) The development of full journeymen.

(3) The minimum length and type of training.

(4) The minimum wages of trainees.

(5) Trainees certifications.

(6) Keeping records and furnishing reports.

(e)(1) Training programs considered by a State highway agency to meet the standards under this directive shall be submitted to the FHWA division Administrator with a recommendation for approval.

(2) Employment pursuant to training programs approved by the FHWA division Administrator will be exempt from the minimum wage rate provisions of section 113 of title 23 U.S.C. Approval, however, shall not be given to training programs which provide for employment of trainees at wages less than those required by the Special Training Provisions. (Appendix B.)

(f)(1) Apprenticeship programs approved by the U.S. Department of Labor as of the date of proposed use by a Federal-aid highway contractor or subcontractor need not be formally approved by the State highway agency or the FHWA division Administrator. Such programs, including their minimum wage provisions, are acceptable for use, provided they are administered in a manner reasonably calculated to meet the equal employment opportunity obligations of the contractor.

(2) Other training programs approved by the U.S. Department of Labor as of the date of proposed use by a Federal-aid highway contractor or subcontractor are also acceptable for use without the formal approval of the State highway agency or the division Administrator provided:

(i) The U.S. Department of Labor has clearly approved the program aspects relating to equal employment opportunity and the payment of trainee wage rates in lieu of prevailing wage rates.

(ii) They are reasonably calculated to qualify the average trainees for journeyman status in the classification concerned by the end of the training period.

(iii) They are administered in a manner calculated to meet the equal employment obligations of the contractors.

(g) The State highway agencies have the option of permitting Federal-aid highway construction contractors to bid on training to be given under this directive. The following procedures are to be utilized by those State highway agencies that elect to provide a bid item for training:

(1) The number of training positions shall continue to be specified in the Special Training Provisions. Furthermore, this number should be converted into an estimated number of hours of training which is to be used in arriving at the total bid price for the training item. Increases and decreases from the estimated amounts would be handled as overruns or underruns;

(2) A section concerning the method of payment should be included in the Special Training Provisions. Some offsite training is permissible as long as the training is an integral part of an approved training program and does not comprise a substantial part of the overall training. Furthermore, the trainee must be concurrently employed on a federally aided highway construction project subject to the Special Training Provisions attached to this directive. Reimbursement for offsite training may only be made to the contractor where he does one or more of the following: Contributes to the cost of the training, provides the instruction to the trainee, or pays the trainee's wages during the offsite training period;

(3) A State highway agency may modify the special provisions to specify the numbers to be trained in specific job classifications;

(4) A State highway agency can specify training standards provided any prospective bidder can use them, the training standards are made known in the advertised specifications, and such standards are found acceptable by FHWA.

[40 FR 28053, July 3, 1975; 40 FR 57358, Dec. 9, 1975, as amended at 41 FR 3080, Jan. 21, 1976]



§230.113   Implementation of supportive services.

(a) The State highway agency shall establish procedures, subject to the availability of funds under 23 U.S.C. 140(b), for the provision of supportive services in support of training programs approved under this directive. Funds made available to implement this paragraph shall not be used to finance the training of State highway agency employees or to provide services in support of such training. State highway agencies are not required to match funds allocated to them under this section.

(b) In determining the types of supportive services to be provided which will increase the effectiveness of approved training programs. State highway agencies shall give preference to the following types of services in the order listed:

(1) Services related to recruiting, counseling, transportation, physical examinations, remedial training, with special emphasis upon increasing training opportunities for members of minority groups and women;

(2) Services in connection with the administration of on-the-job training programs being sponsored by individual or groups of contractors and/or minority groups and women's groups;

(3) Services designed to develop the capabilities of prospective trainees for undertaking on-the-job training;

(4) Services in connection with providing a continuation of training during periods of seasonal shutdown;

(5) Followup services to ascertain outcome of training being provided.

(c) State highway agencies which desire to provide or obtain supportive services other than those listed above shall submit their proposals to the Federal Highway Administration for approval. The proposal, together with recommendations of the division and regional offices shall be submitted to the Administrator for appropriate action.

(d) When the State highway agency provides supportive services by contract, formal advertising is not required by the FHWA, however, the State highway agency shall solicit proposals from such qualified sources as will assure the competitive nature of the procurement. The evaluation of proposals by the State highway agency must include consideration of the proposer's ability to effect a productive relationship with contractors, unions (if appropriate), minority and women groups, minority and women trainees, and other persons or organizations whose cooperation and assistance will contribute to the successful performance of the contract work.

(e) In the selection of contractors to provide supportive services, State highway agencies shall make conscientious efforts to search out and utilize the services of qualified minority or women organizations, or minority or women business enterprises.

(f) As a minimum, State highway agency contracts to obtain supportive services shall include the following provisions:

(1) A statement that a primary purpose of the supportive services is to increase the effectiveness of approved on-the-job training programs, particularly their effectiveness in providing meaningful training opportunities for minorities, women, and the disadvantaged on Federal-aid highway projects;

(2) A clear and complete statement of the services to be provided under the contract, such as services to construction contractors, subcontractors, and trainees, for recruiting, counseling, remedial educational training, assistance in the acquisition of tools, special equipment and transportation, followup procedures, etc.;

(3) The nondiscrimination provisions required by Title VI of the Civil Rights Act of 1964 as set forth in FHWA Form PR-1273, and a statement of nondiscrimination in employment because of race, color, religion, national origin or sex;

(4) The establishment of a definite perriod of contract performance together with, if appropriate, a schedule stating when specific supportive services are to be provided;

(5) Reporting requirements pursuant to which the State highway agency will receive monthly or quarterly reports containing sufficient statistical data and narrative content to enable evaluation of both progress and problems;

(6) A requirement that the contractor keep track of trainees receiving training on Federal-aid highway construction projects for up to 6 months during periods when their training is interrupted. Such contracts shall also require the contractor to conduct a 6 month followup review of the employment status of each graduate who completes an on-the-job training program on a Federal-aid highway construction project subsequent to the effective date of the contract for supportive services.

(7) The basis of payment;

(8) An estimated schedule for expenditures;

(9) The right of access to contractor and subcontractor records and the right to audit shall be granted to authorize State highway agency and FHWA officials;

(10) Noncollusion certification;

(11) A requirement that the contractor provide all information necessary to support progress payments if such are provided for in the contract;

(12) A termination clause.

(g) The State highway agency is to furnish copies of the reports received under paragraph (b)(5) of this section, to the division office.

[40 FR 28053, July 3, 1975, as amended at 41 FR 3080, Jan. 21, 1976]



§230.115   Special contract requirements for "Hometown" or "Imposed" Plan areas.

Direct Federal and Federal-aid contracts to be performed in "Hometown" or "Imposed" Plan areas will incorporate the special provision set forth in appendix G.


§230.117   Reimbursement procedures (Federal-aid highway construction projects only).

(a) On-the-job special training provisions. State highway agencies will be reimbursed on the same pro-rata basis as the construction costs of the Federal-aid project.

(b) Supportive services. (1) The State highway agency must keep a separate account of supportive services funds since they cannot be interchanged with regular Federal-aid funds. In addition, these funds may not be expended in a manner that would provide for duplicate payment of Federal or Federal-aid funds for the same service.

(2) Where a State highway agency does not obligate all its funds within the time specified in the particular year's allocation directive, the funds shall revert to the FHWA Headquarters Office to be made available for use by other State highway agencies, taking into consideration each State's need for and ability to use such funds.


§230.119   Monitoring of supportive services.

Supportive services procured by a State highway agency shall be monitored by both the State highway agency and the division office.


§230.121   Reports.

(a) Employment reports on Federal-aid highway construction contracts not subject to "Hometown" or "Imposed" plan requirements.

(1) Paragraph 10c of the special provisions (appendix A) sets forth specific reporting requirements. FHWA Form PR-1391, Federal-Aid Highway Construction Contractors Annual EEO Report, (appendix C) and FHWA Form PR 1392, Federal-Aid Highway Construction Summary of Employment Data (including minority breakdown) for all Federal-Aid Highway Projects for month ending July 31st, 19 -- , (appendix D) are to be used to fulfill these reporting requirements.

(2) Form PR 1391 is to be completed by each contractor and each subcontractor subject to this part for every month of July during which work is performed, and submitted to the State highway agency. A separate report is to be completed for each covered contract or subcontract. The employment data entered should reflect the work force on board during all or any part of the last payroll period preceding the end of the month. The State highway agency is to forward a single copy of each report to the FHWA division office.

(3) Form PR 1392 is to be completed by the State highway agencies, summarizing the reports on PR 1391 for the month of July received from all active contractors and subcontractors. Three (3) copies of completed Forms PR 1392 are to be forwarded to the division office.

(b) Employment reports on direct Federal highway construction contracts not subject to "Hometown" or "Imposed" plan requirements. Forms PR 1391 (appendix C) and PR 1392 (appendix D) shall be used for reporting purposes as prescribed in §230.121(a).

(c) Employment reports on direct Federal and Federal-aid highway construction contracts subject to "Hometown" or "Imposed" plan requirements.

(1) Reporting requirements for direct Federal and Federal-aid highway construction projects located in areas where "Hometown" or "Imposed" plans are in effect shall be in accordance with those issued by the U.S. Department of Labor, Office of Federal Contract Compliance.

(2) In order that we may comply with the U.S. Senate Committee on Public Works' request that the Federal Highway Administration submit a report annually on the status of the equal employment opportunity program, Form PR 1391 is to be completed annually by each contractor and each subcontractor holding contracts or subcontracts exceeding $10,000 except as otherwise provided for under 23 U.S.C. 117. The employment data entered should reflect the work force on board during all or any part of the last payroll period preceding the end of the month of July.

(d) [Reserved]

(e) Reports on supportive services contracts. The State highway agency is to furnish copies of the reports received from supportive services contractors to the FHWA division office which will furnish a copy to the regional office.

[40 FR 28053, July 3, 1975, as amended at 43 FR 19386, May 5, 1978; 61 FR 14616, Apr. 3, 1996]




Appendix A to Subpart A of Part 230 -- Special Provisions

SPECIFIC EQUAL EMPLOYMENT OPPORTUNITY RESPONSIBILITIES

1. General. a. Equal employment opportunity requirements not to discriminate and to take affirmative action to assure equal employment opportunity as required by Executive Order 11246 and Executive Order 11375 are set forth in Required Contract, Provisions (Form PR-1273 or 1316, as appropriate) and these Special Provisions which are imposed pursuant to section 140 of title 23 U.S.C., as established by section 22 of the Federal-Aid Highway Act of 1968. The requirements set forth in these Special Provisions shall constitute the specific affirmative action requirements for project activities under this contract and supplement the equal employment opportunity requirements set forth in the Required Contract Provisions.

b. The contractor will work with the State highway agencies and the Federal Government in carrying out equal employment opportunity obligations and in their review of his/her activities under the contract.

c. The contractor and all his/her subcontractors holding subcontracts not including material suppliers, of $10,000 or more, will comply with the following minimum specific requirement activities of equal employment opportunity: (The equal employment opportunity requirements of Executive Order 11246, as set forth in volume 6, chapter 4, section 1, subsection 1 of the Federal-Aid Highway Program Manual, are applicable to material suppliers as well as contractors and subcontractors.) The contractor will include these requirements in every subcontract of $10,000 or more with such modification of language as is necessary to make them binding on the subcontractor.

2. Equal Employment Opportunity Policy. The contractor will accept as his operating policy the following statement which is designed to further the provision of equal employment opportunity to all persons without regard to their race, color, religion, sex, or national origin, and to promote the full realization of equal employment opportunity through a positive continuing program:

It is the policy of this Company to assure that applicants are employed, and that employees are treated during employment, without regard to their race, religion, sex, color, or national origin. Such action shall include: employment, upgrading, demotion, or transfer; recruitment or recruitment advertising; layoff or termination; rates of pay or other forms of compensation; and selection for training, including apprenticeship, preapprenticeship, and/or on-the-job training.

3. Equal Employment Opportunity Officer. The contractor will designate and make known to the State highway agency contracting officers and equal employment opportunity officer (hereinafter referred to as the EEO Officer) who will have the responsibility for and must be capable of effectively administering and promoting an active contractor program of equal employment opportunity and who must be assigned adequate authority and responsibility to do so.

4. Dissemination of Policy. a. All members of the contractor's staff who are authorized to hire, supervise, promote, and discharge employees, or who recommend such action, or who are substantially involved in such action, will be made fully cognizant of, and will implement, the contractor's equal employment opportunity policy and contractual responsibilities to provide equal employment opportunity in each grade and classification of employment. To ensure that the above agreement will be met, the following actions will be taken as a minimum:

(1) Periodic meetings of supervisory and personnel office employees will be conducted before the start of work and then not less often than once every six months, at which time the contractor's equal employment opportunity policy and its implementation will be reviewed and explained. The meetings will be conducted by the EEO Officer or other knowledgeable company official.

(2) All new supervisory or personnel office employees will be given a thorough indoctrination by the EEO Officer or other knowledgeable company official, covering all major aspects of the contractor's equal employment opportunity obligations within thirty days following their reporting for duty with the contractor.

(3) All personnel who are engaged in direct recruitment for the project will be instructed by the EEO Officer or appropriate company official in the contractor's procedures for locating and hiring minority group employees.

b. In order to make the contractor's equal employment opportunity policy known to all employees, prospective employees and potential sources of employees, i.e., schools, employment agencies, labor unions (where appropriate), college placement officers, etc., the contractor will take the following actions:

(1) Notices and posters setting forth the contractor's equal employment opportunity policy will be placed in areas readily accessible to employees, applicants for employment and potential employees.

(2) The contractor's equal employment opportunity policy and the procedures to implement such policy will be brought to the attention of employees by means of meetings, employee handbooks, or other appropriate means.

5. Recruitment. a. When advertising for employees, the contractor will include in all advertisements for employees the notation: "An Equal Opportunity Employer." All such advertisements will be published in newspapers or other publications having a large circulation among minority groups in the area from which the project work force would normally be derived.

b. The contractor will, unless precluded by a valid bargaining agreement, conduct systematic and direct recruitment through public and private employee referral sources likely to yield qualified minority group applicants, including, but not limited to, State employment agencies, schools, colleges and minority group organizations. To meet this requirement, the contractor will, through his EEO Officer, identify sources of potential minority group employees, and establish with such identified sources procedures whereby minority group applicants may be referred to the contractor for employment consideration.

In the event the contractor has a valid bargaining agreement providing for exclusive hiring hall referrals, he is expected to observe the provisions of that agreement to the extent that the system permits the contractor's compliance with equal employment opportunity contract provisions. (The U.S. Department of Labor has held that where implementation of such agreements have the effect of discriminating against minorities or women, or obligates the contractor to do the same, such implementation violates Executive Order 11246, as amended.)

c. The contractor will encourage his present employees to refer minority group applicants for employment by posting appropriate notices or bulletins in areas accessible to all such employees. In addition, information and procedures with regard to referring minority group applicants will be discussed with employees.

6. Personnel Actions. Wages, working conditions, and employee benefits shall be established and administered, and personnel actions of every type, including hiring, upgrading, promotion, transfer, demotion, layoff, and termination, shall be taken without regard to race, color, religion, sex, or national origin. The following procedures shall be followed:

a. The contractor will conduct periodic inspections of project sites to insure that working conditions and employee facilities do not indicate discriminatory treatment of project site personnel.

b. The contractor will periodically evaluate the spread of wages paid within each classification to determine any evidence of discriminatory wage practices.

c. The contractor will periodically review selected personnel actions in depth to determine whether there is evidence of discrimination. Where evidence is found, the contractor will promptly take corrective action. If the review indicates that the discrimination may extend beyond the actions reviewed, such corrective action shall include all affected persons.

d. The contractor will promptly investigate all complaints of alleged discrimination made to the contractor in connection with his obligations under this contract, will attempt to resolve such complaints, and will take appropriate corrective action within a reasonable time. If the investigation indicates that the discrimination may affect persons other than the complainant, such corrective action shall include such other persons. Upon completion of each investigation, the contractor will inform every complainant of all of his avenues of appeal.

7. Training and Promotion. a. The contractor will assist in locating, qualifying, and increasing the skills of minority group and women employees, and applicants for employment.

b. Consistent with the contractor's work force requirements and as permissible under Federal and State regulations, the contractor shall make full use of training programs, i.e., apprenticeship, and on-the-job training programs for the geographical area of contract performance. Where feasible, 25 percent of apprentices or trainees in each occupation shall be in their first year of apprenticeship or training. In the event the Training Special Provision is provided under this contract, this subparagraph will be superseded as indicated in Attachment 2.

c. The contractor will advise employees and applicants for employment of available training programs and entrance requirements for each.

d. The contractor will periodically review the training and promotion potential of minority group and women employees and will encourage eligible employees to apply for such training and promotion.

8. Unions. If the contractor relies in whole or in part upon unions as a source of employees, the contractor will use his/her best efforts to obtain the cooperation of such unions to increase opportunities for minority groups and women within the unions, and to effect referrals by such unions of minority and female employees. Actions by the contractor either directly or through a contractor's association acting as agent will include the procedures set forth below:

a. The contractor will use best efforts to develop, in cooperation with the unions, joint training programs aimed toward qualifying more minority group members and women for membership in the unions and increasing the skills of minority group employees and women so that they may qualify for higher paying employment.

b. The contractor will use best efforts to incorporate an equal employment opportunity clause into each union agreement to the end that such union will be contractually bound to refer applicants without regard to their race, color, religion, sex, or national origin.

c. The contractor is to obtain information as to the referral practices and policies of the labor union except that to the extent such information is within the exclusive possession of the labor union and such labor union refuses to furnish such information to the contractor, the contractor shall so certify to the State highway department and shall set forth what efforts have been made to obtain such information.

d. In the event the union is unable to provide the contractor with a reasonable flow of minority and women referrals within the time limit set forth in the collective bargaining agreement, the contractor will, through independent recruitment efforts, fill the employment vacancies without regard to race, color, religion, sex, or national origin; making full efforts to obtain qualified and/or qualifiable minority group persons and women. (The U.S. Department of Labor has held that it shall be no excuse that the union with which the contractor has a collective bargaining agreement providing for exclusive referral failed to refer minority employees.) In the event the union referral practice prevents the contractor from meeting the obligations pursuant to Executive Order 11246, as amended, and these special provisions, such contractor shall immediately notify the State highway agency.

9. Subcontracting. a. The contractor will use his best efforts to solicit bids from and to utilize minority group subcontractors or subcontractors with meaningful minority group and female representation among their employees. Contractors shall obtain lists of minority-owned construction firms from State highway agency personnel.

b. The contractor will use his best efforts to ensure subcontractor compliance with their equal employment opportunity obligations.

10. Records and Reports. a. The contractor will keep such records as are necessary to determine compliance with the contractor's equal employment opportunity obligations. The records kept by the contractor will be designed to indicate:

(1) The number of minority and nonminority group members and women employed in each work classification on the project.

(2) The progress and efforts being made in cooperation with unions to increase employment opportunities for minorities and women (applicable only to contractors who rely in whole or in part on unions as a source of their work force),

(3) The progress and efforts being made in locating, hiring, training, qualifying, and upgrading minority and female employees, and

(4) The progress and efforts being made in securing the services of minority group subcontractors or subcontractors with meaningful minority and female representation among their employees.

b. All such records must be retained for a period of three years following completion of the contract work and shall be available at reasonable times and places for inspection by authorized representatives of the State highway agency and the Federal Highway Administration.

c. The contractors will submit an annual report to the State highway agency each July for the duration of the project, indicating the number of minority, women, and non-minority group employees currently engaged in each work classification required by the contract work. This information is to be reported on Form PR 1391. If on-the-job training is being required by "Training Special Provision", the contractor will be required to furnish Form FHWA 1409.

[40 FR 28053, July 3, 1975, as amended at 43 FR 19386, May 5, 1978. Correctly redesignated at 46 FR 21156, Apr. 9, 1981]




Appendix B to Subpart A of Part 230 -- Training Special Provisions

This Training Special Provision supersedes subparagraph 7b of the Special Provision entitled "Specific Equal Employment Opportunity Responsibilities," (Attachment 1), and is in implementation of 23 U.S.C. 140(a).

As part of the contractor's equal employment opportunity affirmative action program training shall be provided as follows:

The contractor shall provide on-the-job training aimed at developing full journeymen in the type of trade or job classification involved.

The number of trainees to be trained under the special provisions will be ____ (amount to be filled in by State highway department).

In the event that a contractor subcontracts a portion of the contract work, he shall determine how many, if any, of the trainees are to be trained by the subcontractor, provided, however, that the contractor shall retain the primary responsibility for meeting the training requirements imposed by this special provision. The contractor shall also insure that this training special provision is made applicable to such subcontract. Where feasible, 25 percent of apprentices or trainees in each occupation shall be in their first year of apprenticeship or training.

The number of trainees shall be distributed among the work classifications on the basis of the contractor's needs and the availability of journeymen in the various classifications within a reasonable area of recruitment. Prior to commencing construction, the contractor shall submit to the State highway agency for approval the number of trainees to be trained in each selected classification and training program to be used. Furthermore, the contractor shall specify the starting time for training in each of the classifications. The contractor will be credited for each trainee employed by him on the contract work who is currently enrolled or becomes enrolled in an approved program and will be reimbursed for such trainees as provided hereinafter.

Training and upgrading of minorities and women toward journeymen status is a primary objective of this Training Special Provision. Accordingly, the contractor shall make every effort to enroll minority trainees and women (e.g., by conducting systematic and direct recruitment through public and private sources likely to yield minority and women trainees) to the extent that such persons are available within a reasonable area of recruitment. The contractor will be responsible for demonstrating the steps that he has taken in pursuance thereof, prior to a determination as to whether the contractor is in compliance with this Training Special Provision. This training commitment is not intended, and shall not be used, to discriminate against any applicant for training, whether a member of a minority group or not.

No employee shall be employed as a trainee in any classification in which he has successfully completed a training course leading to journeyman status or in which he has been employed as a journeyman. The contractor should satisfy this requirement by including appropriate questions in the employee application or by other suitable means. Regardless of the method used the contractor's records should document the findings in each case.

The minimum length and type of training for each classification will be as established in the training program selected by the contractor and approved by the State highway agency and the Federal Highway Administration. The State highway agency and the Federal Highway Administration shall approve a program if it is reasonably calculated to meet the equal employment opportunity obligations of the contractor and to qualify the average trainee for journeyman status in the classification concerned by the end of the training period. Furthermore, apprenticeship programs registered with the U.S. Department of Labor, Bureau of Apprenticeship and Training, or with a State apprenticeship agency recognized by the Bureau and training programs approved but not necessarily sponsored by the U.S. Department of Labor, Manpower Administration, Bureau of Apprenticeship and Training shall also be considered acceptable provided it is being administered in a manner consistent with the equal employment obligations of Federal-aid highway construction contracts. Approval or acceptance of a training program shall be obtained from the State prior to commencing work on the classification covered by the program. It is the intention of these provisions that training is to be provided in the construction crafts rather than clerk-typists or secretarial-type positions. Training is permissible in lower level management positions such as office engineers, estimators, timekeepers, etc., where the training is oriented toward construction applications. Training in the laborer classification may be permitted provided that significant and meaningful training is provided and approved by the division office. Some offsite training is permissible as long as the training is an integral part of an approved training program and does not comprise a significant part of the overall training.

Except as otherwise noted below, the contractor will be reimbursed 80 cents per hour of training given an employee on this contract in accordance with an approved training program. As approved by the engineer, reimbursement will be made for training persons in excess of the number specified herein. This reimbursement will be made even though the contractor receives additional training program funds from other sources, provided such other does not specifically prohibit the contractor from receiving other reimbursement. Reimbursement for offsite training indicated above may only be made to the contractor where he does one or more of the following and the trainees are concurrently employed on a Federal-aid project; contributes to the cost of the training, provides the instruction to the trainee or pays the trainee's wages during the offsite training period.

No payment shall be made to the contractor if either the failure to provide the required training, or the failure to hire the trainee as a journeyman, is caused by the contractor and evidences a lack of good faith on the part of the contractor in meeting the requirements of this Training Special Provision. It is normally expected that a trainee will begin his training on the project as soon as feasible after start of work utilizing the skill involved and remain on the project as long as training opportunities exist in his work classification or until he has completed his training program. It is not required that all trainees be on board for the entire length of the contract. A contractor will have fulfilled his responsibilities under this Training Special Provision if he has provided acceptable training to the number of trainees specified. The number trained shall be determined on the basis of the total number enrolled on the contract for a significant period.

Trainees will be paid at least 60 percent of the appropriate minimum journeyman's rate specified in the contract for the first half of the training period, 75 percent for the third quarter of the training period, and 90 percent for the last quarter of the training period, unless apprentices or trainees in an approved existing program are enrolled as trainees on this project. In that case, the appropriate rates approved by the Departments of Labor or Transportation in connection with the existing program shall apply to all trainees being trained for the same classification who are covered by this Training Special Provision.

The contractor shall furnish the trainee a copy of the program he will follow in providing the training. The contractor shall provide each trainee with a certification showing the type and length of training satisfactorily completed.

The contractor will provide for the maintenance of records and furnish periodic reports documenting his performance under this Training Special Provision.

[40 FR 28053, July 3, 1975. Correctly redesignated at 46 FR 21156, Apr. 9, 1981]


Appendix C to Subpart A of Part 230

View or Download PDF



Appendix D to Subpart A of Part 230

View or Download PDF



General Information and Instructions

This form is to be developed from the "Contractor's Annual EEO Report." This data is to be compiled by the State and submitted annually. It should reflect the total employment on all Federal-Aid Highway Projects in the State as of July 31st. The staffing figures to be reported should represent the project work force on board in all or any part of the last payroll period preceding the end of July. The staffing figures to be reported in Table A should include journey-level men and women, apprentices, and on-the-job trainees. Staffing figures to be reported in Table B should include only apprentices and on-the-job trainees as indicated.

Entries made for "Job Categories" are to be confined to the listing shown. Miscellaneous job classifications are to be incorporated in the most appropriate category listed on the form. All employees on projects should thus be accounted for.

This information will be useful in complying with the U.S. Senate Committee on Public Works request that the Federal Highway Administration submit a report annually on the status of the Equal Employment Opportunity Program, its effectiveness, and progress made by the States and the Administration in carrying out section 22(A) of the Federal-Aid Highway Act of 1968. In addition, the form should be used as a valuable tool for States to evaluate their own programs for ensuring equal opportunity.

It is requested that States submit this information annually to the FHWA Divisions no later than September 25.

Line 01 -- State & Region Code. Enter the 4-digit code from the list below.

Alabama     01-04....................................  Montana 30-08
Alaska     02-10.................................... Nebraska 31-07
Arizona     04-09....................................  Nevada 32-09
Arkansas     05-06....................................    New 33-01
              Hampshir
                  e
California    06-09....................................    New 34-01
               Jersey
Colorado     08-08....................................    New 35-06
               Mexico
Delaware     10-03....................................   North 37-04
              Carolina
District of   11-03....................................   North 38-08
Columbia                           Dakota
Florida     12-04....................................   Ohio 39-05
Georgia     13-04.................................... Oklahoma 40-06
Hawaii     15-09....................................  Oregon 41-10
Idaho     16-10.................................... Pennsylv 42-03
                ania
Illinois     17-05....................................  Puerto 43-01
                Rico
Iowa     19-07....................................   South 45-04
              Carolina
Kansas     20-07....................................   South 46-08
               Dakota
Kentucky     21-04.................................... Tennesse 47-04
                  e
Louisiana    22-06....................................   Texas 48-06
Maine     23-01....................................   Utah 49-08
Maryland     24-03....................................  Vermont 50-01
Massachusetts  25-01.................................... Virginia 51-03
Michigan     26-05.................................... Washingt 53-10
                 on
Minnesota    27-05....................................   West 54-03
              Virginia
Mississippi   28-04.................................... Wisconsi 55-05
                  n
Missouri     29-07....................................  Wyoming 56-08
(23 U.S.C. sec. 140(a), 315, 49 CFR 1.48(b)) [44 FR 46832, Aug. 8, 1979. Correctly redesignated at 46 FR 21156, Apr. 9, 1981, and amended at 56 FR 4721, Feb. 6, 1991] Appendixes E-F to Subpart A of Part 230 [Reserved]

Appendix G to Subpart A of Part 230 -- Special Reporting Requirements for "Hometown" or "Imposed" Plan Areas

In addition to the reporting requirements set forth elsewhere in this contract the contractor and the subcontractors holding subcontracts, not including material suppliers, of $10,000 or more, shall submit for every month of July during which work is performed, employment data as contained under Form PR-1391 (appendix C to 23 CFR part 230) and in accordance with the instructions included thereon.

[40 FR 28053, July 3, 1975. Correctly redesignated at 46 FR 21156, Apr. 9, 1981]


Subpart B -- Supportive Services for Minority, Disadvantaged, and Women Business Enterprises


Source: 50 FR 51243, Dec. 16, 1985, unless otherwise noted.


§230.201   Purpose.

To prescribe the policies, procedures, and guidance to develop, conduct, and administer supportive services assistance programs for minority, disadvantaged, and women business enterprises.


§230.202   Definitions.

(a) Minority Business Enterprise, as used in this subpart, refers to all small businesses which participate in the Federal-aid highway program as a minority business enterprise (MBE), women business enterprise (WBE), or disadvantaged business enterprise (DBE), all defined under 49 CFR part 23. This expanded definition is used only in this subpart as a simplified way of defining the firms eligible to benefit from this supportive services program.

(b) Supportive Services means those services and activities provided in connection with minority business enterprise programs which are designed to increase the total number of minority businesses active in the highway program and contribute to the growth and eventual self-sufficiency of individual minority businesses so that such businesses may achieve proficiency to compete, on an equal basis, for contracts and subcontracts.

(c) State highway agency means that department, commission, board, or official of any State charged by its laws with the responsibility for highway construction. The term State is considered equivalent to State highway agency if the context so implies.


§230.203   Policy.

Based on the provisions of Pub. L. 97-424, dated January 6, 1983, it is the policy of the Federal Highway Administration (FHWA) to promote increased participation of minority business enterprises in Federal-aid highway contracts in part through the development and implementation of cost effective supportive services programs through the State highway agencies.


§230.204   Implementation of supportive services.

(a) Subject to the availability of funds under 23 U.S.C. 140(c), the State highway agency shall establish procedures to develop, conduct, and administer minority business enterprise training and assistance programs specifically for the benefit of women and minority businesses. Supportive services funds allocated to the States shall not be used to finance the training of State highway agency employees or to provide services in support of such training. State highway agencies are not required to match funds allocated to them under this section. Individual States are encouraged to be actively involved in the provision of supportive services. Such involvement can take the form of staff, funding, and/or direct assistance to augment the supportive services efforts financed by Federal-aid funds.

(b) State highway agencies shall give preference to the following types of services:

(1) Services relating to identification, prequalification, and certification assistance, with emphasis on increasing the total number of legitimate minority business enterprises participating in the Federal-aid highway program;

(2) Services in connection with estimating, bidding, and technical assistance designed to develop and improve the capabilities of minority businesses and assist them in achieving proficiency in the technical skills involved in highway construction;

(3) Services designed to develop and improve the immediate and long-term business management, recordkeeping, and financial accounting capabilities;

(4) Services to assist minority business enterprises to become eligible for and to obtain bonding and financial assistance;

(5) Services relating to verification procedures to ensure that only bona fide minority business enterprises are certified as eligible for participation in the Federal-aid highway program;

(6) Follow-up services to ascertain the outcome of training and assistance being provided; and

(7) Other services which contribute to long-term development, increased opportunities, and eventual self-sufficiency of minority business enterprises.

(c) A detailed work statement of the supportive services which the State highway agency considers to meet the guidance under this regulation and a program plan for meeting the requirements of paragraph (b) of this section and accomplishing other objectives shall be submitted to the FHWA for approval.

(d) State highway agencies which desire to provide or obtain services other than those listed in paragraph (b) of this section shall submit their proposals to the FHWA for approval.

(e) When the State highway agency provides supportive services by contract, formal advertising is not required by FHWA; however, the State highway agency shall solicit proposals from such qualified sources as will assure the competitive nature of the procurement. The evaluation of proposals by the State highway agency must include consideration of the proposer's ability to effect a productive relationship with majority and minority contractors, contractors' associations, minority groups, and other persons or organizations whose cooperation and assistance will increase the opportunities for minority business enterprises to compete for and perform contracts and subcontracts.

(f) In the selection of contractors to perform supportive services, State highway agencies shall make conscientious efforts to search out, and utilize the services of qualified minority or women organizations, or minority or women enterprises.

(g) As a minimum, State highway agency contracts to obtain supportive services shall include the following provisions:

(1) A statement that a primary purpose of the supportive services is to increase the total number of minority firms participating in the Federal-aid highway program and to contribute to the growth and eventual self-sufficiency of minority firms;

(2) A statement that supportive services shall be provided only to those minority business enterprises determined to be eligible for participation in the Federal-aid highway program in accordance with 49 CFR part 23 and have a work specialty related to the highway construction industry;

(3) A clear and complete statement of the services to be provided under the contract, such as technical assistance, managerial assistance, counseling, certification assistance, and follow-up procedures as set forth in §230.204(b) of this part;

(4) The nondiscrimination provisions required by Title VI of the Civil Rights Act of 1964 as set forth in Form FHWA-1273, Required Contract Provisions, Federal-Aid Construction Contracts, 1 and a statement of nondiscrimination in employment because of race, color, religion, sex, or national origin;

1Form FHWA-1273 is available for inspection and copying at the locations given in 49 CFR part 7, appendix D, under Document Inspection Facilities, and at all State highway agencies.

(5) The establishment of a definite period of contract performance together with, if appropriate, a schedule stating when specific supportive services are to be provided;

(6) Monthly or quarterly reports to the State highway agency containing sufficient data and narrative content to enable evaluation of both progress and problems;

(7) The basis of payment;

(8) An estimated schedule for expenditures;

(9) The right of access to records and the right to audit shall be granted to authorize State highway agency and FHWA officials;

(10) Noncollusion certification;

(11) A requirement that the contractor provide all information necessary to support progress payments if such are provided for in the contract; and

(12) A termination clause.

(h) The State highway agency is to furnish copies of the reports received under paragraph(g)(6) of this section to the FHWA division office.

[50 FR 51243, Dec. 16, 1985, as amended at 52 FR 36922, Oct. 2, 1987]



§230.205   Supportive services funds obligation.

Supportive services funds shall be obligated in accordance with the procedures set forth in §230.117(b) of this part. The point of obligation is defined as that time when the FHWA has approved a detailed work statement for the supportive services.


§230.206   Monitoring supportive services.

Supportive services programs shall be continually monitored and evaluated by the State highway agency so that needed improvements can be identified and instituted. This requires the documentation of valid effectiveness measures by which the results of program efforts may be accurately assessed.


§230.207   Sources of assistance.

It is the policy of the FHWA that all potential sources of assistance to minority business enterprises be utilized. The State highway agency shall take actions to ensure that supportive services contracts reflect the availability of all sources of assistance in order to maximize resource utilization and avoid unnecessary duplication.

Subpart C -- State Highway Agency Equal Employment Opportunity Programs


Source: 41 FR 28270, July 9, 1976, unless otherwise noted.


§230.301   Purpose.

The purpose of the regulations in this subpart is to set forth Federal Highway Administration (FHWA) Federal-aid policy and FHWA and State responsibilities relative to a State highway agency's internal equal employment opportunity program and for assuring compliance with the equal employment opportunity requirements of federally-assisted highway construction contracts.


§230.303   Applicability.

The provisions of this subpart are applicable to all States that receive Federal financial assistance in connection with the Federal-aid highway program.


§230.305   Definitions.

As used in this subpart, the following definitions apply:

(a) Affirmative Action Plan means:

(1) With regard to State highway agency work forces, a written document detailing the positive action steps the State highway agency will take to assure internal equal employment opportunity (internal plan).

(2) With regard to Federal-aid construction contract work forces, the Federal equal employment opportunity bid conditions, to be enforced by a State highway agency in the plan areas established by the Secretary of Labor and FHWA special provisions in nonplan areas (external plan).

(b) Equal employment opportunity program means the total State highway agency program, including the affirmative action plans, for ensuring compliance with Federal requirements both in State highway agency internal employment and in employment on Federal-aid construction projects.

(c) Minority groups. An employee may be included in the minority group to which he or she appears to belong, or is regarded in the community as belonging. As defined by U.S. Federal agencies for employment purposes, minority group persons in the U.S. are identified as Blacks (not of Hispanic origin), Hispanics, Asian or Pacific Islanders, and American Indians or Alaskan Natives.

(d) Racial/ethnic identification. For the purpose of this regulation and any accompanying report requirements, an employee may be included in the group to which he or she appears to belong, identifies with, or is regarded in the community as belonging. However, no person should be counted in more than one racial/ethnic category. The following group categories will be used:

(1) The category White (not of Hispanic origin): All persons having origins in any of the original peoples of Europe, North Africa, the Middle East, or the Indian Subcontinent.

(2) The category Black (not of Hispanic origin): All persons having origins in any of the Black racial groups.

(3) The category Hispanic: All persons of Mexican, Puerto Rican, Cuban, Central or South American, or other Spanish culture or origin, regardless of race.

(4) The category Asian or Pacific Islanders: All persons having origins in any of the original peoples of the Far East, Southeast Asia, or the Pacific Islands. This area includes, for example, China, Japan, Korea, the Philippine Islands, and Samoa.

(5) The category American Indian or Alaskan Native: All persons having origins in any of the original peoples of North America.

(e) State means any of the 50 States of the United States, the District of Columbia, the Commonwealth of Puerto Rico, Guam, American Samoa, and the Virgin Islands.

(f) State highway agency means that department, commission, board, or official of any State charged by its laws with the responsibility for highway construction. The term State should be considered equivalent to State highway agency if the context so implies.

[41 FR 28270, July 9, 1976, as amended at 41 FR 46293, Oct. 20, 1976]



§230.307   Policy.

Every employee and representative of State highway agencies shall perform all official equal employment opportunity actions in an affirmative manner, and in full accord with applicable statutes, executive orders, regulations, and policies enunciated thereunder, to assure the equality of employment opportunity, without regard to race, color, religion, sex, or national origin both in its own work force and in the work forces of contractors, subcontractors, and material suppliers engaged in the performance of Federal-aid highway construction contracts.


§230.309   Program format.

It is essential that a standardized Federal approach be taken in assisting the States in development and implementation of EEO programs. The format set forth in appendix A provides that standardized approach. State equal employment opportunity programs that meet or exceed the prescribed standards will comply with basic FHWA requirements.


§230.311   State responsibilities.

(a) Each State highway agency shall prepare and submit an updated equal employment opportunity program, one year from the date of approval of the preceding program by the Federal Highway Administrator, over the signature of the head of the State highway agency, to the Federal Highway Administrator through the FHWA Division Administrator. The program shall consist of the following elements:

(1) The collection and analysis of internal employment data for its entire work force in the manner prescribed in part II, paragraph III of appendix A; and

(2) The equal employment opportunity program, including the internal affirmative action plan, in the format and manner set forth in appendix A.

(b) In preparation of the program required by §230.311(a), the State highway agency shall consider and respond to written comments from FHWA regarding the preceding program.


§230.313   Approval procedure.

After reviewing the State highway agency equal employment opportunity program and the summary analysis and recommendations from the FHWA regional office, the Washington Headquarters Office of Civil Rights staff will recommend approval or disapproval of the program to the Federal Highway Administrator. The State highway agency will be advised of the Administrator's decision. Each program approval is effective for a period of one year from date of approval.

Appendix A to Subpart C of Part 230 -- State Highway Agency Equal Employment Opportunity Programs

Each State highway agency's (SHA) equal employment opportunity (EEO) program shall be in the format set forth herein and shall address Contractor Compliance (part I) and SHA Internal Employment (part II), including the organizational structure of the SHA total EEO Program (internal and external).

PART I -- CONTRACTOR COMPLIANCE

I. Organization and structure. A. Statehighway agency EEO Coordinator (External) and staff support. 1. Describe the organizational location and responsibilities of the State highway agency EEO Coordinator. (Provided organization charts of the State highway agency and of the EEO staff.)

2. Indicate whether full or part-time; if part-time, indicate percentage of time devoted to EEO.

3. Indicate length of time in position, civil rights experience and training, and supervision.

4. Indicate whether compliance program is centralized or decentralized.

5. Identify EEO Coordinator's staff support (full- and part-time) by job title and indicate areas of their responsibilities.

6. Identify any other individuals in the central office having a responsibility for the implementation of this program and describe their respective roles and training received in program area.

B. District or division personnel. 1. Describe the responsibilities and duties of any district EEO personnel. Identify to whom they report.

2. Explain whether district EEO personnel are full-time or have other responsibilities such as labor compliance or engineering.

3. Describe training provided for personnel having EEO compliance responsibility.

C. Project personnel. Describe the EEO role of project personnel.

II. Compliance procedures. A. Applicable directives. 1. FHWA Contract Compliance Procedures.

2. EEO Special Provisions (FHWA Federal-Aid Highway Program Manual, vol. 6, chap. 4, sec. 1, subsec. 2, Attachment 1) 1

1The Federal-Aid Highway Program Manual is available for inspection and copying at the Federal Highway Administration (FHWA), 400 7th St., SW., Washington, DC 20590, or at FHWA offices listed in 49 CFR part 7, appendix D.

3. Training Special Provisions (FHWA Federal-Aid Highway Program Manual, vol. 6, chap. 4, sec. 1, subsec. 2, Attachment 2) 1

4. FHWA Federal-Aid Highway Program Manual, vol. 6, chap. 4, sec. 1, subsec. 6 (Contract Procedures), and subsec. 8 (Minority Business Enterprise). 1

B. Implementation. 1. Describe process (methods) of incorporating the above FHWA directives into the SHA compliance program.

2. Describe the methods used by the State to familiarize State compliance personnel with all FHWA contract compliance directives. Indicate frequency of work shops, training sessions, etc.

3. Describe the procedure for advising the contractor of the EEO contract requirements at any preconstruction conference held in connection with a Federal-aid contract.

III. Accomplishments. Describe accomplishments in the construction EEO compliance program during the past fiscal year.

A. Regular project compliance review program. This number should include at least all of the following items:

1. Number of compliance reviews conducted.

2. Number of contractors reviewed.

3. Number of contractors found in compliance.

4. Number of contractors found in noncompliance.

5. Number of show cause notices issued.

6. Number of show cause notices rescinded.

7. Number of show cause actions still under conciliation and unresolved.

8. Number of followup reviews conducted.

(Note: In addition to information requested in items 4-8 above, include a brief summary of total show cause and followup activities -- findings and achievements.)

B. Consolidated compliance reviews. 1. Identify the target areas that have been reviewed since the inception of the consolidated compliance program. Briefly summarize total findings.

2. Identify any significant impact or effect of this program on contractor compliance.

C. Home office reviews. If the State conducts home office reviews, describe briefly the procedures followed by State.

D. Major problems encountered. Describe major problems encountered in connection with any review activities during the past fiscal year.

E. Major breakthroughs. Comment briefly on any major breakthrough or other accomplishment significant to the compliance review program.

IV. Areawide plans/Hometown and Imposed (if applicable). A. Provide overall analysis of the effectiveness of each areawide plan in the State.

B. Indicate by job titles the number of State personnel involved in the collection, consolidation, preparation, copying, reviewing, analysis, and transmittal of area plan reports (Contracting Activity and Post Contract Implementation). Estimate the amount of time (number of hours) spent collectively on this activity each month. How does the State use the plan report data?

C. Identify Office of Federal Contract Compliance Programs (OFCCP) area plan audits or compliance checks in which State personnel participated during the last fiscal year. On the average, how many hours have been spent on these audits and/or checks during the past fiscal year?

D. Describe the working relationship of State EEO compliance personnel with representatives of plan administrative committee(s).

E. Provide recommendations for improving the areawide plan program and the reporting system.

V. Contract sanctions. A. Describe the procedures used by the State to impose contract sanctions or institute legal proceedings.

B. Indicate the State or Federal laws which are applicable.

C. Does the State withhold a contractor's progress payments for failure to comply with EEO requirements? If so, identify contractors involved in such actions during the past fiscal year. If not, identify other actions taken.

VI. Complaints. A. Describe the State's procedures for handling discrimination complaints against contractors.

B. If complaints are referred to a State fair employment agency or similar agency, describe the referral procedure.

C. Identify the Federal-aid highway contractors that have had discrimination complaints filed against them during the past fiscal year and provide current status.

VII. External training programs, including supportive services. A. Describe the State's process for reviewing the work classifications of trainees to determine that there is a proper and reasonable distribution among appropriate craft.

B. Describe the State's procedures for identifying the number of minorities and women who have completed training programs.

C. Describe the extent of participation by women in construction training programs.

D. Describe the efforts made by the State to locate and use the services of qualified minority and female supportive service consultants. Indicate if the State's supportive service contractor is a minority or female owned enterprise.

E. Describe the extent to which reports from the supportive service contractors provide sufficient data to evaluate the status of training programs, with particular reference to minorities and women.

VIII. Minority business enterprise program. FHPM 6-4-1-8 sets forth the FHWA policy regarding the minority business enterprise program. The implementation of this program should be explained by responding to the following:

A. Describe the method used for listing of minority contractors capable of, or interested in, highway construction contracting or subcontracting. Describe the process used to circulate names of appropriate minority firms and associations to contractors obtaining contract proposals.

B. Describe the State's procedure for insuring that contractors take action to affirmatively solicit the interest, capability, and prices of potential minority subcontractors.

C. Describe the State's procedure for insuring that contractors have designated liaison officers to administer the minority business enterprise program in an effective manner. Specify resource material, including contracts, which the State provides to liaison officers.

D. Describe the action the State has taken to meet its goals for prequalification or licensing of minority business. Include dollar goals established for the year, and describe what criteria or formula the State has adopted for setting such goals. If it is different from the previous year, describe in detail.

E. Outline the State's procedure for evaluating its prequalification/licensing requirements.

F. Identify instances where the State has waived prequalification for subcontractors on Federal-aid construction work or for prime contractors on Federal-aid contracts with an estimated dollar value lower than $100,000.

G. Describe the State's methods of monitoring the progress and results of its minority business enterprise efforts.

IX. Liaison. Describe the liaison established by the State between public (State, county, and municpal) agencies and private organizations involved in EEO programs. How is the liaison maintained on a continuing basis?

X. Innovative programs. Identify any innovative EEO programs or management procedures initiated by the State and not previously covered.

PART II -- STATE HIGHWAY AGENCY EMPLOYMENT

I. General. The State highway agency's (SHA) internal program is an integral part of the agency's total activities. It should include the involvement, commitment and support of executives, managers, supervisors and all other employees. For effective administration and implementation of the EEO Program, an affirmative action plan (AAP) is required. The scope of an EEO program and an AAP must be comprehensive, covering all elements of the agency's personnel management policies and practices. The major part of an AAP must be recognition and removal of any barriers to equal employment opportunity, identification of problem areas and of persons unfairly excluded or held back and action enabling them to compete for jobs on an equal basis. An effective AAP not only benefits those who have been denied equal employment opportunity but will also greatly benefit the organization which often has overlooked, screened out or underutilized the great reservoir of untapped human resources and skills, especially among women and minority groups.

Set forth are general guidelines designed to assist the State highway agencies in implementing internal programs, including the development and implementation of AAP's to ensure fair and equal treatment for all persons, regardless of race, color, religion, sex or national origin in all employment practices.

II. Administration and implementation. The head of each State highway agency is responsible for the overall administration of the internal EEO program, including the total integration of equal opportunity into all facets of personnel management. However, specific program responsibilities should be assigned for carrying out the program at all management levels.

To ensure effectiveness in the implementation of the internal EEO program, a specific and realistic AAP should be developed. It should include both short and long-range objectives, with priorities and target dates for achieving goals and measuring progress, according to the agency's individual need to overcome existing problems.

A. State Highway Agency Affirmative Action Officer (internal). 1. Appointment of Affirmative Action Officer. The head of the SHA should appoint a qualified Affirmative Action (AA) Officer (Internal EEO Officer) with responsibility and authority to implement the internal EEO program. In making the selection, the following factors should be considered:

a. The person appointed should have proven ability to accomplish major program goals.

b. Managing the internal EEO program requires a major time commitment; it cannot be added on to an existing full-time job.

c. Appointing qualified minority and/or female employees to head or staff the program may offer good role models for present and potential employees and add credibility to the programs involved. However, the most essential requirements for such position(s) are sensitivity to varied ways in which discrimination limits job opportunities, commitment to program goals and sufficient status and ability to work with others in the agency to achieve them.

2. Responsibilities of the Affirmative Action Officer. The responsibilities of the AA Officer should include, but not necessarily be limited to:

a. Developing the written AAP.

b. Publicizing its content internally and externally.

c. Assisting managers and supervisors in collecting and analyzing employment data, identifying problem areas, setting goals and timetables and developing programs to achieve goals. Programs should include specific remedies to eliminate any discriminatory practices discovered in the employment system.

d. Handling and processing formal discrimination complaints.

e. Designing, implementing and monitoring internal audit and reporting systems to measure program effectiveness and to determine where progress has been made and where further action is needed.

f. Reporting, at least quarterly, to the head of the SHA on progress and deficiencies of each unit in relation to agency goals.

g. In addition, consider the creation of:

(1) An EEO Advisory Committee, whose membership would include top management officials,

(2) An EEO Employee Committee, whose membership would include rank and file employees, with minority and female representatives from various job levels and departments to meet regularly with the AA officer, and

(3) An EEO Counseling Program to attempt informal resolution of discrimination complaints.

B. Contents of an affirmative action plan. The Affirmative Action Plan (AAP) is an integral part of the SHA's EEO program. Although the style and format of AAP's may vary from one SHA to another, the basic substance will generally be the same. The essence of the AAP should include, but not necessarily be limited to:

1. Inclusion of a strong agency policy statement of commitment to EEO.

2. Assignment of responsibility and authority for program to a qualified individual.

3. A survey of the labor market area in terms of population makeup, skills, and availability for employment.

4. Analyzing the present work force to identify jobs, departments and units where minorities and females are underutilized.

5. Setting specific, measurable, attainable hiring and promotion goals, with target dates, in each area of underutilization.

6. Making every manager and supervisor responsible and accountable for meeting these goals.

7. Reevaluating job descriptions and hiring criteria to assure that they reflect actual job needs.

8. Finding minorities and females who are qualified or qualifiable to fill jobs.

9. Getting minorities and females into upward mobility and relevant training programs where they have not had previous access.

10. Developing systems to monitor and measure progress regularly. If results are not satisfactory to meet goals, determine the reasons and make necessary changes.

11. Developing a procedure whereby employees and applicants may process allegations of discrimination to an impartial body without fear of reprisal.

C. Implementation of an affirmative action plan. The written AAP is the framework and management tool to be used at all organizational levels to actively implement, measure and evaluate program progress on the specific action items which represent EEO program problems or deficiencies. The presence of a written plan alone does not constitute an EEO program, nor is it, in itself, evidence of an ongoing program. As a minimum, the following specific actions should be taken.

1. Issue written equal employment opportunity policy statement and affirmative action commitment. To be effective, EEO policy provisions must be enforced by top management, and all employees must be made aware that EEO is basic agency policy. The head of the SHA (1) should issue a firm statement of personal commitment, legal obligation and the importance of EEO as an agency goal, and (2) assign specific responsibility and accountability to each executive, manager and supervisor.

The statement should include, but not necessarily be limited to, the following elements:

a. EEO for all persons, regardless of race, color, religion, sex or national origin as a fundamental agency policy.

b. Personal commitment to and support of EEO by the head of the SHA.

c. The requirement that special affirmative action be taken throughout the agency to overcome the effects of past discrimination.

d. The requirement that the EEO program be a goal setting program with measurement and evaluation factors similar to other major agency programs.

e. Equal opportunity in all employment practices, including (but not limited to) recruiting, hiring, transfers, promotions, training, compensation, benefits, recognition (awards), layoffs, and other terminations.

f. Responsibility for positive affirmative action in the discharge of EEO programs, including performance evaluations of managers and supervisors in such functions, will be expected of and shared by all management personnel.

g. Accountability for action or inaction in the area of EEO by management personnel.

2. Publicize the affirmative action plan. a. Internally: (1) Distribute written communications from the head of the SHA.

(2) Include the AAP and the EEO policy statement in agency operations manual.

(3) Hold individual meetings with managers and supervisors to discuss the program, their individual responsibilities and to review progress.

(4) Place Federal and State EEO posters on bulletin boards, near time clocks and in personnel offices.

(5) Publicize the AAP in the agency newsletters and other publications.

(6) Present and discuss the AAP as a part of employee orientation and all training programs.

(7) Invite employee organization representatives to cooperate and assist in developing and implementing the AAP.

b. Externally: Distribute the AAP to minority groups and women's organizations, community action groups, appropriate State agencies, professional organizations, etc.

3. Develop and implement specific programs to eliminate discriminatory barriers and achieve goals. a. Job structuring and upward mobility: The AAP should include specific provisions for:

(1) Periodic classification plan reviews to correct inaccurate position descriptions and to ensure that positions are allocated to the appropriate classification.

(2) Plans to ensure that all qualification requirements are closely job related.

(3) Efforts to restructure jobs and establish entry level and trainee positions to facilitate progression within occupational areas.

(4) Career counseling and guidance to employees.

(5) Creating career development plans for lower grade employees who are underutilized or who demonstrate potential for advancement.

(6) Widely publicizing upward mobility programs and opportunities within each work unit and within the total organizational structure.

b. Recruitment and placement. The AAP should include specific provisions for, but not necessarily limited to:

(1) Active recruitment efforts to support and supplement those of the central personnel agency or department, reaching all appropriate sources to obtain qualified employees on a nondiscriminatory basis.

(2) Maintaining contracts with organizations representing minority groups, women, professional societies, and other sources of candidates for technical, professional and management level positions.

(3) Ensuring that recruitment literature is relevant to all employees, including minority groups and women.

(4) Reviewing and monitoring recruitment and placement procedures so as to assure that no discriminatory practices exist.

(5) Cooperating with management and the central personnel agency on the review and validation of written tests and other selection devices.

(6) Analyzing the flow of applicants through the selection and appointment process, including an analytical review of reasons for rejections.

(7) Monitoring the placement of employees to ensure the assignment of work and workplace on a nondiscriminatory basis.

c. Promotions. The AAP should include specific provisions for, but not necessarily limited to:

1. Establishing an agency-wide merit promotion program, including a merit promotion plan, to provide equal opportunity for all persons based on merit and without regard to race, color, religion, sex or national origin.

2. Monitoring the operation of the merit promotion program, including a review of promotion actions, to assure that requirements procedures and practices support EEO program objectives and do not have a discriminatory impact in actual operation.

3. Establishing skills banks to match employee skills with available job advancement opportunities.

4. Evaluating promotion criteria (supervisory evaluations, oral interviews, written tests, qualification standards, etc.) and their use by selecting officials to identify and eliminate factors which may lead to improper "selection out" of employees or applicants, particularly minorities and women, who traditionally have not had access to better jobs. It may be appropriate to require selecting officials to submit a written justification when well qualified persons are passed over for upgrading or promotion.

5. Assuring that all job vacancies are posted conspicuously and that all employees are encouraged to bid on all jobs for which they feel they are qualified.

6. Publicizing the agency merit promotion program by highlighting breakthrough promotions, i.e. advancement of minorities and women to key jobs, new career heights, etc.

d. Training. The AAP should include specific provisions for, but not necessarily limited to:

(1) Requiring managers and supervisors to participate in EEO seminars covering the AAP, the overall EEO program and the administration of the policies and procedures incorporated therein, and on Federal, State and local laws relating to EEO.

(2) Training in proper interviewing techniques of employees who conduct employment selection interviews.

(3) Training and education programs designed to provide opportunities for employees to advance in relation to the present and projected manpower needs of the agency and the employees' career goals.

(4) The review of profiles of training course participants to ensure that training opportunities are being offered to all eligible employees on an equal basis and to correct any inequities discovered.

e. Layoffs, recalls, discharges, demotions, and disciplinary actions. The standards for deciding when a person shall be terminated, demoted, disciplined, laid off or recalled should be the same for all employees, including minorities and females. Seemingly neutral practices should be reexamined to see if they have a disparate effect on such groups. For example, if more minorities and females are being laid off because they were the last hired, then, adjustments should be made to assure that the minority and female ratios do not decrease because of these actions.

(1) When employees, particularly minorities and females, are disciplined, laid off, discharged or downgraded, it is advisable that the actions be reviewed by the AA Officer before they become final.

(2) Any punitive action (i.e. harassment, terminations, demotions), taken as a result of employees filing discrimination complaints, is illegal.

(3) The following records should be kept to monitor this area of the internal EEO program:

On all terminations, including layoffs and discharges: indicate total number, name, (home address and phone number), employment date, termination date, recall rights, sex, racial/ethnic identification (by job category), type of termination and reason for termination.

On all demotions: indicate total number, name, (home address and phone number), demotion date, sex, racial/ethnic identification (by job category), and reason for demotion.

On all recalls: indicate total number, name, (home address and phone number) recall date, sex, and racial/ethnic identification (by job category).

Exit interviews should be conducted with employees who leave the employment of the SHA.

f. Other personnel actions. The AAP should include specific provisions for, but not necessarily limited to:

(1) Assuring that information on EEO counseling and grievance procedures is easily available to all employees.

(2) A system for processing complaints alleging discrimination because of race, color, religion, sex or national origin to an impartial body.

(3) A system for processing grievances and appeals (i.e. disciplinary actions, adverse actions, adverse action appeals, etc).

(4) Including in the performance appraisal system a factor to rate manager's and supervisors' performance in discharging the EEO program responsibilities assigned to them.

(5) Reviewing and monitoring the performance appraisal program periodically to determine its objectivity and effectiveness.

(6) Ensuring the equal availability of employee benefits to all employees.

4. Program evaluation. An internal reporting system to continually audit, monitor and evaluate programs is essential for a successful AAP. Therefore, a system providing for EEO goals, timetables, and periodic evaluations needs to be established and implemented. Consideration should be given to the following actions:

a. Defining the major objectives of EEO program evaluation.

b. The evaluation should be directed toward results accomplished, not only at efforts made.

c. The evaluation should focus attention on assessing the adequacy of problem identification in the AAP and the extent to which the specific action steps in the plan provide solutions.

d. The AAP should be reviewed and evaluated at least annually. The review and evaluation procedures should include, but not be limited to, the following:

(1) Each bureau, division or other major component of the agency should make annual and such other periodic reports as are needed to provide an accurate review of the operations of the AAP in that component.

(2) The AA Officer should make an annual report to the head of the SHA, containing the overall status of the program, results achieved toward established objectives, identity of any particular problems encountered and recommendations for corrective actions needed.

e. Specific, numerical goals and objectives should be established for the ensuing year. Goals should be developed for the SHA as a whole, as well as for each unit and each job category.

III. Employment statistical data. A. As a minimum, furnish the most recent data on the following:

1. The total population in the State,

2. The total labor market in State, with a breakdown by racial/ethnic identification and sex, and

3. An analysis of (1) and (2) above, in connection with the availability of personnel and jobs within SHA's.

B. State highway agencies shall use the EEO-4 Form in providing current work force data. This data shall reflect only State department of transportation/State highway department employment.

View or Download PDF



View or Download PDF



[41 FR 28270, July 9, 1976, as amended at 41 FR 46294, Oct. 20, 1976]

Subpart D -- Construction Contract Equal Opportunity Compliance Procedures


Source: 41 FR 34239, Aug. 13, 1976, unless otherwise noted.


§230.401   Purpose.

The purpose of the regulations in this subpart is to prescribe policies and procedures to standardize the implementation of the equal opportunity contract compliance program, including compliance reviews, consolidated compliance reviews, and the administration of areawide plans.


§230.403   Applicability.

The procedures set forth hereinafter apply to all nonexempt direct Federal and Federal-aid highway construction contracts and subcontracts, unless otherwise specified.


§230.405   Administrative responsibilities.

(a) Federal Highway Administration (FHWA) responsibilities. (1) The FHWA has the responsibility to ensure that contractors meet contractural equal opportunity requirements under E.O. 11246, as amended, and title 23 U.S.C., and to provide guidance and direction to States in the development and implementation of a program to assure compliance with equal opportunity requirements.

(2) The Federal Highway Administrator or a designee may inquire into the status of any matter affecting the FHWA equal opportunity program and, when considered necessary, assume jurisdiction over the matter, proceeding in coordination with the State concerned. This is without derogation of the authority of the Secretary of Transportation, Department of Transportation (DOT), the Director, DOT Departmental Office of Civil Rights (OCR) or the Director, Office of Federal Contract Compliance Programs (OFCCP), Department of Labor.

(3) Failure of the State highway agency (SHA) to discharge the responsibilities stated in §230.405(b)(1) may result in DOT's taking any or all of the following actions (see appendix A to 23 CFR part 630, subpart C "Federal-aid project agreement"):

(i) Cancel, terminate, or suspend the Federal-aid project agreement in whole or in part;

(ii) Refrain from extending any further assistance to the SHA under the program with respect to which the failure or refusal occurred until satisfactory assurance of future compliance has been received from the SHA; and

(iii) Refer the case to an appropriate Federal agency for legal proceedings.

(4) Action by the DOT, with respect to noncompliant contractors, shall not relieve a SHA of its responsibilities in connection with these same matters; nor is such action by DOT a substitute for corrective action utilized by a State under applicable State laws or regulations.

(b) State responsibilities. (1) The SHA's, as contracting agencies, have a responsibility to assure compliance by contractors with the requirements of Federal-aid construction contracts, including the equal opportunity requirements, and to assist in and cooperate with FHWA programs to assure equal opportunity.

(2) The corrective action procedures outlined herein do not preclude normal contract administration procedures by the States to ensure the contractor's completion of specific contract equal opportunity requirements, as long as such procedures support, and sustain the objectives of E.O. 11246, as amended. The State shall inform FHWA of any actions taken against a contractor under normal State contract administration procedures, if that action is precipitated in whole or in part by noncompliance with equal opportunity contract requirements.


§230.407   Definitions.

For the purpose of this subpart, the following definitions shall apply, unless the context requires otherwise:

(a) Actions, identified by letter and number, shall refer to those items identified in the process flow chart. (Appendix D);

(b) Affirmative Action Plan means a written positive management tool of a total equal opportunity program indicating the action steps for all organizational levels of a contractor to initiate and measure equal opportunity program progress and effectiveness. (The Special Provisions [23 CFR part 230 A, appendix A] and areawide plans are Affirmative Action Plans.);

(c) Affirmative Actions means the efforts exerted towards achieving equal opportunity through positive, aggressive, and continuous result-oriented measures to correct past and present discriminatory practices and their effects on the conditions and privileges of employment. These measures include, but are not limited to, recruitment, hiring, promotion, upgrading, demotion, transfer, termination, compensation, and training;

(d) Areawide Plan means an Affirmative Action Plan approved by the Department of Labor to increase minority and female utilization in crafts of the construction industry in a specified geographical area pursuant to E.O. 11246, as amended, and taking the form of either a "Hometown" or an "Imposed" Plan.

(1) Hometown Plan means a voluntary areawide agreement usually developed by representatives of labor unions, minority organizations, and contractors, and approved by the OFCCP for the purpose of implementing the equal employment opportunity requirements pursuant to E.O. 11246, as amended;

(2) Imposed Plan means mandatory affirmative action requirements for a specified geographical area issued by OFCCP and, in some areas, by the courts;

(e) Compliance Specialist means a Federal or State employee regularly employed and experienced in civil rights policies, practices, procedures, and equal opportunity compliance review and evaluation functions;

(f) Consolidated Compliance Review means a review and evaluation of all significant construction employment in a specific geographical (target) area;

(g) Construction shall have the meanings set forth in 41 CFR 60-1.3(e) and 23 U.S.C. 101(a). References in both definitions to expenses or functions incidental to construction shall include preliminary engineering work in project development or engineering services performed by or for a SHA;

(h) Corrective Action Plan means a contractor's unequivocal written and signed commitment outlining actions taken or proposed, with time limits and goals, where appropriate to correct, compensate for, and remedy each violation of the equal opportunity requirements as specified in a list of deficiencies. (Sometimes called a conciliation agreement or a letter of commitment.);

(i) Contractor means, any person, corporation, partnership, or unincorporated association that holds a FHWA direct or federally assisted construction contract or subcontract regardless of tier;

(j) Days shall mean calendar days;

(k) Discrimination means a distinction in treatment based on race, color, religion, sex, or national origin;

(l) Equal Employment Opportunity means the absence of partiality or distinction in employment treatment, so that the right of all persons to work and advance on the basis of merit, ability, and potential is maintained;

(m) Equal Opportunity Compliance Review means an evaluation and determination of a nonexempt direct Federal or Federal-aid contractor's or subcontractor's compliance with equal opportunity requirements based on:

(1) Project work force -- employees at the physical location of the construction activity;

(2) Area work force -- employees at all Federal-aid, Federal, and non-Federal projects in a specific geographical area as determined under §230.409 (b)(9); or

(3) Home office work force -- employees at the physical location of the corporate, company, or other ownership headquarters or regional managerial, offices, including "white collar" personnel (managers, professionals, technicians, and clericals) and any maintenance or service personnel connected thereto;

(n) Equal Opportunity Requirements is a general term used throughout this document to mean all contract provisions relative to equal employment opportunity (EEO), subcontracting, and training;

(o) Good Faith Effort means affirmative action measures designed to implement the established objectives of an Affirmative Action Plan;

(p) Show Cause Notice means a written notification to a contractor based on the determination of the reviewer (or in appropriate cases by higher level authority) to be in noncompliance with the equal opportunity requirements. The notice informs the contractor of the specific basis for the determination and provides the opportunity, within 30 days from receipt, to present an explanation why sanctions should not be imposed;

(q) State highway agency (SHA) means that department, commission, board, or official of any State charged by its laws with the responsibility for highway construction. The term State should be considered equivalent to State highway agency. With regard to direct Federal contracts, references herein to SHA's shall be considered to refer to FHWA regional offices, as appropriate.


§230.409   Contract compliance review procedures.

(a) General. A compliance review consists of the following elements:

(1) Review Scheduling (Actions R-1 and R-2).

(2) Contractor Notification (Action R-3).

(3) Preliminary Analysis (Phase I) (Action R-4).

(4) Onsite Verification and Interviews (Phase II) (Action R-5).

(5) Exit Conference (Action R-6).

(6) Compliance Determination and Formal Notification (Actions R-8, R-9, R-10, R-11, R-12).

The compliance review procedure, as described herein and in appendix D provides for continual monitoring of the employment process. Monitoring officials at all levels shall analyze submissions from field offices to ensure proper completion of procedural requirements and to ascertain the effectiveness of program implementation.

(b) Review scheduling. (Actions R-1 and R-2). Because construction work forces are not constant, particular attention should be paid to the proper scheduling of equal opportunity compliance reviews. Priority in scheduling equal opportunity compliance reviews shall be given to reviewing those contractor's work forces:

(1) Which hold the greatest potential for employment and promotion of minorities and women (particularly in higher skilled crafts or occupations);

(2) Working in areas which have significant minority and female labor forces within a reasonable recruitment area;

(3) Working on projects that include special training provisions; and

(4) Where compliance with equal opportunity requirements is questionable. (Based on previous PR-1391's (23 CFR part 230, subpart A, appendix C) Review Reports and Hometown Plan Reports).

In addition, the following considerations shall apply:

(5) Reviews specifically requested by the Washington Headquarters shall receive priority scheduling;

(6) Compliance Reviews in geographical areas covered by areawide plans would normally be reviewed under the Consolidated Compliance Review Procedures set forth in §230.415.

(7) Reviews shall be conducted prior to or during peak employment periods.

(8) No compliance review shall be conducted that is based on a home office work force of less than 15 employees unless requested or approved by Washington Headquarters; and

(9) For compliance reviews based on an area work force (outside of areawide plan coverage), the Compliance Specialist shall define the applicable geographical area by considering:

(i) Union geographical boundaries;

(ii) The geographical area from which the contractor recruits employees, i.e. reasonable recruitment area;

(iii) Standard Metropolitan Statistical Area (SMSA) or census tracts; and

(iv) The county in which the Federal or Federal-aid project(s) is located and adjacent counties.

(c) Contractor notification (Action R-3). (1) The Compliance Specialist should usually provide written notification to the contractor of the pending compliance review at least 2 weeks prior to the onsite verification and interviews. This notification shall include the scheduled date(s), an outline of the mechanics and basis of the review, requisite interviews, and documents required.

(2) The contractor shall be requested to provide a meeting place on the day of the visit either at the local office of the contractor or at the jobsite.

(3) The contractor shall be requested to supply all of the following information to the Compliance Specialist prior to the onsite verification and interviews.

(i) Current Form PR-1391 developed from the most recent payroll;

(ii) Copies of all current bargaining agreements;

(iii) Copies of purchase orders and subcontracts containing the EEO clause;

(iv) A list of recruitment sources available and utilized;

(v) A statement of the status of any action pertaining to employment practices taken by the Equal Employment Opportunity Commission (EEOC) or other Federal, State, or local agency regarding the contractor or any source of employees;

(vi) A list of promotions made during the past 6 months, to include race, national origin, and sex of employee, previous job held, job promoted into; and corresponding wage rates;

(vii) An annotated payroll to show job classification, race, national origin and sex;

(viii) A list of minority- or female-owned companies contacted as possible subcontractors, vendors, material suppliers, etc.; and

(ix) Any other necessary documents or statements requested by the Compliance Specialist for review prior to the actual onsite visit.

(4) For a project review, the prime contractor shall be held responsible for ensuring that all active subcontractors are present at the meeting and have supplied the documentation listed in §230.409(c)(3).

(d) Preliminary analysis (Phase I) (Action R-4). Before the onsite verification and interviews, the Compliance Specialist shall analyze the employment patterns, policies, practices, and programs of the contractor to determine whether or not problems exist by reviewing information relative to:

(1) The contractor's current work force;

(2) The contractor's relationship with referral sources, e.g., unions, employment agencies, community action agencies, minority and female organizations, etc.;

(3) The minority and female representation of sources;

(4) The availability of minorities and females with requisite skills in a reasonable recruitment area;

(5) Any pending EEOC or Department of Justice cases or local or State Fair Employment Agency cases which are relevant to the contractor and/or the referral sources; and

(6) The related projects (and/or contractor) files of FHWA regional or division and State Coordinator's offices to obtain current information relating to the status of the contractor's project(s), value, scheduled duration, written corrective action plans, PR-1391 or Manpower Utilization Reports, training requirements, previous compliance reviews, and other pertinent correspondence and/or reports.

(e) Onsite verification and interviews (Phase II) (Action R-5). (1) Phase II of the review consists of the construction or home office site visit(s). During the initial meeting with the contractor, the following topics shall be discussed:

(i) Objectives of the visit;

(ii) The material submitted by the contractor, including the actual implementation of the employee referral source system and any discrepancies found in the material; and

(iii) Arrangements for the site tour(s) and employee interviews.

(2) The Compliance Specialist shall make a physical tour of the employment site(s) to determine that:

(i) EEO posters are displayed in conspicuous places in a legible fashion;

(ii) Facilities are provided on a nonsegregated basis (e.g. work areas, washroom, timeclocks, locker rooms, storage areas, parking lots, and drinking fountains);

(iii) Supervisory personnel have been oriented to the contractor's EEO commitments;

(iv) The employee referral source system is being implemented;

(v) Reported employment data is accurate;

(vi) Meetings have been held with employees to discuss EEO policy, particularly new employees; and

(vii) Employees are aware of their right to file complaints of discrimination.

(3) The Compliance Specialist should interview at least one minority, one nonminority, and one woman in each trade, classification, or occupation. The contractor's superintendent or home office manager should also be interviewed.

(4) The Compliance Specialist shall, on a sample basis, determine the union membership status of union employees on the site (e.g. whether they have permits, membership cards, or books, and in what category they are classified [e.g., A, B, or C]).

(5) The Compliance Specialist shall also determine the method utilized to place employees on the job and whether equal opportunity requirements have been followed.

(6) The Compliance Specialist shall determine, and the report shall indicate the following:

(i) Is there reasonable representation and utilization of minorities and women in each craft, classification or occupation? If not, what has the contractor done to increase recruitment, hiring, upgrading, and training of minorities and women?

(ii) What action is the contractor taking to meet the contractual requirement to provide equal employment opportunity?

(iii) Are the actions taken by the contractor acceptable? Could they reasonably be expected to result in increased utilization of minorities and women?

(iv) Is there impartiality in treatment of minorities and women?

(v) Are affirmative action measures of an isolated nature or are they continuing?

(vi) Have the contractor's efforts produced results?

(f) Exit conference (Action R-6). (1) During the exit conference with the contractor, the following topics shall be discussed:

(i) Any preliminary findings that, if not corrected immediately or not corrected by the adoption of an acceptable voluntary corrective action plan, would necessitate a determination of noncompliance;

(ii) The process and time in which the contractor shall be informed of the final determination (15 days following the onsite verification and interviews); and

(iii) Any other matters that would best be resolved before concluding the onsite portion of the review.

(2) Voluntary corrective action plans may be negotiated at the exit conference, so that within 15 days following the exit portion of the review, the Compliance Specialist shall prepare the review report and make a determination of either:

(i) Compliance, and so notify the contractor; or

(ii) Noncompliance, and issue a 30-day show cause notice.

The acceptance of a voluntary corrective action plan at the exit conference does not preclude a determination of noncompliance, particularly if deficiencies not addressed by the plan are uncovered during the final analysis and report writing. (Action R-7) A voluntary corrective action plan should be accepted with the understanding that it only address those problems uncovered prior to the exit conference.

(g) Compliance determinations (Action R-8). (1) The evidence obtained at the compliance review shall constitute a sufficient basis for an objective determination by the Compliance Specialist conducting the review of the contractor's compliance or noncompliance with contractual provisions pursuant to E.O. 11246, as amended, and FHWA EEO Special Provisions implementing the Federal-Aid Highway Act of 1968, where applicable.

(2) Compliance determinations on contractors working in a Hometown Plan Area shall reflect the status of those crafts covered by part II of the plan bid conditions. Findings regarding part I crafts shall be transmitted through channels to the Washington Headquarters, Office of Civil Rights.

(3) The compliance status of the contractor will usually be reflected by positive efforts in the following areas:

(i) The contractor's equal employment opportunity (EEO) policy;

(ii) Dissemination of the policy and education of supervisory employees concerning their responsibilities in implementing the EEO policy;

(iii) The authority and responsibilities of the EEO officer;

(iv) The contractor's recruitment activities, especially establishing minority and female recruitment and referral procedures;

(v) The extent of participation and minority and female utilization in FHWA training programs;

(vi) The contractor's review of personnel actions to ensure equal opportunities;

(vii) The contractor's participation in apprenticeship or other training;

(viii) The contractor's relationship (if any) with unions and minority and female union membership;

(ix) Effective measures to assure nonsegregated facilities, as required by contract provisions;

(x) The contractor's procedures for monitoring subcontractors and utilization of minority and female subcontractors and/or subcontractors with substantial minority and female employment; and

(xi) The adequacy of the contractor's records and reports.

(4) A contractor shall be considered to be in compliance (Action R-9) when the equal opportunity requirements have been effectively implemented, or there is evidence that every good faith effort has been made toward achieving this end. Efforts to acheive this goal shall be result-oriented, initiated and maintained in good faith, and emphasized as any other vital management function.

(5) A contractor shall be considered to be in noncompliance (Action R-10) when:

(i) The contractor has discriminated against applicants or employees with respect to the conditions or privileges of employment; or

(ii) The contractor fails to provide evidence of every good faith effort to provide equal opportunity.

(h) Show cause procedures -- (1) General. Once the onsite verification and exit conference (Action R-5) have been completed and a compliance determination made, (Action R-8), the contractor shall be notified in writing of the compliance determination. (Action R-11 or R-12) This written notification shall be sent to the contractor within 15 days following the completion of the onsite verification and exit conference. If a contractor is found in noncompliance (Action R-10), action efforts to bring the contractor into compliance shall be initiated through the issuance of a show cause notice (Action R-12). The notice shall advise the contractor to show cause within 30 days why sanctions should not be imposed.

(2) When a show cause notice is required. A show cause notice shall be issued when a determination of noncompliance is made based upon:

(i) The findings of a compliance review;

(ii) The results of an investigation which verifies the existence of discrimination; or

(iii) Areawide plan reports that show an underutilization of minorities (based on criteria of U.S. Department of Labor's Optional Form 66 "Manpower Utilization Report") throughout the contractor's work force covered by part II of the plan bid conditions.

(3) Responsibility for issuance. (i) Show cause notices will normally be issued by SHA's to federally assisted contractors when the State has made a determination of noncompliance, or when FHWA has made such a determination and has requested the State to issue the notice.

(ii) When circumstances warrant, the Regional Federal Highway Administrator or a designee may exercise primary compliance responsibility by issuing the notice directly to the contractor.

(iii) The Regional Federal Highway Administrators in Regions 8, 10, and the Regional Engineer in Region 15, shall issue show cause notices to direct Federal contractors found in noncompliance.

(4) Content of show cause notice. The show cause notice must: (See sample -- appendix A of this subpart)

(i) Notify the contractor of the determination of noncompliance;

(ii) Provide the basis for the determination of noncompliance;

(iii) Notify the contractor of the obligation to show cause within 30 days why formal proceedings should not be instituted;

(iv) Schedule (date, time, and place) a compliance conference to be held approximately 15 days from the contractor's receipt of the notice;

(v) Advise the contractor that the conference will be held to receive and discuss the acceptability of any proposed corrective action plan and/or correction of deficiencies; and

(vi) Advise the contractor of the availability and willingness of the Compliance Specialist to conciliate within the time limits of the show cause notice.

(5) Preparing and processing the show cause notice. (i) The State or FHWA official who conducted the investigation or review shall develop complete background data for the issuance of the show cause notice and submit the recommendation to the head of the SHA or the Regional Federal Highway Administrator, as appropriate.

(ii) The recommendation, background data, and final draft notice shall be reviewed by appropriate State or FHWA legal counsel.

(iii) Show cause notices issued by the SHA shall be issued by the head of that agency or a designee.

(iv) The notice shall be personally served to the contractor or delivered by certified mail, return receipt requested, with a certificate of service or the return receipt filed with the case record.

(v) The date of the contractor's receipt of the show cause notice shall begin the 30-day show cause period. (Action R-13).

(vi) The 30-day show cause notice shall be issued directly to the noncompliant contractor or subcontractor with an informational copy sent to any concerned prime contractors.

(6) Conciliation efforts during show cause period. (i) The Compliance Specialist is required to attempt conciliation with the contractor throughout the show cause time period. Conciliation and negotiation efforts shall be directed toward correcting contractor program deficiencies and initiating corrective action which will maintain and assure equal opportunity. Records shall be maintained in the State, FHWA division, or FHWA regional office's case files, as appropriate, indicating actions and reactions of the contractor, a brief synopsis of any meetings with the contractor, notes on verbal communication and written correspondence, requests for assistance or interpretations, and other relevant matters.

(ii) In instances where a contractor is determined to be in compliance after a show cause notice has been issued, the show cause notice will be recinded and the contractor formally notified (Action R-17). The FHWA Washington Headquarters, Office of Civil Rights, shall immediately be notified of any change in status.

(7) Corrective action plans. (i) When a contractor is required to show cause and the deficiencies cannot be corrected within the 30-day show cause period, a written corrective action plan may be accepted. The written corrective action plan shall specify clear unequivocal action by the contractor with time limits for completion. Token actions to correct cited deficiencies will not be accepted. (See Sample Corrective Action Plan -- appendix B of this subpart)

(ii) When a contractor submits an acceptable written corrective action plan, the contractor shall be considered in compliance during the plan's effective implementation and submission of required progress reports. (Action R-15 and R-17).

(iii) When an acceptable corrective action plan is not agreed upon and the contractor does not otherwise show cause as required, the formal hearing process shall be recommended through appropriate channels by the compliance specialist immediately upon expiration of the 30-day show cause period. (Action R-16, R-18, R-19)

(iv) When a contractor, after having submitted an acceptable corrective action plan and being determined in compliance is subsequently determined to be in noncompliance based upon the contractor's failure to implement the corrective action plan, the formal hearing process must be recommended immediately. There are no provisions for reinstituting a show cause notice.

(v) When, however, a contractor operating under an acceptable corrective action plan carries out the provisions of the corrective action plan but the actions do not result in the necessary changes, the corrective action plan shall be immediately amended through negotiations. If, at this point, the contractor refuses to appropriately amend the corrective action plan, the formal hearing process shall be recommended immediately.

(vi) A contractor operating under an approved voluntary corrective action plan (i.e. plan entered into prior to the issuance of a show cause) must be issued a 30-day show cause notice in the situations referred to in paragraphs (h) (7) (iv) and (v) of this section, i.e., failure to implement an approved corrective action plan or failure of corrective actions to result in necessary changes.

(i) Followup reviews. (1) A followup review is an extension of the initial review process to verify the contractors performance of corrective action and to validate progress report information. Therefore, followup reviews shall only be conducted of those contractors where the initial review resulted in a finding of noncompliance and a show cause notice was issued.

(2) Followup reviews shall be reported as a narrative summary referencing the initial review report.

(j) Hearing process. (1) When such procedures as show cause issuance and conciliation conferences have been unsuccessful in bringing contractors into compliance within the prescribed 30 days, the reviewer (or other appropriate level) shall immediately recommend, through channels, that the Department of Transportation obtain approval from the Office of Federal Contract Compliance Programs for a formal hearing (Action R-19). The Contractor should be notified of this action.

(2) Recommendations to the Federal Highway Administrator for hearing approval shall be accompanied by full reports of findings and case files containing any related correspondence. The following items shall be included with the recommendation:

(i) Copies of all Federal and Federal-aid contracts and/or subcontracts to which the contractor is party;

(ii) Copies of any contractor or subcontractor certifications;

(iii) Copy of show cause notice;

(iv) Copies of any corrective action plans; and

(v) Copies of all pertinent Manpower Utilization Reports, if applicable.

(3) SHA's through FHWA regional and division offices, will be advised of decisions and directions affecting contractors by the FHWA Washington Headquarters, Office of Civil Rights, for the Department of Transportation.

(k) Responsibility determinations. (1) In instances where requests for formal hearings are pending OFCCP approval, the contractor may be declared a nonresponsible contractor for inability to comply with the equal opportunity requirements.

(2) SHA's shall refrain from entering into any contract or contract modification subject to E.O. 11246, as amended, with a contractor who has not demonstrated eligibility for Government contracts and federally assisted construction contracts pursuant to E.O. 11246, as amended.


§230.411   Guidance for conducting reviews.

(a) Extensions of time. Reasonable extensions of time limits set forth in these instructions may be authorized by the SHA's or the FHWA regional office, as appropriate. However, all extensions are subject to Washington Headquarters approval and should only be granted with this understanding. The Federal Highway Administrator shall be notified of all time extensions granted and the justification therefor. In sensitive or special interest cases, simultaneous transmittal of reports and other pertinent documents is authorized.

(b) Contract completion. Completion of a contract or seasonal shutdown shall not preclude completion of the administrative procedures outlined herein or the possible imposition of sanctions or debarment.

(c) Home office reviews outside regions. When contractor's home offices are located outside the FHWA region in which the particular contract is being performed, and it is determined that the contractors' home offices should be reviewed, requests for such reviews with accompanying justification shall be forwarded through appropriate channels to the Washington Headquarters, Office of Civil Rights. After approval, the Washington Headquarters, Office of Civil Rights, (OCR) shall request the appropriate region to conduct the home office review.

(d) Employment of women. Executive Order 11246, as amended, implementing rules and regulations regarding sex discrimination are outlined in 41 CFR part 60-20. It is the responsibility of the Compliance Specialist to ensure that contractors provide women full participation in their work forces.

(e) Effect of exclusive referral agreements. (1) The OFCCP has established the following criteria for determining compliance when an exclusive referral agreement is involved;

(i) It shall be no excuse that the union, with which the contractor has a collective bargaining agreement providing for exclusive referral, failed to refer minority or female employees.

(ii) Discrimination in referral for employment, even if pursuant to provisions of a collective bargaining agreement, is prohibited by the National Labor Relations Act and Title VII of the Civil Rights Act of 1964, as amended.

(iii) Contractors and subcontractors have a responsibility to provide equal opportunity if they want to participate in federally involved contracts. To the extent they have delegated the responsibility for some of their employment practices to some other organization or agency which prevents them from meeting their obligations, these contractors must be found in noncompliance.

(2) If the contractor indicates that union action or inaction is a proximate cause of the contractor's failure to provide equal opportunity, a finding of noncompliance will be made and a show cause notice issued, and:

(i) The contractor will be formally directed to comply with the equal opportunity requirements.

(ii) Reviews of other contractors with projects within the jurisdiction of the applicable union locals shall be scheduled.

(iii) If the reviews indicate a pattern and/or practice of discrimination on the part of specific union locals, each contractor in the area shall be informed of the criteria outlined in §230.411(e)(1) of this section. Furthermore, the FHWA Washington Headquarters, OCR, shall be provided with full documentary evidence to support the discriminatory pattern indicated.

(iv) In the event the union referral practices prevent the contractor from meeting the equal opportunity requirements pursuant to the E.O. 11246, as amended, such contractor shall immediately notify the SHA.


§230.413   Review reports.

(a) General. (1) The Compliance Specialist shall maintain detailed notes from the beginning of the review from which a comprehensive compliance review report can be developed.

(2) The completed compliance review report shall contain documentary evidence to support the determination of a contractor's or subcontractor's compliance status.

(3) Findings, conclusions, and recommendations shall be explicitly stated and, when necessary, supported by documentary evidence.

(4) The compliance review report shall contain at least the following information. 1 (Action R-20)

1The Federal Highway Administration will accept completed Form FHWA-86 for the purpose. The form is available at the offices listed in 49 CFR part 7, appendix D.

(i) Complete name and address of contractor.

(ii) Project(s) identification.

(iii) Basis for the review, i.e. area work force, project work force, home office work force, and target area work force.

(iv) Identification of Federal or Federal-aid contract(s).

(v) Date of review.

(vi) Employment data by job craft, classification, or occupation by race and sex in accordance with (iii) above. This shall be the data verified during the onsite.

(vii) Identification of local unions involved with contractor, when applicable.

(viii) Determination of compliance status: compliance or noncompliance.

(ix) Copy of show cause notice or compliance notification sent to contractor.

(x) Name of the Compliance Specialist who conducted the review and whether that person is a State, division or regional Compliance Specialist.

(xi) Concurrences at appropriate levels.

(5) Each contractor (joint venture is one contractor) will be reported separately. When a project review is conducted, the reports should be attached, with the initial report being that of the prime contractor followed by the reports of each subcontractor.

(6) Each review level is responsible for ensuring that required information is contained in the report.

(7) When a project review is conducted, the project work force shall be reported. When an areawide review is conducted (all Federal-aid, Federal, and non-Federal projects in an area), then areawide work force shall be reported. When a home office review is conducted, only home office work force shall be reported. Other information required by regional offices shall be detached before forwarding the reports to the Washington Headquarters, OCR.

(8) The Washington Headquarters, OCR, shall be provided all of the following:

(i) The compliance review report required by §230.413(a)(4).

(ii) Corrective action plans.

(iii) Show cause notices or compliance notifications.

(iv) Show cause recissions.

While other data and information should be kept by regional offices (including progress reports, correspondence, and similar review backup material), it should not be routinely forwarded to the Washington Headquarters, OCR.

(b) Administrative requirements -- (1) State conducted reviews. (i) Within 15 days from the completion of the onsite verification and exit conference, the State Compliance Specialist will:

(A) Prepare the compliance review report, based on information obtained;

(B) Determine the contractor's compliance status;

(C) Notify the contractor of the compliance determination, i.e., send the contractor either notification of compliance or show cause notice; and

(D) Forward three copies of the compliance review report, and the compliance notification or show cause notice to the FHWA division EEO Specialist.

(ii) Within 10 days of receipt, the FHWA division EEO Specialist shall:

(A) Analyze the State's report, ensure that it is complete and accurate;

(B) Resolve nonconcurrence, if any;

(C) Indicate concurrence, and, where appropriate, prepare comments; and

(D) Forward two copies of the compliance review report, and the compliance notification or show cause notice to the Regional Civil Rights Director.

(iii) Within 15 days of receipt, the FHWA Regional Civil Rights Director shall:

(A) Analyze the report, ensure that it is complete and accurate;

(B) Resolve nonconcurrence, if any;

(C) Indicate concurrence, and, where appropriate, prepare comments; and

(D) Forward one copy of the compliance review report, and the compliance notification or show cause notice to the Washington Headquarters, OCR.

(2) FHWA division conducted reviews. (i) Within 15 days from the completion of the onsite verification and exit conference, the division EEO Specialist shall:

(A) Prepare compliance review report, based on information obtained;

(B) Determine the contractor's compliance status;

(C) Notify the State to send the contractor the compliance determination, i.e. either notification of compliance or show cause notice; and

(D) Forward two copies of the compliance review report and the compliance notification or show cause notice to the Regional Civil Rights Director.

(ii) Within 15 days of receipt, the FHWA Regional Civil Rights Director will take the steps outlined in §230.413(b)(1)(iii).

(3) FHWA region conducted reviews. (i) Within 15 days from the completion of the onsite verification and exit conference the regional EEO Specialist shall:

(A) Prepare the compliance review report, based on information obtained;

(B) Determine the contractor's compliance status;

(C) Inform the appropriate division to notify the State to send the contractor the compliance determination i.e. either notification of compliance or show cause notice; and

(D) Forward one copy of the compliance review report, and the compliance notification or show cause notice to the Washington Headquarters, OCR.

(4) Upon receipt of compliance review reports, the Washington Headquarters, OCR, shall review, resolve any nonconcurrences, and record them for the purpose of:

(i) Providing ongoing technical assistance to FHWA regional and division offices and SHA's;

(ii) Gathering a sufficient data base for program evaluation;

(iii) Ensuring uniform standards are being applied in the compliance review process;

(iv) Initiating appropriate changes in FHWA policy and implementing regulations; and

(v) Responding to requests from the General Accounting Office, Office of Management and Budget, Senate Subcommittee on Public Roads, and other agencies and organizations.


§230.415   Consolidated compliance reviews.

(a) General. Consolidated compliance reviews shall be implemented to determine employment opportunities on an areawide rather than an individual project basis. The consolidated compliance review approach shall be adopted and directed by either Headquarters, region, division, or SHA, however, consolidated reviews shall at all times remain a cooperative effort.

(b) OFCCP policy requires contracting agencies to ensure compliance, in hometown an imposed plan areas, on an areawide rather than a project basis. The consolidated compliance review approach facilitates implementation of this policy.

(c) Methodology -- (1) Selection of a target area. In identifying the target area of a consolidated compliance review (e.g. SMSA, hometown or imposed plan area, a multicounty area, or an entire State), consideration shall at least be given to the following facts:

(i) Minority and female work force concentrations;

(ii) Suspected or alleged discrimination in union membership or referral practices by local unions involved in highway construction;

(iii) Present or potential problem areas;

(iv) The number of highway projects in the target area; and

(v) Hometown or imposed plan reports that indicate underutilization of minorities or females.

(2) Determine the review period. After the target area has been selected, the dates for the actual onsite reviews shall be established.

(3) Obtain background information. EEO-3's Local Union Reports, should be obtained from regional offices of the EEOC. Target area civilian labor force statistics providing percent minorities and percent females in the target area shall be obtained from State employment security agencies or similar State agencies.

(4) Identify contractors. Every nonexempt federally assisted or direct Federal contractor and subcontractor in the target area shall be identified. In order to establish areawide employment patterns in the target area, employment data is needed for all contractors and subcontractors in the area. However, only those contractors with significant work forces (working prior to peak and not recently reviewed) may need to be actually reviwed onsite. Accordingly, once all contractors are identified, those contractors which will actually be reviewed onsite shall be determined. Compliance determinations shall only reflect the status of crafts covered by part II of plan bid conditions. Employment data of crafts covered by part I of plan bid conditions shall be gathered and identified as such in the composite report, however, OFCCP has reserved the responsibility for compliance determinations on crafts covered by part I of the plan bid conditions.

(5) Contractor notification. Those contractors selected for onsite review shall be sent a notification letter as outlined in §230.409(c) along with a request for current workforce data 2 for completion and submission at the onsite review. Those contractors in the target area not selected for onsite review shall also be requested to supply current workforce data as of the onsite review period, and shall return the data within 15 days following the onsite review period.

2The Consolidated Workforce Questionnaire is convenient for the purpose and appears as attachment 4 to volume 2, chapter 2, section 3 of the Federal-Aid Highway Program Manual, which is available at the offices listed in 49 CFR part 7, appendix D.

(6) Onsite reviews. Compliance reviews shall then be conducted in accordance with the requirements set forth in §230.409. Reviewers may use Form FHWA-86, Compliance Data Report, if appropriate. It is of particular importance during the onsite reviews that the review team provide for adequate coordination of activities at every stage of the review process.

(7) Compliance determinations. Upon completion of the consolidated reviews, compliance determinations shall be made on each review by the reviewer. Individual show cause notices or compliance notifications shall be sent (as appropriate) to each reviewed contractor.

The compliance determination shall be based on the contractor's target area work force (Federal, Federal-aid and non-Federal), except when the target area is coincidental with hometown plan area, compliance determinations must not be based on that part of a contractor's work force covered by part I of the plan bid conditions, as previously set forth in this regulation. For example: ABC Contracting, Inc. employs carpenters, operating engineers, and cement masons. Carpenters and operating engineers are covered by part II of the plan bid conditions, however, cement masons are covered by part I of the plan bid conditions. The compliance determination must be based only on the contractor's utilization of carpenters and operating engineers.

(d) Reporting -- (1) Composite report. A final composite report shall be submitted as a complete package to the Washington Headquarters, OCR, within 45 days after the review period and shall consist of the following:

(i) Compliance review report, for each contractor and subcontractor with accompanying show cause notice or compliance notification.

(ii) Work force data to show the aggregate employment of all contractors in the target area.

(iii) A narrative summary of findings and recommendations to include the following:

(A) A summary of highway construction employment in the target area by craft, race, and sex. This summary should explore possible patterns of discrimination or underutilization and possible causes, and should compare the utilization of minorities and females on contractor's work forces to the civilian labor force percent for minorities and females in the target area.

(B) If the target area is a plan area, a narrative summary of the plan's effectiveness with an identification of part I and part II crafts. This summary shall discuss possible differences in minority and female utilization between part I and part II crafts, documenting any inferences drawn from such comparisons.

(C) If applicable, discuss local labor unions' membership and/or referral practices that impact on the utilization of minorities and females in the target area. Complete and current copies of all collective bargaining agreements and copies of EEO-3, Local Union Reports, for all appropriate unions shall accompany the composite report.

(D) Any other appropriate data, analyses, or information deemed necessary for a complete picture of the areawide employment.

(E) Considering the information compiled from the summaries listed above, make concrete recommendations on possible avenues for correcting problems uncovered by the analyses.

(2) Annual planning report. The proper execution of consolidated compliance reviews necessitates scheduling, along with other fiscal program planning. The Washington Headquarters, OCR, shall be notified of all planned consolidated reviews by August 10 of each year and of any changes in the target area or review periods, as they become known. The annual consolidated planning report shall indicate:

(i) Selected target areas:

(ii) The basis for selection of each area; and

(iii) The anticipated review period (dates) for each target area.

Appendix A to Subpart D of Part 230 -- Sample Show Cause Notice

Certified Mail, Return Receipt Requested

Date

Contractor's Name

Address

City, State, and Zip Code.

DEAR CONTRACTOR: As a result of the review of your (Project Number) project located at (Project Location) conducted on (Date) by (Reviewing Agency), it is our determination that you are not in compliance with your equal opportunity requirements and that good faith efforts have not been made to meet your equal opportunity requirements in the following areas:

List of Deficiencies

1.

2.

3.

Your failure to take the contractually required affirmative action has contributed to the unacceptable level of minority and female employment in your operations, particularly in the semiskilled and skilled categories of employees.

The Department of Labor regulations (41 CFR 60) implementing Executive Order 11246, as amended, are applicable to your Federal-aid highway construction contract and are controlling in this matter (see Required Contract Provisions, Form PR-1273, Clause II). Section 60-1.20(b) of these regulations provides that when equal opportunity deficiencies exist, it is necessary that you make a commitment in writing to correct such deficiencies before you may be found in compliance. The commitment must include the specific action which you propose to take to correct each deficiency and the date of completion of such action. The time period allotted shall be no longer than the minimum period necessary to effect the necessary correction. In accordance with instructions issued by the Office of Federal Contract Compliance Programs (OFCCP), U.S. Department of Labor, your written commitment must also provide for the submission of monthly progress reports which shall include a head count of minority and female representation at each level of each trade and a list of minority employees.

You are specifically advised that making the commitment discussed above will not preclude a further determination of noncompliance upon a finding that the commitment is not sufficient to achieve compliance.

We will hold a compliance conference at -- -- -- -- -- -- -- -- (Address) at -- -- -- -- -- -- -- -- (Time) on -- -- -- -- -- -- -- -- (Date) for you to submit and discuss your written commitment. If your written commitment is acceptable and if the commitment is sufficient to achieve compliance, you will be found in compliance during the effective implementation of that commitment. You are cautioned, however, that our determination is subject to review by the Federal Highway Administration, the Department of Transportation, and OFCCP and may be disapproved if your written commitment is not considered sufficient to achieve compliance.

If you indicate either directly or by inaction that you do not wish to participate in the scheduled conference and do not otherwise show cause within 30 days from receipt of this notice why enforcement proceedings should not be instituted, this agency will commence enforcement proceedings under Executive Order 11246, as amended.

If your written commitment is accepted and it is subsequently found that you have failed to comply with its provisions, you will be advised of this determination and formal sanction proceedings will be instituted immediately.

In the event formal sanction proceedings are instituted and the final determination is that a violation of your equal opportunity contract requirements has taken place, any Federal-aid highway construction contracts or subcontracts which you hold may be canceled, terminated, or suspended, and you may be debarred from further such contracts or subcontracts. Such other sanctions as are authorized by Executive Order 11246, as amended, may also be imposed.

We encourage you to to take whatever action is necessary to resolve this matter and are anxious to assist you in achieving compliance. Any questions concerning this notice should be addressed to (Name, Address, and Phone).

Sincerely yours,

[41 FR 34245, Aug. 13, 1976]




Appendix B to Subpart D of Part 230 -- Sample Corrective Action Plan

Deficiency 1: Sources likely to yield minority employees have not been contacted for recruitment purposes.

Commitment: We have developed a system of written job applications at our home office which readily identifies minority applicants. In addition to this, as a minimum, we will contact the National Association for the Advancement of Colored People (NAACP), League of Latin American Citizens (LULAC), Urban League, and the Employment Security Office within 20 days to establish a referral system for minority group applicants and expand our recruitment base. We are in the process of identifying other community organizations and associations that may be able to provide minority applicants and will submit an updated listing of recruitment sources and evidence of contact by -- -- -- -- -- -- -- -- (Date).

Deficiency 2: There have been inadequate efforts to locate, qualify, and increase skills of minority and female employees and applicants for employment.

Commitment: We will set up an individual file for each apprentice or trainee by -- -- -- -- -- -- (Date) in order to carefully screen the progress, ensure that they are receiving the necessary training, and being promoted promptly upon completion of training requirements. We have established a goal of at least 50 percent of our apprentices and trainees will be minorities and 15 percent will be female. In addition to the commitment made to deficiency number 1, we will conduct a similar identification of organizations able to supply female applicants. Based on our projected personnel needs, we expect to have reached our 50 percent goal for apprentices and trainees by -- -- -- -- -- -- -- (Date).

Deficiency 3: Very little effort to assure subcontractors have meaningful minority group representation among their employees.

Commitment: In cooperation with the Regional Office of Minority Business Enterprise, Department of Commerce, and the local NAACP, we have identified seven minority-owned contractors that may be able to work on future contracts we may receive. These contractors (identified in the attached list) will be contacted prior to our bidding on all future contracts. In addition, we have scheduled a meeting with all subcontractors currently working on our contracts. This meeting will be held to inform the subcontractors of our intention to monitor their reports and require meaningful minority representation. This meeting will be held on -- -- -- -- -- -- -- -- -- -- (Date) and we will summarize the discussions and current posture of each subcontractor for your review by -- -- -- -- -- -- -- -- -- -- (Date) Additionally, as requested, we will submit a PR-1391 on -- -- -- -- -- -- -- -- -- -- (Date), -- -- -- -- -- -- -- -- -- -- -- -- -- -- -- -- -- -- -- -- (Date), -- -- -- -- -- -- -- -- -- -- (Date). Finally, we have committed ourselves to maintaining at least 20 percent minority and female representation in each trade during the time we are carrying out the above commitments. We plan to have completely implemented all the provisions of these commitments by -- -- -- -- -- -- -- -- -- -- (Date).

[41 FR 34245, Aug. 13, 1976]




Appendix C to Subpart D of Part 230 -- Sample Show Cause Rescission

Certified Mail, Return Receipt Requested

Date

Contractor

Address

City, State, and Zip Code

DEAR CONTRACTOR: On -- -- -- -- -- -- -- , (Date) you received a 30-day show cause notice from this office for failing to implement the required contract requirements pertaining to equal employment opportunity.

Your corrective action plan, discussed and submitted at the compliance conference held on -- -- -- -- -- -- -- -- -- -- (Date), has been reviewed and determined to be acceptable. Your implementation of your corrective action plan shows that you are now taking the required affirmative action and can be considered in compliance with Executive Order 11246, as amended. If it should later be determined that your corrective action plan is not sufficient to achieve compliance, this Rescission shall not preclude a subsequent finding of noncompliance.

In view of the above, this letter is to inform you that the 30-day show cause notice of -- -- -- -- -- -- -- -- -- -- (Date) is hereby rescinded. You are further advised that if it is found that you have failed to comply with the provisions of your corrective action plan, formal sanction proceedings will be instituted immediately.

Sincerely,

Appendix D to Subpart D of Part 230 -- Equal Opportunity Compliance Review Process Flow Chart

View or Download PDF

[41 FR 34245, Aug. 13, 1976]

SUBCHAPTER D -- NATIONAL HIGHWAY INSTITUTE




PART 260 -- EDUCATION AND TRAINING PROGRAMS



Subpart A -- Fellowship and Scholarship Grants


   Sec.
260.101   Purpose.
260.103   Definitions.
260.105   Policy.
260.107   Eligibility.
260.109   Selection.
260.111   Responsibilities of educational institutions.
260.113   Responsibilities of employing agencies.
260.115   Equal opportunity.
260.117   Application procedures.

Subparts B-C [Reserved]


Subpart D -- State Education and Training Programs

260.401   Purpose.
260.403   Policy.
260.405   Application and approval procedures.
260.407   Implementation and reimbursement.
Appendix A to Part 260 -- Request for Use of Federal-Aid Highway Funds for Education or Training (Form FHWA-1422)

Subpart A -- Fellowship and Scholarship Grants


Authority: 23 U.S.C. 307(a), 315, 321 and 403; and 49 CFR 1.48(b).

Source: 43 FR 3558, Jan. 26, 1978, unless otherwise noted.


§260.101   Purpose.

To establish policy for the Federal Highway Administration (FHWA) Fellowship and Scholarship Programs as administered by the National Highway Institute (NHI).


§260.103   Definitions.

As used in this regulation, the following definitions apply:

(a) Candidate. One who meets the eligibility criteria set forth in §260.107, and who has completed and submitted the necessary forms and documents in order to be considered for selection for a fellowship or scholarship.

(b) Direct educational expenses. Those expenses directly related to attending school including tuition, student fees, books, and expendable supplies but excluding travel expenses to and from the school.

(c) Employing agency. The agency for which the candidate works. This may be either a State or local highway/transportation agency or the FHWA.

(d) Fellowship. The grant presented to the recipient's school and administered by the school to assist the candidate financially during the period of graduate study.

(e) Living stipend. The portion of the fellowship or scholarship grant remaining after the direct educational expenses have been deducted.

(f) Local highway/transportation agency. The agency or metropolitan planning organization with the responsibility for initiating and carrying forward a highway program or public transportation program utilizing highways at the local level, usually the city or county level.

(g) National Highway Institute (NHI). The organization located within the FHWA responsible for the administration of the FHWA fellowship and scholarship grant programs.

(h) Recipient. The successful candidate receiving a fellowship or scholarship.

(i) Scholarship. The grant presented to the recipient's school and administered by the school to assist the candidate financially during the period of post-secondary study.

(j) State highway/transportation agency. The agency with the responsibility for initiating and carrying forward a highway program or public transportation program utilizing highways at the State level.


§260.105   Policy.

It is the policy of the FHWA to administer, through the NHI, fellowship and scholarship grant programs to assist State and local agencies and the FHWA in developing the expertise needed for the implementation of their highway programs and to assist in the development of more effective transportation programs at all levels of government. These programs shall provide financial support for up to 24 months of either full-time or part-time study in the field of highway transportation. The programs for each year shall be announced by FHWA notices. 1 These notices shall contain an application form and shall announce the number of grants to be awarded and their value.

1The Federal Highway Administration notices are available for inspection and copying as prescribed in 49 CFR part 7, appendix D.

[43 FR 3558, Jan. 26, 1978, as amended at 45 FR 67091, Oct. 9, 1980]



§260.107   Eligibility.

(a) Prior recipients of FHWA scholarships or fellowships are eligible if they will have completed all specific work commitments before beginining study under the programs for which applications are made.

(b) Candidates for the fellowship program shall have earned bachelor's or comparable college-level degrees prior to beginining advanced studies under the program.

(c) Candidates shall submit evidence of acceptance, or probable acceptance, for study in programs that will enhance their contributions to their employers. Evidence of probable acceptance may be a letter from the department chairman or other school official.

(d) Candidates shall agree to pursue certain minimum study loads as determined by the FHWA and designated in the FHWA notices announcing the programs each year.

(e) FHWA employees who receive awards will be required to execute continued service agreements, consistent with the Government Employees Training Act requirements, which obligate the employees to continue to work for the agency for three times the duration of the training received.

(f) Candidates who are students or employees of State or local highway/transportation agencies shall agree in writing to work on a full-time basis in public service with State or local highway/transportation agencies for a specified period of time after completing study under the program. The FHWA notices announcing the programs each year shall specify the time period of the work commitment.

(g) Candidates shall agree to respond to brief questionnaires designed to assist the NHI in program evaluation both during and following the study period.

(h) Recipients of awards for full-time shall agree to limit their part-time employment as stipulated in the FHWA notice announcing the programs.

(i) Candidates shall not profit financially from FHWA grants. Where acceptance of the living stipend portion of the grant would result in a profit to the candidate, as determined by comparing the candidate's regular full-time salary with the candidate's part-time salary and employer salary support plus living stipend, the grant amount will be reduced accordingly. In cases where a candidate must relocate and maintain two households, exceptions to this condition will be considered.

(j) Candidates shall be citizens, or shall declare their intent to become citizens of the United States.


§260.109   Selection.

(a) Candidates shall be rated by a selection panel appointed by the Director of the NHI. Members of the panel shall represent the highway transportation interests of government, industry, and the academic community. The factors considered by the selection panel are weighed in accordance with specific program objectives.

(b) The major factors to be considered by the panel are:

(1) Candidate's potential to contribute to a public agency's highway transportation program,

(2) Relevance of a candidate's study program to the objectives of the fellowship or scholarship program,

(3) Relevant experience, and

(4) Academic and professional achievements.

(c) Using ratings given by the selection panel, the Director of the NHI shall select candidates for awards and designate alternates.

(d) The FHWA may designate in the FHWA notices announcing the programs the maximum number of awards that will be made to employees of any one agency.


§260.111   Responsibilities of educational institutions.

(a) The college or university chosen by the grant recipient shall enter into an appropriate agreement with the FHWA providing for the administration of the grant by the college or university.

(b) The college or university chosen by the recipient shall designate a faculty advisor prior to the commitment of funds by the FHWA. The faculty advisor will be requested to submit reports of the recipient's study progress following completion of each study period. These reports are oriented toward total program evaluation. To assure the recipient's rights to privacy, the FHWA will obtain appropriate advance concurrences from the recipient.


§260.113   Responsibilities of employing agencies.

(a) A candidate's employing agency is responsible for furnishing a statement of endorsement and information concerning the relevancy of the candidate's study to agency requirements. The agency is encouraged to identify educational and training priorities and to provide backup to support its priority candidates for these programs.

(b) Employing agencies are encouraged to give favorable consideration to the requests of candidates for educational leave and salary support for the study period to facilitate the candidates' applications. Agency decisions involving salary support and educational leave that will affect the acceptance of awards by recipients should be made at the earliest possible date to provide adequate time for the FHWA to select alternates to replace candidates that decline their awards.

(c) Agencies are responsible for negotiations with their candidates concerning conditions of reinstatement and the candidates' commitments to return to work.

(d) Employing agencies are encouraged to publicize the availability of these grants throughout the agencies, to implement procedures for internal evaluation of applications, and to forward the applications to the FHWA division office in their State.

(e) Employing agencies that choose to process their employees' applications are responsible for observing the cutoff date for the FHWA to receive applications. This date will be stipulated in the Notices announcing the program for each academic year.


§260.115   Equal opportunity.

(a) Consistent with the provisions of the Civil Rights Act of 1964 and Title VI, assurances executed by each State, 23 U.S.C. 324, and 29 U.S.C. 794, no applicant, including otherwise qualified handicapped individuals, shall on the grounds of race, color, religion, sex, national origin, or handicap, be excluded from participation in, be denied benefits of, or be otherwise subjected to discrimination under this program.

(b) In accordance with Executive Order 11141, no individual shall be denied benefits of this program because of age.

(c) Agencies should make information on this program available to all eligible employees, including otherwise qualified handicapped individuals, so as to assure nondiscrimination on the grounds of race, color, religion, sex, national origin, age, or handicap.


§260.117   Application procedures.

(a) The FHWA notices announcing each year's programs and containing the application form may be obtained from FHWA regional and division offices, State highway agencies, metropolitan planning organizations, Governors' highway safety representatives, Urban Mass Transportation Administration regional directors, major transit authorities and from colleges and universities. Forms may also be obtained from the NHI, HHI-3, FHWA, Washington, DC 20590.

(b) In order to become a candidate, the applicant shall complete and forward the application form according to the instructions in the FHWA notice announcing the programs. The cutoff date for submitting the application stipulated in the notices should be observed.

Subparts B-C [Reserved]

Subpart D -- State Education and Training Programs


Authority: 23 U.S.C. 315, 321 (b) and (c); 49 CFR 1.48(b).

Source: 43 FR 35477, Aug. 10, 1978, unless otherwise noted.


§260.401   Purpose.

To prescribe policy and implement procedures for the administration of Federal-aid funds for education and training of State and local highway department employees.


§260.403   Policy.

It is the policy of the Federal Highway Administration (FHWA) to provide continuing education of State and local highway agency employees engaged or to be engaged in Federal-aid highway work. To carry out this policy, States are encouraged to fully utilize the authority contained in 23 U.S.C. 321(b) and 321(c).


§260.405   Application and approval procedures.

The State may apply for education and training funds by submitting a signed agreement designating the desired Federal-aid funds, not to exceed the limits in 23 U.S.C. 321(b). The FHWA's approval of the agreement will constitute obligation of funds and authorization for work to proceed.


§260.407   Implementation and reimbursement.

(a) After execution of the fiscal agreement, the State may make grants and contracts with public and private agencies, institutions, individuals, and the National Highway Institute to provide highway-related training and education. The principal recipients of this training shall be employees who are engaged or likely to be engaged, in Federal-aid highway work.

(b) Claims for Federal-aid reimbursement of costs incurred may be submitted following established procedures to cover 75 percent of the cost of tuition and direct educational expenses (including incidental training, equipment, and program materials) exclusive of travel, subsistence, or salary of trainees.

(c) As provided in 23 U.S.C. 321(c), education and training for subject areas that are identified by the FHWA as Federal program responsibilities, shall be provided at no cost to State and local governments.

[43 FR 35477, Aug. 10, 1978, as amended at 45 FR 6378, Jan. 28, 1980; 53 FR 3745, Feb. 9, 1988]


Appendix A to Part 260

View or Download PDF



View or Download PDF






SUBCHAPTER E -- PLANNING AND RESEARCH




PART 420 -- PLANNING AND RESEARCH PROGRAM ADMINISTRATION



Subpart A -- Administration of FHWA Planning and Research Funds


   Sec.
420.101   Purpose and applicability.
420.103   Definitions.
420.105   Policy.
420.107   SPR minimum research, development, and technology transfer expenditure.
420.109   Distribution of PL funds.
420.111   Work program.
420.113   Eligibility of costs.
420.115   Approval and authorization procedures.
420.117   Program monitoring and reporting.
420.119   Fiscal procedures.
420.121   Other requirements.

Subpart B -- Research, Development and Technology Transfer Program Management

420.201   Purpose and applicability.
420.203   Definitions.
420.205   Policy.
420.207   Conditions for grant approval.
420.209   State work program.
420.211   Eligibility of costs.
420.213   Certification requirements.
420.215   Procedure for withdrawal of approval.

Authority: 23 U.S.C. 103(i), 104(f), 115, 120, 133(b), 134(n), 157(c), 303(g), 307, and 315; and 49 CFR 1.48(b).

Source: 59 FR 37557, July 22, 1994, unless otherwise noted.

Subpart A -- Administration of FHWA Planning and Research Funds



§420.101   Purpose and applicability.

This part prescribes the Federal Highway Administration (FHWA) policies and procedures for the administration of activities undertaken by States and their subrecipients, including Metropolitan Planning Organizations (MPOs), with FHWA planning and research funds. It applies to activities and studies funded as part of a recipient's or subrecipient's work program or as separate Federal-aid projects that are not included in a work program. This subpart also is applicable to the approval and authorization of research, development, and technology transfer (RD&T) work programs; additional policies and procedures regarding administration of RD&T programs are contained in subpart B of this part. The requirements in this part supplement those in 49 CFR Part 18 which are applicable to administration of these funds.


§420.103   Definitions.

Unless otherwise specified in this part, the definitions in 23 U.S.C. 101(a) are applicable to this part. As used in this part:

Grant agreement means a legal instrument between an awarding agency and recipient where the principal purpose is to provide funds to the recipient to carry out a public purpose of support or stimulation authorized by law.

FHWA planning and research funds means:

(1) State planning and research (SPR) funds (the 2 percent funds authorized under 23 U.S.C. 307(c)(1));

(2) Metropolitan planning (PL) funds (the 1 percent funds authorized under 23 U.S.C. 104(f) to carry out the provisions of 23 U.S.C. 134(a));

(3) National highway system (NHS) funds authorized under 23 U.S.C. 104(b)(1) used for transportation planning in accordance with 23 U.S.C. 134 and 135, highway research and planning in accordance with 23 U.S.C. 307, highway-related technology transfer activities, or development and establishment of management systems under 23 U.S.C. 303;

(4) Surface transportation program (STP) funds authorized under 23 U.S.C. 104(b)(3) used for highway and transit research and development and technology transfer programs, surface transportation planning programs, or development and establishment of management systems under 23 U.S.C. 303; and

(5) Minimum allocation funds authorized under 23 U.S.C. 157(c) used for carrying out, respectively, the provisions of 23 U.S.C. 307(c)(1) (up to 1 1/2 percent) and 23 U.S.C. 134(a) (up to 1/2 percent).

Metropolitan planning area means the geographic area in which the metropolitan transportation planning process required by 23 U.S.C. 134 and section 8 of the Federal Transit Act (49 U.S.C. app. 1607) must be carried out.

Metropolitan planning organization (MPO) means the forum for cooperative transportation decisionmaking for a metropolitan planning area.

National pooled-fund study means a planning or RD&T study or activity expected to solve problems of national significance, usually administered by the FHWA headquarters office in cooperation with States and/or MPOs, that is funded by State and/or MPO contributions of FHWA planning and research funds, with or without matching funds.

Procurement contract means a legal instrument between an awarding agency and recipient where the principal purpose is to acquire (by purchase, lease, or barter) property or services for the direct benefit or use of the awarding agency.

Regional pooled-fund study means a planning or RD&T study expected to solve problems of regional significance, usually administered by an FHWA region office in cooperation with a lead State and/or MPO, that is funded by State and/or MPO contributions of FHWA planning and research funds, with or without matching funds.

State transportation agency (STA) means the State highway department, transportation department, or other State transportation agency to which Federal-aid highway funds are apportioned.

Work program means a periodic statement of proposed work and estimated costs that document the eligible activities to be undertaken with FHWA planning and research funds during the next 1 or 2-year period by STAs and/or their subrecipients.


§420.105   Policy.

(a) Within the limitations of available funding and with the understanding that planning activities of national significance, identified in paragraph (b) of this section, and the requirements of 23 U.S.C. 134, 135, 303, and 307(c) are being adequately addressed, the FHWA will allow STAs and their subrecipients:

(1) Maximum possible flexibility in the use of FHWA planning and research funds to meet highway and multimodal transportation planning and RD&T needs at the national, State, and local levels while ensuring legal use of such funds and avoiding unnecessary duplication of efforts; and

(2) To determine which eligible planning and RD&T activities they desire to support with FHWA planning and research funds and at what funding level.

(b) The STAs shall provide data that support the FHWA's responsibilities to the Congress and to the public. These data include, but are not limited to, information required for: Preparing proposed legislation and reports to the Congress; evaluating the extent, performance, condition, and use of the Nation's transportation systems; analyzing existing and proposed Federal-aid funding methods and levels and the assignment of user cost responsibility; maintaining a critical information base on fuel availability, use, and revenues generated; and calculating apportionment factors. (The information collection requirements in paragraph (b) of §420.105 have been approved by the Office of Management and Budget (OMB) under control numbers 2125-0028 and 2125-0032.)


§420.107   SPR minimum research, development, and technology transfer expenditure.

(a) In accordance with the provisions of 23 U.S.C. 307(c), not less than 25 percent of the SPR funds apportioned to a State for a fiscal year shall be expended for RD&T activities relating to highway, public transportation, and intermodal transportation systems, unless the State certifies, and the FHWA accepts the State's certification, that total expenditures by the State during the fiscal year for transportation planning under 23 U.S.C. 134 and 135 will exceed 75 percent of the amount apportioned for the fiscal year.

(b) Prior to submitting a request for an exception to the 25 percent requirement, the State shall ensure that:

(1) The additional planning activities are essential and there are no other reasonable options available for funding these planning activities (including the use of National Highway System, Surface Transportation Program, or Federal Transit Administration Section 26(a)(2) funds or by deferment of lower priority planning activities);

(2) The planning activities have a higher priority than RD&T activities in overall needs of the State for a given year; and

(3) The total level of effort by the State in RD&T (using both Federal and State funds) is adequate.

(c) If the State chooses to pursue an exception, the request, along with supporting justification, shall be sent to the FHWA Division Administrator for action by the FHWA Associate Administrator for Research and Development. The Associate Administrator's decision shall be based upon the following considerations:

(1) Whether the State has a process for identifying RD&T needs and for implementing a viable RD&T program.

(2) Whether the State is contributing to cooperative RD&T programs or activities, such as the National Cooperative Highway Research Program, the Transportation Research Board, the implementation of products of the Strategic Highway Research Program, and pooled-fund studies.

(3) Whether the State is using SPR funds for technology transfer and for transit or intermodal research and development to help meet the 25 percent minimum requirement.

(4) The percentage or amount of the State's FHWA planning and research funds that were used for RD&T prior to enactment of the 25 percent requirement and whether the percentage or amount will increase if the exception is approved.

(5) If an exception is approved for the fiscal year, whether the State can demonstrate that it will meet the requirement or substantially increase its RD&T expenditures over a multi-year period.

(6) Whether the amount of Federal funds needed for planning for the program period exceeds the total of the 75 percent limit for the fiscal year and any unexpended (including unused funds that can be released from completed projects) funds for planning from previous apportionments.

(d) If the State's request for an exception is approved, the exception will be valid only for the fiscal year in which the exception is approved. A new request must be submitted in subsequent fiscal years.


§420.109   Distribution of PL funds.

(a) States shall make all PL funds authorized by 23 U.S.C. 104(f) available to the MPOs in accordance with a formula developed by the State, in consultation with the MPOs, and approved by the FHWA. The State shall not use any PL funds for grant or subgrant administration.

(b) In developing the formula for distributing PL funds, the State shall consider population, status of planning, attainment of air quality standards, metropolitan area transportation needs, and other factors necessary to provide for an appropriate distribution of funds to carry out the requirements of 23 U.S.C. 134 and other applicable requirements of Federal law.

(c) As soon as practicable after PL funds have been apportioned by the FHWA to the States, the STAs shall inform the MPOs and the FHWA of the amounts allocated to each MPO.

(d) If the STA, in a State receiving the minimum apportionment of PL funds under the provisions of 23 U.S.C. 104(f)(2), determines that the share of funds to be allocated to any MPO results in the MPO receiving more funds than necessary to carry out the provisions of 23 U.S.C. 134(a), the STA may, after considering the views of the affected MPOs and with the approval of the FHWA, use these funds to finance transportation planning outside of metropolitan planning areas.

(e) In accordance with the provisions of 23 U.S.C. 134(n), any PL funds not needed for carrying out the metropolitan planning provisions of 23 U.S.C. 134 may be made available by the MPOs to the State for funding statewide planning activities under 23 U.S.C. 135, subject to approval by the FHWA.

(f) Any State PL fund distribution formula that does not meet the requirements of paragraphs (a) or (b) of this section shall be brought into conformance with such requirements as soon as possible, but no later than in time for distribution of PL funds apportioned to the State for the first Federal fiscal year beginning after August 22, 1994.


§420.111   Work program.

(a) Proposed use of FHWA planning and research funds shall be documented by the STAs and subrecipients in a work program(s) acceptable to the FHWA. Statewide, metropolitan, other transportation planning activities, and transportation RD&T activities may be administered as separate programs, paired in various combinations, or brought together as a single work program. Similarly, these transportation planning and RD&T activities may be authorized for fiscal purposes as one combined Federal-aid project or as separate Federal-aid projects. The expenditure of PL funds for transportation planning outside of metropolitan planning areas under §420.109(d) may be included in the work program for statewide transportation planning activities or in a separate work program submitted by the STA.

(b) Work program(s) that document transportation planning activities shall include a description of work to be accomplished and cost estimates for each activity. Additional information on metropolitan planning area work programs is contained in 23 CFR 450.314. Additional information on research, development, and technology transfer work program content and format is contained in subpart B of this part.

(c) The STAs that use separate Federal-aid projects in accordance with §420.111(a) shall submit, in addition to the financial information specified below for each program, one overall summary showing the funding for the entire FHWA funded planning, research, development, and technology transfer effort. Each work program shall include a financial summary that shows:

(1) Federal share by type of fund;

(2) Matching rate by type of fund;

(3) State and/or local matching share; and

(4) Other State or local funds.

(d) The STAs and MPOs also are encouraged to include cost estimates for transportation planning, research, development, and technology transfer related activities funded with other Federal or State and/or local funds; particularly for producing the FHWA-required data specified in paragraph (b) of §420.105, for planning for other transportation modes, and for air quality planning activities in areas designated as nonattainment for transportation-related pollutants in their work programs. The MPOs in Transportation Management Areas shall include such information in their work programs in accordance with the provisions of 23 CFR part 450. (The information collection requirements in §§420.111(a), (b), and (c), and 420.117(b) and (c) for metropolitan planning areas have been approved by the OMB and assigned control number 2132-0529.)


§420.113   Eligibility of costs.

(a) Costs will be eligible for FHWA participation provided that the costs:

(1) Are for work performed for activities eligible under the section of title 23, U.S.C., applicable to the class of funds used for the activities;

(2) Are verifiable from the STA's or the subrecipient's records;

(3) Are necessary and reasonable for proper and efficient accomplishment of project objectives and meet the other criteria for allowable costs in the applicable cost principles cited in 49 CFR 18.22;

(4) Are included in the approved budget, or amendment thereto; and

(5) Were not incurred prior to FHWA authorization.

(b)(1) Except as specified in paragraph (b)(2) of this section, indirect costs of an STA are not eligible for reimbursement with FHWA planning and research funds.

(2) Salaries for services rendered by STA employees who are generally classified as administrative are eligible for reimbursement for a transportation planning unit, RD&T unit, or other unit performing eligible work with FHWA planning and research funds (including development, establishment, and implementation of the management and monitoring systems required by 23 U.S.C. 303 and 23 CFR part 500) in the ratio of time spent on the participating portion of work in the unit to the total unit's working hours.

(c) Indirect costs of MPOs and local governments are allowable if supported by a cost allocation plan and indirect cost proposal approved in accordance with the provisions of OMB Circular A-87. An initial plan and proposal must be submitted to the Federal cognizant or oversight agency for negotiation and approval prior to recovering any indirect costs. The cost allocation plan and indirect cost proposal shall be updated annually and retained by the MPO or local government, unless requested to be resubmitted by the Federal cognizant or oversight agency, for review at the time of the audit required in accordance with 49 CFR Part 90. If the MPO or local government's indirect cost rate varies significantly from the rate approved for the previous year, or if the MPO or local government changes its accounting system and affects the previously approved indirect cost allocation plan and proposal or rate and its basis of application, the indirect cost allocation plan and proposal shall be resubmitted for negotiation and approval. In either case, a rate shall be negotiated and approved for billing purposes until a new plan and proposal are approved.

(d) Indirect costs of other STA subrecipients, including other State agencies, are allowable if supported by a cost allocation plan and indirect cost proposal prepared, submitted, and approved by the cognizant or oversight agency in accordance with the OMB requirements applicable to the subrecipient.


§420.115   Approval and authorization procedures.

(a) The STA and its subrecipients shall obtain work program approval and authorization to proceed prior to beginning work on activities in the work program. Such approvals and authorizations should be based on final work program documents. The STA and its subrecipients also shall obtain prior approval for budget and programmatic changes as specified in 49 CFR 18.30 and for those items of allowable costs which require prior approval in accordance with the applicable cost principles specified in 49 CFR 18.22.

(b) Except for advance construction, authorization to proceed with the work program(s) in whole or in part shall be deemed a contractual obligation of the Federal Government pursuant to 23 U.S.C. 106 and shall require that appropriate funds be available for the full Federal share of the cost of work authorized. Those STAs that do not have sufficient FHWA planning and research funds or obligation authority available to obligate the full Federal share of the entire work program(s) may utilize the advance construction provisions of 23 U.S.C. 115(a) in accordance with the requirements of 23 CFR Part 630, subpart G. The STAs that do not meet the advance construction provisions, or do not wish to utilize them, may request authorization to proceed with that portion of the work program(s) for which FHWA planning and research funds are available. In the latter case, authorization to proceed may be given for either selected work activities or for a portion of the program period, but such authorization shall not constitute a commitment by the FHWA to fund the remaining portion of the work program(s) should additional funds become available.

(c) A project agreement shall be executed by the STA and FHWA Division Office for each statewide transportation planning, metropolitan planning area transportation planning, or RD&T work program, individual activity or study, or any combination administered as a single Federal-aid project. The project agreement shall be executed after the authorization has been given by the FHWA to proceed with the work in whole or in part. In the event that the project agreement is executed for only part of the work program, the project agreement shall be amended when authorization is given to proceed with additional work.


§420.117   Program monitoring and reporting.

(a) In accordance with 49 CFR 18.40, the STA shall monitor all activities, including those of its subrecipients, supported by FHWA planning and research funds to assure that the work is being managed and performed satisfactorily and that time schedules are being met.

(b)(1) The STA shall submit performance and expenditure reports, including a report from each subrecipient, that contain as a minimum:

(i) Comparison of actual performance with established goals;

(ii) Progress in meeting schedules;

(iii) Status of expenditures in a format compatible with the work program, including a comparison of budgeted (approved) amounts and actual costs incurred;

(iv) Cost overruns or underruns;

(v) Approved work program revisions; and

(vi) Other pertinent supporting data.

(2) Additional information on reporting requirements for individual RD&T studies is contained in subpart B of this part.

(c) The frequency of reports required by paragraph (b) of this section shall be annual unless more frequent reporting is determined to be necessary by the FHWA; but in no case will reports be required more frequently than quarterly. These reports are due 90 days after the end of the reporting period for annual and final reports and no later than 30 days after the end of the reporting period for other reports.

(d) Events that have significant impact on the work program(s) shall be reported as soon as they become known. The type of events or conditions that require reporting include: problems, delays, or adverse conditions that will materially affect the ability to attain program objectives. This disclosure shall be accompanied by a statement of the action taken, or contemplated, and any Federal assistance needed to resolve the situation.

(e) A provision of the Federal-Aid Project Agreement requires both the preparation of suitable reports to document the results of activities performed with FHWA planning and research funds and FHWA approval prior to publishing such reports. The STA may request a waiver of the requirement for prior approval. The FHWA's approval constitutes acceptance of such reports as evidence of work performed but does not imply endorsement of a report's findings or recommendations. Reports prepared for FHWA funded work shall include appropriate credit references and disclaimer statements. (The information collection requirements in §§420.117(b) and (c) for metropolitan planning areas have been approved by the OMB and assigned control number 2132-0529.)


§420.119   Fiscal procedures.

(a) SPR funds shall be administered and accounted for as a single fund regardless of the category of Federal-aid highway funds from which they are derived.

(b) PL funds shall be administered and accounted for as a single fund.

(c) Optional funds authorized under 23 U.S.C. 104(b)(1), 104(b)(3), and 157(c) used for eligible planning and RD&T purposes shall be identified separately in the work program(s) and shall be administered and accounted for separately for fiscal purposes. The statewide and, if appropriate, metropolitan transportation improvement program provisions of 23 CFR Part 450 must be met for the use of NHS, STP, or minimum allocation funds for planning or RD&T purposes.

(d) The maximum rate of Federal participation with funds identified in paragraphs (a) through (c) of this section shall be as prescribed in title 23, U.S.C., for the specific class of funds; unless, for funds identified under paragraph (a) or (b) of this section, the FHWA determines that the interests of the Federal-aid highway program would be best served without such match in accordance with 23 U.S.C. 307(c)(3) or 23 U.S.C. 104(f)(3). The FHWA also may waive the requirement for matching funds if national or regional high priority planning or RD&T problems can be more effectively addressed if several States and/or MPOs pool their funds. Requests for 100 percent Federal funding must be submitted to the FHWA Division Office for approval by the Associate Administrator for Program Development (for planning activities) or the Associate Administrator Research and Development (for RD&T activities).

(e) The provisions of 49 CFR 18.24 are applicable to any necessary matching of FHWA planning and research funds.

(f) Payment shall be made in accordance with the provisions of 49 CFR 18.21.


§420.121   Other requirements.

(a) The financial management systems of the STAs and their subrecipients shall be in accordance with the provisions of 49 CFR 18.20(a).

(b) Program income, as defined in 49 CFR 18.25(b), shall be shown and deducted to determine the net costs on which the FHWA share will be based, unless an alternative method for using program income is specified in the Federal-Aid Project Agreement.

(c) Audits shall be performed in accordance with 49 CFR 18.26 and 49 CFR Part 90.

(d) Acquisition, use, and disposition of equipment purchased by the STAs and their subrecipients with FHWA planning and research funds shall be in accordance with 49 CFR 18.32(b).

(e) Acquisition and disposition of supplies acquired by the STAs and their subrecipients with FHWA planning and research funds shall be in accordance with 49 CFR 18.33.

(f) In accordance with 49 CFR 18.34, STAs and their subrecipients may copyright any books, publications, or other copyrightable materials developed in the course of the FHWA planning and research funded project. The FHWA reserves a royalty-free, nonexclusive and irrevocable right to reproduce, publish, or otherwise use, and to authorize others to use, the work for Government purposes.

(g) Procedures for the procurement of property and services with FHWA planning and research funds by the STAs and their subrecipients shall be in accordance with 49 CFR 18.36(a) and, if applicable, 18.36(t). The STAs and their subrecipients shall not use FHWA funds for procurements from persons (as defined in 49 CFR 29.105) who have been debarred or suspended in accordance with the provisions of 49 CFR Part 29, subparts A through E.

(h) The STAs shall follow State laws and procedures when awarding and administering subgrants to MPOs and local governments and shall ensure that the requirements of 49 CFR 18.37(a) have been satisfied. STAs shall have primary responsibility for administering FHWA planning and research funds passed through to subrecipients, for ensuring that such funds are expended for eligible activities, and for ensuring that the funds are administered in accordance with this part, 49 CFR Part 18, and applicable cost principles.

(i) Recordkeeping and retention requirements shall be in accordance with 49 CFR 18.42.

(j) The STAs and their subrecipients are subject to the provisions of 37 CFR Part 401 governing patents and inventions and shall include, or incorporate by reference, the standard patent rights clause at 37 CFR 401.14, except for §401.14(g), in all subgrants or contracts. In addition, STAs and their subrecipients shall include the following clause, suitably modified to identify the parties, in all subgrants or contracts, regardless of tier, for experimental, developmental or research work: "The subgrantee or contractor will retain all rights provided for the State in this clause, and the State will not, as part of the consideration for awarding the subgrant or contract, obtain rights in the subgrantee's or contractor's subject inventions."

(k) In accordance with the provisions of 49 CFR Part 29, subpart F, STAs shall certify to the FHWA that they will provide a drug free workplace. This requirement can be satisfied through the annual certification for the Federal-aid highway program.

(l) The provisions of 49 CFR Part 20 regarding restrictions on influencing certain Federal activities are applicable to all tiers of recipients of FHWA planning and research funds.

(m) The nondiscrimination provisions of 23 CFR Parts 200 and 230 and 49 CFR Part 21, with respect to Title VI of the Civil Rights Act of 1964 and the Civil Rights Restoration Act of 1987, apply to all programs and activities of recipients, subrecipients, and contractors receiving FHWA planning and research funds whether or not those programs or activities are federally funded.

(n) The STAs shall administer the transportation planning and RD&T program(s) consistent with their overall efforts to implement section 1003(b) of the Intermodal Surface Transportation Efficiency Act of 1991 (Pub. L. 102-240, 105 Stat. 1914) and 49 CFR Part 23 regarding disadvantaged business enterprises.

(o) States and their subrecipients shall administer subgrants to universities, hospitals, and other non-profit organizations in accordance with the administrative requirements of OMB Circular A-110 as implemented by the U.S. DOT in 49 CFR Part 19, Uniform Administrative Requirements for Grants and Agreements with Institutions of Higher Education, Hospitals, and Other Non-Profit Organizations.

(p) Reports and other documents prepared under FHWA planning and research funded grants or subgrants awarded after August 22, 1994, must be in metric units.

Subpart B -- Research, Development and Technology Transfer Program Management



§420.201   Purpose and applicability.

The purpose of this subpart is to implement the provisions of 23 U.S.C. 307 and to prescribe Federal assistance requirements for research, development, and technology transfer (RD&T) activities, programs, and studies undertaken by States with FHWA planning and research funds. The requirements of this subpart and subpart A of this part are applicable to work performed by the States and their subrecipients with FHWA planning and research funds.


§420.203   Definitions.

Unless otherwise specified in this part, the definitions in 23 U.S.C. 101(a) and Part 420, subpart A, are applicable to this subpart. As used in this subpart:

Applied research means the study of phenomena relating to a specific known need in connection with the functional characteristics of a system; the primary purpose of this kind of research is to answer a question or solve a problem.

Basic research means the study of phenomena whose specific application has not been identified; the primary purpose of this kind of research is to increase knowledge.

Cooperatively funded study means an RD&T study or activity, administered by the FHWA, a lead State, or other agency, that is funded by some combination of a State's contribution of FHWA planning and research funds, FHWA administrative contract funds, 100 percent State funds, or funds from other Federal agencies.

Development means the translation of basic or applied research results into prototype materials, devices, techniques, or procedures for the practical solution of a specific problem in transportation.

Final report means a report documenting a completed RD&T study or activity.

Intermodal RD&T means research, development, and technology transfer activities involving more than one mode of transportation including transfer facilities between modes.

National Cooperative Highway Research Program (NCHRP) means the cooperative RD&T program directed toward solving problems of national or regional significance identified by States and the FHWA, and administered by the Transportation Research Board, National Academy of Sciences.

Peer review means a review conducted by persons who are knowledgeable of the management and operation of RD&T programs. This may include but is not limited to representatives of another State, the FHWA, American Association of State Highway and Transportation Officials, Transportation Research Board (TRB), universities or the private sector.

RD&T activity means a basic or applied research, development, or technology transfer project or study.

Research means a systematic controlled inquiry involving analytical and experimental activities which primarily seek to increase the understanding of underlying phenomena. Research can be basic or applied.

Technology transfer means those activities that lead to the adoption of a new technique or product by users and involves dissemination, demonstration, training, and other activities that lead to eventual innovation.

Transportation Research Information Services (TRIS) means the TRB-maintained computerized storage and retrieval system for abstracts of ongoing and completed RD&T activities, including abstracts of RD&T reports and articles.


§420.205   Policy.

(a) It is the FHWA's policy to administer the RD&T program activities utilizing FHWA planning and research funds consistent with the policy specified in §420.105 and the following general principles in paragraphs (b) through (g) of this section.

(b) State transportation agencies shall provide information necessary for peer reviews.

(c) States are encouraged to develop, establish, and implement an RD&T program, funded with Federal and State resources, that anticipates and addresses transportation concerns before they become critical problems. To promote effective utilization of available resources, States are encouraged to cooperate with other States, the FHWA, and other appropriate agencies to achieve RD&T objectives established at the national level and to develop a technology transfer program to promote and use those results.

(d) States will be allowed the authority and flexibility to manage and direct their RD&T activities as presented in their work programs, and to initiate RD&T activities supported by FHWA planning and research funds, subject to the limitation of Federal funds and to compliance with program conditions set forth in subpart A of this part and §420.207.

(e) States will have primary responsibility for managing RD&T activities supported with FHWA planning and research funds carried out by other State agencies and organizations and for ensuring that such funds are expended for purposes consistent with this subpart.

(f) Each State shall develop, establish, and implement a management process that ensures effective use of available FHWA planning and research funds for RD&T activities on a statewide basis. Each State is permitted to tailor its management process to meet State or local needs; however, the process must comply with the minimum requirements and conditions of this subpart.

(g) States are encouraged to make effective use of the FHWA Division, Regional, and Headquarters office expertise in developing and carrying out their RD&T activities. Participation of the FHWA on advisory panels and in program review meetings is encouraged.


§420.207   Conditions for grant approval.

(a) As a condition for approval of FHWA planning and research funds for RD&T activities, a State shall implement a program of RD&T activities for planning, design, construction, and maintenance of highways, public transportation, and intermodal transportation systems. Not less than 25 percent of the State's apportioned SPR funds shall be spent on such activities, unless waived by the FHWA, in accordance with the provisions of §420.107. In addition the State shall develop, establish, and implement a management process that identifies and implements RD&T activities expected to address highest priority transportation issues, and includes:

(1) An interactive process for identification and prioritization of RD&T activities for inclusion in an RD&T work program;

(2) Utilization, to the maximum extent possible, of all FHWA planning and research funds set aside for RD&T activities either internally or for participation in national, regional pooled, or cooperatively funded studies;

(3) Procedures for tracking program activities, schedules, accomplishments, and fiscal commitments;

(4) Support and use of the TRIS database for program development, reporting of active RD&T activities, and input of the final report information;

(5) Procedures to determine the effectiveness of the State's management process in implementing the RD&T program, to determine the utilization of the State's RD&T outputs, and to facilitate peer reviews of its RD&T Program on a periodic basis and;

(6) Procedures for documenting RD&T activities through the preparation of final reports. As a minimum, the documentation shall include the data collected, analyses performed, conclusions, and recommendations. The State shall actively implement appropriate research findings and should document benefits.

(b) Each State shall conduct peer reviews of its RD&T program and should participate in the review of other States' programs on a periodic basis. To assist peer reviewers in completing a quality and performance effectiveness review, the State shall disclose to them information and documentation required to be collected and maintained under this subpart. Travel and other costs associated with peer reviews of the State's program may be identified as a line item in the State work program and will be eligible for 100 percent Federal funding. At least two members of the peer review team shall be selected from the FHWA list of qualified peer reviewers. The peer review team shall provide a written report of its findings to the State. The State shall forward a copy of the report to the FHWA Division Administrator with a written response to the peer review findings.

(c) Documentation that describes the management process and the procedures for selecting and implementing RD&T activities shall be developed and maintained by the State. The documentation shall be submitted by the State to the FHWA Division office for FHWA approval. Significant changes in the management process also shall be submitted by the State for FHWA approval. The State shall make the documentation available, as necessary, to facilitate peer reviews.


§420.209   State work program.

(a) The State's RD&T work program shall, as a minimum, consist of an annual or biennial description of activities and individual RD&T activities to be accomplished during the program period, estimated costs for each eligible activity, and a description of any cooperatively funded activities that are part of a national or regional pooled study including the NCHRP contribution. The State's work program should include a list of the major items with a cost estimate for each item.

(b) The State's RD&T work program shall include financial summaries showing the funding levels and share (Federal, State, and other sources) for RD&T activities for the program year. States are encouraged to include any activity funded 100 percent with State or other funds.

(c) Approval and authorization procedures in §420.115 are applicable to the State's RD&T work program.


§420.211   Eligibility of costs.

(a) Unless otherwise specified in this section, the eligible costs for Federal participation in §420.113 are applicable to this part.

(b) Costs for implementation of RD&T activities in conformity with the requirements and conditions set forth in this subpart are eligible for Federal participation.

(c) Indirect costs of a State transportation agency RD&T unit are allowable to the extent specified in §420.113(b).

(d) Indirect costs of other State agencies and organizations are allowable if supported by a cost allocation plan and indirect cost proposal in accordance with OMB requirements.


§420.213   Certification requirements.

(a) Each State shall certify to the FHWA Division Administrator before June 30, 1995, that it is complying with the requirements of this subpart. For those States unable to meet full compliance by June 30, 1995, the FHWA Division Administrator may grant conditional approval of the State's RD&T management process. A conditional approval shall cite those areas of the State's management process that are deficient. All deficiencies must be corrected by January 1, 1996. A copy of the certification shall be submitted with each work program. A new certification will be required if the State significantly revises its management process for the RD&T program.

(b) The certification shall consist of a statement signed by the Administrator, or an official designated by the Administrator, of the State transportation agency certifying as follows: I (name of certifying official), (position title), of the State (Commonwealth) of ____, do hereby certify that the State (Commonwealth) is in compliance with all requirements of 23 U.S.C. 307 and its implementing regulations with respect to the research, development and technology transfer program, and contemplate no changes in statutes, regulations, or administrative procedures which would affect such compliance.

(c) The FHWA Division Administrator shall determine if the State is in compliance with the requirements of this subpart.


§420.215   Procedure for withdrawal of approval.

(a) If a State is not complying with the requirements of this subpart, or is not performing in accordance with its RD&T management process, the FHWA Division Administrator shall issue a written notice of proposed determination of noncompliance to the State. The notice shall set forth the reasons for the proposed determination and inform the State that it may reply in writing within 30 calendar days from the date of the notice. The State's reply should address the deficiencies cited in the notice and provide documentation as necessary.

(b) If the State and Division Administrator cannot resolve the differences set forth in the determination of nonconformity, the State may appeal to the Federal Highway Administrator.

(c) The Federal Highway Administrator's action shall constitute the final decision of the FHWA.

(d) An adverse decision shall result in immediate withdrawal of approval of FHWA planning and research funds for the State's RD&T activities until the State is in full compliance.




PART 450 -- PLANNING ASSISTANCE AND STANDARDS



Subpart A -- Planning Definitions


   Sec.
450.100   Purpose.
450.102   Applicability.
450.104   Definitions.

Subpart B -- Statewide Transportation Planning

450.200   Purpose.
450.202   Applicability.
450.204   Definitions.
450.206   Statewide transportation planning process: General requirements.
450.208   Statewide transportation planning process: Factors.
450.210   Coordination.
450.212   Public involvement.
450.214   Statewide transportation plan.
450.216   Statewide transportation improvement program (STIP).
450.218   Funding.
450.220   Approvals.
450.222   Project selection for implementation.
450.224   Phase-in of new requirements.

Subpart C -- Metropolitan Transportation Planning and Programming

450.300   Purpose.
450.302   Applicability.
450.304   Definitions.
450.306   Metropolitan planning organization: Designations and redesignation.
450.308   Metropolitan planning organization: Metropolitan planning area boundaries.
450.310   Metropolitan planning organization: Agreements.
450.312   Metropolitan transportation planning: Responsibilities, cooperation, and coordination.
450.314   Metropolitan transportation planning process: Unified planning work programs.
450.316   Metropolitan transportation planning process: Elements.
450.318   Metropolitan transportation planning process: Major metropolitan transportation investments.
450.320   Metropolitan transportation planning process: Relation to management systems.
450.322   Metropolitan transportation planning process: Transportation plan.
450.324   Transportation improvement program: General.
450.326   Transportation improvement program: Modification.
450.328   Transportation improvement program: Relationship to statewide TIP.
450.330   Transportation improvement program: Action required by FHWA/FTA.
450.332   Project selection for implementation.
450.334   Metropolitan transportation planning process: Certification.
450.336   Phase-in of new requirements.

Authority: 23 U.S.C. 134, 135, 217(g), and 315; 42 U.S.C. 7410 et seq.; 49 U.S.C. 5303-5306; 49 CFR 1.48(b) and 1.51.

Source: 58 FR 58064, Oct. 28, 1993, unless otherwise noted.

Subpart A -- Planning Definitions



§450.100   Purpose.

The purpose of this subpart is to provide definitions for terms used in this part which go beyond those terms defined in 23 U.S.C. 101(a).


§450.102   Applicability.

The definitions in this subpart are applicable to this part, except as otherwise provided.


§450.104   Definitions.

Except as defined in this subpart, terms defined in 23 U.S.C 101(a) are used in this part as so defined.

Consultation means that one party confers with another identified party and, prior to taking action(s), considers that party's views.

Cooperation means that the parties involved in carrying out the planning, programming and management systems processes work together to achieve a common goal or objective.

Coordination means the comparison of the transportation plans, programs, and schedules of one agency with related plans, programs and schedules of other agencies or entities with legal standing, and adjustment of plans, programs and schedules to achieve general consistency .

Governor means the Governor of any one of the fifty States, or Puerto Rico, and includes the Mayor of the District of Columbia.

Maintenance area means any geographic region of the United States designated nonattainment pursuant to the CAA Amendments of 1990 (Section 102(e)), 42 U.S.C. 7410 et seq., and subsequently redesignated to attainment subject to the requirement to develop a maintenance plan under section 175A of the Clean Air Act as amended (CAA), 42 U.S.C. 7410 et seq.

Major metropolitan transportation investment means a high-type highway or transit improvement of substantial cost that is expected to have a significant effect on capacity, traffic flow, level of service, or mode share at the transportation corridor or subarea scale. Consultation among the MPO, State department of transportation, transit operator, the FHWA and the FTA may lead to the designation of other proposed improvements as major investments beyond the examples listed below. Examples of such investments could generally include but are not limited to: Construction of a new partially controlled access (access allowed only for public roads) principal arterial, extension of an existing partially controlled access (access allowed only for public roads) principal arterial by one or more miles, capacity expansion of a partially controlled access (access provided only for public roads) principal arterial by at least one lane through widening or an equivalent increase in capacity produced by access control or technological improvement, construction or extension of a high-occupancy vehicle (HOV) facility or a fixed guideway transit facility by one or more miles, the addition of lanes or tracks to an existing fixed guideway transit facility for a distance of one or more miles, or a substantial increase in transit service on a fixed guideway facility. For this purpose, a fixed guideway refers to any public transportation facility which utilizes and occupies a designated right-of-way or rails including (but not limited to) rapid rail, light rail, commuter rail, busways, automated guideway transit, and people movers. Projects that generally are not considered to be major transportation investments include but are not limited to: Highway projects on principal arterials where access is not limited to public roads only, small scale improvements or extensions (normally less than one mile) on principal arterials with the primary goal of relieving localized safety or operational difficulties, resurfacing, replacement, or rehabilitation of existing principal arterials and equipment, highway projects not located on a principal arterial, and changes in transit routing and scheduling.

Management system means a systematic process, designed to assist decisionmakers in selecting cost effective strategies/actions to improve the efficiency and safety of, and protect the investment in the nation's infrastructure. A management system includes: identification of performance measures; data collection and analysis; determination of needs; evaluation, and selection of appropriate strategies/actions to address the needs; and evaluation of the effectiveness of the implemented strategies/actions.

Metropolitan planning area means the geographic area in which the metropolitan transportation planning process required by 23 U.S.C. 134 and section 8 of the Federal Transit Act must be carried out.

Metropolitan planning organization (MPO) means the forum for cooperative transportation decisionmaking for the metropolitan planning area. MPOs designated prior to the promulgation of this regulation remain in effect until redesignated in accordance with §450.106 and nothing in this part is intended to require or encourage such redesignation.

Metropolitan transportation plan means the official intermodal transportation plan that is developed and adopted through the metropolitan transportation planning process for the metropolitan planning area.

Nonattainment area means any geographic region of the United States that the Environmental Protection Agency (EPA) has designated as a nonattainment area for a transportation related pollutant(s) for which a National Ambient Air Quality Standard (NAAQS) exists.

Regionally significant project means a project (other than projects that may be grouped in the STIP/TIP pursuant to §450.216 and §450.324) that is on a facility which serves regional transportation needs (such as access to and from the area outside of the region, major activity centers in the region, major planned developments such as new retail malls, sports complexes, etc., or transportation terminals as well as most terminals themselves) and would normally be included in the modeling of a metropolitan area's transportation network, including, as a minimum, all principal arterial highways and all fixed guideway transit facilities that offer a significant alternative to regional highway travel.

State means any one of the fifty States, the District of Columbia, or Puerto Rico.

State Implementation Plan (SIP) means the portion (or portions) of an applicable implementation plan approved or promulgated, or the most recent revision thereof, under sections 110, 301(d) and 175A of the Clean Air Act (42 U.S.C. 7409, 7601, and 7505a).

Statewide transportation improvement program (STIP) means a staged, multiyear, statewide, intermodal program of transportation projects which is consistent with the Statewide transportation plan and planning processes and metropolitan plans, TIPs and processes.

Statewide transportation plan means the official statewide, intermodal transportation plan that is developed through the statewide transportation planning process.

Transportation improvement program (TIP) means a staged, multiyear, intermodal program of transportation projects which is consistent with the metropolitan transportation plan.

Transportation Management Area (TMA) means an urbanized area with a population over 200,000 (as determined by the latest decennial census) or other area when TMA designation is requested by the Governor and the MPO (or affected local officials), and officially designated by the Administrators of the FHWA and the FTA. The TMA designation applies to the entire metropolitan planning area(s).

Subpart B -- Statewide Transportation Planning



§450.200   Purpose.

The purpose of this subpart is to implement 23 U.S.C. 135, which requires each State to carry out a continuing, comprehensive, and intermodal statewide transportation planning process, including the development of a statewide transportation plan and transportation improvement program, that facilitates the efficient, economic movement of people and goods in all areas of the State, including those areas subject to the requirements of 23 U.S.C 134.


§450.202   Applicability.

The requirements of this subpart are applicable to States and any other agencies/organizations which are responsible for satisfying these requirements.


§450.204   Definitions.

Except as otherwise provided in subpart A of this part, terms defined in 23 U.S.C. 101(a) are used in this part as so defined.


§450.206   Statewide transportation planning process: General requirements.

(a) The statewide transportation planning process shall include, as a minimum:

(1) Data collection and analysis;

(2) Consideration of factors contained in §450.208;

(3) Coordination of activities as noted in §450.210;

(4) Development of a statewide transportation plan that considers a range of transportation options designed to meet the transportation needs (both passenger and freight) of the state including all modes and their connections; and

(5) Development of a statewide transportation improvement program (STIP).

(b) The statewide transportation planning process shall be carried out in coordination with the metropolitan planning process required by subpart C of this part.


§450.208   Statewide transportation planning process: Factors.

(a) Each State shall, at a minimum, explicitly consider, analyze as appropriate and reflect in planning process products the following factors in conducting its continuing statewide transportation planning process:

(1) The transportation needs (strategies and other results) identified through the management systems required by 23 U.S.C. 303;

(2) Any Federal, State, or local energy use goals, objectives, programs, or requirements;

(3) Strategies for incorporating bicycle transportation facilities and pedestrian walkways in appropriate projects throughout the State;

(4) International border crossings and access to ports, airports, intermodal transportation facilities, major freight distribution routes, national parks, recreation and scenic areas, monuments and historic sites, and military installations;

(5) The transportation needs of nonmetropolitan areas (areas outside of MPO planning boundaries) through a process that includes consultation with local elected officials with jurisdiction over transportation;

(6) Any metropolitan area plan developed pursuant to 23 U.S.C. 134 and section 8 of the Federal Transit Act, 49 U.S.C. app. 1607;

(7) Connectivity between metropolitan planning areas within the State and with metropolitan planning areas in other States;

(8) Recreational travel and tourism;

(9) Any State plan developed pursuant to the Federal Water Pollution Control Act, 33 U.S.C. 1251 et seq. (and in addition to plans pursuant to the Coastal Zone Management Act);

(10) Transportation system management and investment strategies designed to make the most efficient use of existing transportation facilities (including consideration of all transportation modes);

(11) The overall social, economic, energy, and environmental effects of transportation decisions (including housing and community development effects and effects on the human, natural and manmade environments);

(12) Methods to reduce traffic congestion and to prevent traffic congestion from developing in areas where it does not yet occur, including methods which reduce motor vehicle travel, particularly single-occupant motor vehicle travel;

(13) Methods to expand and enhance appropriate transit services and to increase the use of such services (including commuter rail);

(14) The effect of transportation decisions on land use and land development, including the need for consistency between transportation decisionmaking and the provisions of all applicable short-range and long-range land use and development plans (analyses should include projections of economic, demographic, environmental protection, growth management and land use activities consistent with development goals and transportation demand projections);

(15) Strategies for identifying and implementing transportation enhancements where appropriate throughout the State;

(16) The use of innovative mechanisms for financing projects, including value capture pricing, tolls, and congestion pricing;

(17) Preservation of rights-of-way for construction of future transportation projects, including identification of unused rights-of-way which may be needed for future transportation corridors, identification of those corridors for which action is most needed to prevent destruction or loss (including strategies for preventing loss of rights-of-way);

(18) Long-range needs of the State transportation system for movement of persons and goods;

(19) Methods to enhance the efficient movement of commercial motor vehicles;

(20) The use of life-cycle costs in the design and engineering of bridges, tunnels, or pavements;

(21) The coordination of transportation plans and programs developed for metropolitan planning areas of the State under 23 U.S.C. 134 and section 8 of the Federal Transit Act with the statewide transportation plans and programs developed under this subpart, and the reconciliation of such plans and programs as necessary to ensure connectivity within transportation systems;

(22) Investment strategies to improve adjoining State and local roads that support rural economic growth and tourism development, Federal agency renewable resources management, and multipurpose land management practices, including recreation development; and

(23) The concerns of Indian tribal governments having jurisdiction over lands within the boundaries of the State.

(b) The degree of consideration and analysis of the factors should be based on the scale and complexity of many issues, including transportation problems, land use, employment, economic development, environmental and housing and community development objectives, the extent of overlap between factors and other circumstances statewide or in subareas within the State.


§450.210   Coordination.

(a) In addition to the coordination required under §450.208(a)(21), in carrying out the requirements of this subpart, each State, in cooperation with participating organizations (such as MPOs, Indian tribal governments, environmental, resource and permit agencies, public transit operators) shall, to the extent appropriate, provide for a fully coordinated process including coordination of the following:

(1) Data collection, data analysis and evaluation of alternatives for a transit, highway, bikeway, scenic byway, recreational trail, or pedestrian program with any such activities for the other programs;

(2) Plans, such as the statewide transportation plan required under §450.214, with programs and priorities for transportation projects, such as the STIP;

(3) Data analysis used in development of plans and programs, (for example, information resulting from traffic data analysis, data and plans regarding employment and housing availability, data and plans regarding land use control and community development) with land use projections, with data analysis on issues that are part of public involvement relating to project implementation, and with data analyses done as part of the establishment and maintenance of management systems developed in response to 23 U.S.C. 303;

(4) Consideration of intermodal facilities with land use planning, including land use activities carried out by local, regional, and multistate agencies;

(5) Transportation planning carried out by the State with transportation planning carried out by Indian tribal governments, Federal agencies and local governments, MPOs, large-scale public and private transportation providers, operators of major intermodal terminals and multistate businesses;

(6) Transportation planning carried out by the State with significant transportation-related actions carried out by other agencies for recreation, tourism, and economic development and for the operation of airports, ports, rail terminals and other intermodal transportation facilities;

(7) Public involvement carried out for the statewide planning process with public involvement carried out for the metropolitan planning process;

(8) Public involvement carried out for planning with public involvement carried out for project development;

(9) Transportation planning carried out by the State with Federal, State, and local environmental resource planning that substantially affects transportation actions;

(10) Transportation planning with financial planning;

(11) Transportation planning with analysis of potential corridors for preservation;

(12) Transportation planning with analysis of social, economic, employment, energy, environmental, and housing and community development effects of transportation actions; and

(13) Transportation planning carried out by the State to meet the requirements of 23 U.S.C. 135 with transportation planning to meet other Federal requirements including the State rail plan.

(b) The degree of coordination should be based on the scale and complexity of many issues including transportation problems, land use, employment, economic, environmental, and housing and community development objectives, and other circumstances statewide or in subareas within the State.


§450.212   Public involvement.

(a) Public involvement processes shall be proactive and provide complete information, timely public notice, full public access to key decisions, and opportunities for early and continuing involvement. The processes shall provide for:

(1) Early and continuing public involvement opportunities throughout the transportation planning and programming process;

(2) Timely information about transportation issues and processes to citizens, affected public agencies, representatives of transportation agency employees, private providers of transportation, other interested parties and segments of the community affected by transportation plans, programs, and projects;

(3) Reasonable public access to technical and policy information used in the development of the plan and STIP;

(4) Adequate public notice of public involvement activities and time for public review and comment at key decision points, including but not limited to action on the plan and STIP;

(5) A process for demonstrating explicit consideration and response to public input during the planning and program development process;

(6) A process for seeking out and considering the needs of those traditionally underserved by existing transportation systems, such as low-income and minority households which may face challenges accessing employment and other amenities;

(7) Periodic review of the effectiveness of the public involvement process to ensure that the process provides full and open access to all and revision of the process as necessary.

(b) Public involvement activities carried out in a metropolitan area in response to metropolitan planning requirements in §450.322(c) or §450.324(c) may by agreement of the State and the MPO satisfy the requirements of this section.

(c) During initial development and major revisions of the statewide transportation plan required under §450.214, the State shall provide citizens, affected public agencies and jurisdictions, employee representatives of transportation and other affected agencies, private and public providers of transportation, and other interested parties a reasonable opportunity to comment on the proposed plan. The proposed plan shall be published, with reasonable notification of its availability, or otherwise made readily available for public review and comment. Likewise, the official statewide transportation plan (see §450.214(d)) shall be published, with reasonable notification of its availability, or otherwise made readily available for public information.

(d) During development and major revision of the statewide transportation improvement program required under §450.216, the Governor shall provide citizens, affected public agencies and jurisdictions, employee representatives of transportation or other affected agencies, private providers of transportation, and other interested parties, a reasonable opportunity for review and comment on the proposed program. The proposed program shall be published, with reasonable notification of its availability, or otherwise made readily available for public review and comment. The approved program (see §450.220(c)) if it differs significantly from the proposed program, shall be published, with reasonable notification of its availability, or otherwise made readily available for public information.

(e) The time provided for public review and comment for minor revisions to the statewide transportation plan or statewide transportation improvement program will be determined by the State and local officials based on the complexity of the revisions.

(f) The State shall, as appropriate, provide for public comment on existing and proposed procedures for public involvement throughout the statewide transportation planning and programming process. As a minimum, the State shall publish procedures and allow 45 days for public review and written comment before the procedures and any major revisions to existing procedures are adopted.

(g) The public involvement processes will be considered by the FHWA and the FTA as they make the planning finding required in §450.220(b) to assure that full and open access is provided to the decision making process.


§450.214   Statewide transportation plan.

(a) The State shall develop a statewide transportation plan for all areas of the State.

(b) The plan shall:

(1) Be intermodal (including consideration and provision, as applicable, of elements and connections of and between rail, commercial motor vehicle, waterway, and aviation facilities, particularly with respect to intercity travel) and statewide in scope in order to facilitate the efficient movement of people and goods;

(2) Be reasonably consistent in time horizon among its elements, but cover a period of at least 20 years;

(3) Contain, as an element, a plan for bicycle transportation, pedestrian walkways and trails which is appropriately interconnected with other modes;

(4) Be coordinated with the metropolitan transportation plans required under 23 U.S.C. 134;

(5) Reference, summarize or contain any applicable short range planning studies, strategic planning and/or policy studies, transportation need studies, management system reports and any statements of policies, goals and objectives regarding issues such as transportation, economic development, housing, social and environmental effects, energy, etc., that were significant to development of the plan; and

(6) Reference, summarize or contain information on the availability of financial and other resources needed to carry out the plan.

(c) In developing the plan, the State shall:

(1) Cooperate with the MPOs on the portions of the plan affecting metropolitan planning areas;

(2) Cooperate with the Indian tribal government and the Secretary of the Interior on the portions of the plan affecting areas of the State under the jurisdiction of an Indian tribal government;

(3) Provide for public involvement as required under §450.212;

(4) Provide for substantive consideration and analysis as appropriate of specified factors as required under §450.208; and

(5) Provide for coordination as required under §450.210.

(d) The State shall provide and carryout a mechanism to establish the document, or documents, comprising the plan as the official statewide transportation plan.

(e) The plan shall be continually evaluated and periodically updated as appropriate using the procedures in this section for development and establishment of the plan.


§450.216   Statewide transportation improvement program (STIP).

(a) Each State shall develop a statewide transportation improvement program for all areas of the State. In case of difficulties in developing the STIP portion for a particular area, e.g., metropolitan area, Indian tribal lands, etc., a partial STIP covering the rest of the State may be developed. The portion of the STIP in a metropolitan planning area (the metropolitan TIP developed pursuant to subpart C of this part) shall be developed in cooperation with the MPO. To assist this process, the State will need to provide MPOs with estimates of available Federal and State funds which the MPO can utilize in developing the metropolitan TIP. Metropolitan planning area TIPs shall be included without modification in the STIP, directly or by reference, once approved by the MPO and the Governor and after needed conformity findings are made. Metropolitan TIPs in nonattainment and maintenance areas are subject to the FHWA and the FTA conformity findings before their inclusion in the STIP. In nonattainment and maintenance areas outside metropolitan planning areas, Federal findings of conformity must be made prior to placing projects in the STIP. The State shall notify the appropriate MPO, local jurisdictions, Federal land agency, Indian tribal government, etc. when a TIP including projects under the jurisdiction of the agency has been included in the STIP. All title 23 and Federal Transit Act fund recipients will share information as projects in the STIP are implemented. The Governor shall provide for public involvement in development of the STIP as required by §450.212. In addition, the STIP shall:

(1) Include a list of priority transportation projects proposed to be carried out in the first 3 years of the STIP. Since each TIP is approved by the Governor, the TIP priorities will dictate STIP priorities for each individual metropolitan area. As a minimum, the lists shall group the projects that are to be undertaken in each of the years, e.g., year 1, year 2, year 3;

(2) Cover a period of not less than 3 years, but may at State discretion cover a longer period. If the STIP covers more than 3 years, the projects in the additional years will be considered by the FHWA and the FTA only as informational;

(3) Contain only projects consistent with the statewide plan developed under §450.214;

(4) In nonattainment and maintenance areas, contain only transportation projects found to conform, or from programs that conform, to the requirements contained in 40 CFR part 51;

(5) Be financially constrained by year and include sufficient financial information to demonstrate which projects are to be implemented using current revenues and which projects are to be implemented using proposed revenue sources while the system as a whole is being adequately operated and maintained. In nonattainment and maintenance areas, projects included in the first two years of the current STIP/TIP shall be limited to those for which funds are available or committed. In the case of proposed funding sources, strategies for ensuring their availability shall be identified;

(6) Contain all capital and non-capital transportation projects (including transportation enhancements, Federal lands highways projects, trails projects, pedestrian walkways, and bicycle transportation facilities), or identified phases of transportation projects, proposed for funding under the Federal Transit Act (49 U.S.C. app. 1602, 1607a, 1612 and 1614) and/or title 23, U.S.C. excluding:

(i) Safety projects funded under section 402 of the Surface Transportation Assistance Act of 1982, as amended (49 U.S.C. app. 2302);

(ii) IVHS planning grants funded under section 6055(b) of the Intermodal Surface Transportation Efficiency Act of 1991 (Pub. L. 102-240, 105 Stat. 1914);

(iii) Transit planning grants funded under section 8 or 26 of the Federal Transit Act (49 U.S.C. app. 1607 and 1622);

(iv) Metropolitan planning projects funded under 23 U.S.C. 104(f);

(v) State planning and research projects funded under 23 U.S.C. 307(c)(1) (except those funded with NHS, STP and minimum allocation (MA) funds that the State and MPO for a metropolitan area agree should be in the TIP and consequently must be in the STIP); and

(vi) Emergency relief projects (except those involving substantial functional, locational or capacity changes);

(7) Contain all regionally significant transportation projects requiring an action by the FHWA or the FTA whether or not the projects are to be funded with title 23, U.S.C. or Federal Transit Act funds, e.g., addition of an interchange to the Interstate System with State, local and/or private funds, demonstration projects not funded under title 23, U.S.C., or the Federal Transit Act. (The STIP should, for information purposes, include all regionally significant transportation projects proposed to be funded with Federal funds other than those administered by the FHWA or the FTA. It should also include, for information purposes, if appropriate and cited in any TIPs, all regionally significant projects, to be funded with non-Federal funds);

(8) Include for each project the following:

(i) Sufficient descriptive material (i.e., type of work, termini, length, etc.) to identify the project or phase;

(ii) Estimated total cost;

(iii) The amount of Federal funds proposed to be obligated during each program year;

(iv) For the first year, the proposed category of Federal funds and source(s) of non-Federal funds;

(v) For the second and third years, the likely category or possible categories of Federal funds and sources of non-Federal funds;

(vi) Identification of the agencies responsible for carrying out the project; and

(9) For non-metropolitan areas, include in the first year only those projects which have been selected in accordance with the project selection requirements in §450.222(c).

(b) Projects that are not considered to be of appropriate scale for individual identification in a given program year may be grouped by function, work type, and/or geographic area using the applicable classifications under 23 CFR 771.117 (c) and (d) and/or 40 CFR part 51.

(c) Projects in any of the first three years of the STIP may be moved to any other of the first three years of the STIP subject to the project selection requirements of §450.222.

(d) The STIP may be amended at any time under procedures agreed to by the cooperating parties consistent with the procedures established in this section (for STIP development), in §450.212 (for public involvement) and in §450.220 (for the FHWA and the FTA approval).


§450.218   Funding.

Funds provided under sections 8, 9, 18, and 26(a)(2) of the Federal Transit Act and 23 U.S.C. 104(b)(1), 104(b)(3), 104(f)(3) and 307(c)(1) may be used to accomplish activities in this subpart.


§450.220   Approvals.

(a) At least every two years, each State shall submit the entire proposed STIP, and amendments as necessary, concurrently to the FHWA and the FTA for joint approval. The State shall certify that the transportation planning process is being carried out in accordance with all applicable requirements of:

(1) 23 U.S.C. 135, section 8(q) of the Federal Transit Act and this part;

(2) Title VI of the Civil Rights Act of 1964 and the Title VI assurance executed by each State under 23 U.S.C. 324 and 29 U.S.C. 794;

(3) Section 1003(b) of the Intermodal Surface Transportation Efficiency Act of 1991 (Pub. L. 102-240, 105 Stat. 1914) regarding the involvement of disadvantaged business enterprises in the FHWA and the FTA funded projects (sec. 105(f), Pub. L. 97-424, 96 Stat. 2100; 49 CFR part 23);

(4) The provisions of the Americans with Disabilities Act of 1990 (Pub. L. 101-336, 104 Stat. 327, as amended) and U.S. DOT regulations "Transportation for Individuals with Disabilities" (49 CFR parts 27, 37, and 38);

(5) The provisions of 49 CFR part 20 regarding restrictions on influencing certain Federal activities; and

(6) In States containing nonattainment and maintenance areas, sections 174 and 176 (c) and (d) of the Clean Air Act as amended (42 U.S.C. 7504, 7506 (c) and (d)).

(b) The FHWA and the FTA Administrators, in consultation with, where applicable, Federal lands agencies, will review the STIP or amendment and jointly make a finding as to the extent the projects in the STIP are based on a planning process that meets or substantially meets the requirements of title 23, U.S.C., the Federal Transit Act and subparts A, B and C of this part.

(c) If, upon review, the FHWA and the FTA Administrators jointly determine that the STIP or amendment meet, to an acceptable degree, the requirements of 23 U.S.C. 135 and these regulations (including subpart C where a metropolitan TIP is involved), they will approve the STIP. Approval action will take one of the following forms, as appropriate:

(1) Joint approval of the STIP;

(2) Joint approval of the STIP subject to certain corrective actions being taken;

(3) Joint approval of the STIP as the basis for approval of identified categories of projects; and/or

(4) Under special circumstances, joint approval of a partial STIP covering only a portion of the State.

(d) The joint approval period for a new STIP or amended STIP will not exceed two years. Where the State demonstrates that extenuating circumstances will delay the submittal of a new STIP or amended STIP for approval, FHWA and FTA will consider and take appropriate action on requests to extend the approval beyond two years for all or part of the STIP for a limited period of time. Where the request involves projects in a metropolitan planning area(s), the affected MPO(s) must concur in the request and if the delay was due to the development and approval of the TIP, the affected MPO(s) must provide supporting information for the request. If nonattainment and/or maintenance areas are involved, a request for an extension cannot be granted if the conformity determination on the TIP is no longer valid under EPA's conformity regulations (40 CFR part 51).

(e) If, upon review, the FHWA and the FTA Administrators jointly determine that the STIP or amendment does not substantially meet the requirements of 23 U.S.C. 135 and this part for any identified categories of projects, they will not approve the STIP.

(f) The FHWA and the FTA will notify the State of actions taken under this section.

(g) Where necessary in order to maintain or establish operations, the Federal Transit Administrator and/or the Federal Highway Administrator may approve operating assistance for specific projects or programs even though the projects or programs may not be included in an approved STIP.


§450.222   Project selection for implementation.

(a) Except as provided in §§450.220(f) and 450.216(a)(7), only projects included in the Federally approved STIP shall be eligible for funds administered by the FHWA or the FTA.

(b) In metropolitan planning areas, transportation projects requiring title 23 or Federal Transit Act funds administered by the FHWA or the FTA shall be selected in accordance with procedures established pursuant to the project selection portion of the metropolitan planning regulation in subpart C of this part.

(c) Outside metropolitan planning areas, transportation projects undertaken on the National Highway System with title 23 funds and under the bridge and Interstate maintenance programs shall be selected by the State in consultation with the affected local officials. Federal lands highway projects shall be selected in accordance with 23 U.S.C. 204. Other transportation projects undertaken with funds administered by the FHWA shall be selected by the State in cooperation with the affected local officials, and projects undertaken with Federal Transit Act funds shall be selected by the State in cooperation with the appropriate affected local officials and transit operators.

(d) The projects in the first year of an approved STIP shall constitute an "agreed to" list of projects for subsequent scheduling and implementation. No further project selection action is required for the implementing agency to proceed with these projects except that if appropriated Federal funds available are significantly less than the authorized amounts, §450.332(c) provides for a revised list of "agreed to" projects to be developed upon the request of the State, MPO, or transit operators. If an implementing agency wishes to proceed with a project in the second and third year of the STIP, the specific project selection procedures stated in paragraphs (b) and (c) of this section must be used. Expedited selection procedures which provide for the advancement of projects from the second or third years of the STIP may be used if agreed to by all the parties involved in the selection.


§450.224   Phase-in of new requirements.

The State shall, by January 1, 1995, identify the official statewide transportation plan, described under §450.214, to be used as a basis for subsequently approved STIPs. Until such a plan is identified, but no later than January 1, 1995, the State may identify existing plans and policies which can serve as the official interim plan. STIP development shall be based upon a transportation plan which serves as the official plan (including an interim plan, if appropriate, prior to January 1, 1995, provided that all factors identified in §450.208 are considered).

Subpart C -- Metropolitan Transportation Planning and Programming



§450.300   Purpose.

The purpose of this subpart is to implement 23 U.S.C. 134 and section 8 of the Federal Transit Act, as amended, which require that a Metropolitan Planning Organization (MPO) be designated for each urbanized area and that the metropolitan area has a continuing, cooperative, and comprehensive transportation planning process that results in plans and programs that consider all transportation modes and supports metropolitan community development and social goals. These plans and programs shall lead to the development and operation of an integrated, intermodal transportation system that facilitates the efficient, economic movement of people and goods.


§450.302   Applicability.

The provisions of this subpart are applicable to agencies involved in the transportation planning, program development, and project selection processes in metropolitan planning areas.


§450.304   Definitions.

Except as otherwise provided in subpart A of this part, terms defined in 23 U.S.C 101(a) are used in this part as so defined.


§450.306   Metropolitan planning organization: Designations and redesignation.

(a) Designations of metropolitan planning organizations (MPOs) made after December 18, 1991, shall be by agreement among the Governor(s) and units of general purpose local governments representing 75 percent of the affected metropolitan population (including the central city or cities as defined by the Bureau of the Census), or in accordance with procedures established by applicable State or local law. To the extent possible, only one MPO shall be designated for each UZA or group of contiguous UZAs. More than one MPO may be designated within an UZA only if the Governor(s) determines that the size and complexity of the UZA make designation of more than one MPO appropriate.

(b) The designation shall clearly identify the policy body that is the forum for cooperative decisionmaking that will be taking the required approval actions as the MPO.

(c) To the extent possible, the MPO designated should be established under specific State legislation, State enabling legislation, or by interstate compact, and shall have authority to carry out metropolitan transportation planning.

(d) Redesignation (designation of a new MPO(s) to replace an existing MPO) shall occur by agreement of the Governor and affected local units of government representing 75 percent of the population in the entire metropolitan area. The central city(ies) must be among the units of local government agreeing to the redesignation.

(e) Nothing in this subpart shall be deemed to prohibit the MPO from utilizing the staff resources of other agencies to carry out selected elements of the planning process.

(f) Existing MPO designations remain valid until a new MPO is redesignated, unless revoked by the Governor and local units of government representing 75 percent of the population in the area served by the existing MPO (the central city(ies) must be among those desiring to revoke the MPO designation), or as otherwise provided under State or local procedures. If the Governor and local officials decide to redesignate an existing MPO, but do not formally revoke the existing MPO designation, the existing MPO remains in effect until a new MPO is formally designated.

(g) Redesignation of an MPO in a multistate metropolitan area requires the approval of the Governor of each State and local officials representing 75 percent of the population in the entire metropolitan planning area. The local officials in the central city(ies) must be among those agreeing to the redesignation.

(h) Redesignation of an MPO covering more than one UZA requires the approval of the Governor and local officials representing 75 percent of the population in the metropolitan planning area covered by the current MPO; the local officials in the central city(ies) in each urbanized area must be among those agreeing to the redesignation.

(i) The voting membership of an MPO policy body designated/redesignated subsequent to December 18, 1991, and serving a TMA, must include representation of local elected officials, officials of agencies that administer or operate major modes or systems of transportation, e.g., transit operators, sponsors of major local airports, maritime ports, rail operators, etc. (including all transportation agencies that were included in the MPO on June 1, 1991), and appropriate State officials. Where agencies that operate other major modes of transportation do not already have a voice on existing MPOs, the MPOs (in cooperation with the States) are encouraged to provide such agencies a voice in the decisionmaking process, including representation/membership on the policy body and/or other appropriate committees. Further, where appropriate, existing MPOs should increase the representation of local elected officials on the policy board and other committees as a means for encouraging their greater involvement in MPO processes. Adding such representation to an MPO will not, in itself, constitute a redesignation action.

(j) Where the metropolitan planning area boundaries for a previously designated MPO need to be expanded, the membership on the MPO policy body and other committees, should be reviewed to ensure that the added area has appropriate representation.

(k) Adding membership (e.g., local elected officials and operators of major modes or systems of transportation, or representatives of newly urbanized areas) to the policy body or expansion of the metropolitan planning area does not automatically require redesignation of the MPO. To the extent possible, it is encouraged that this be done without a formal redesignation. The Governor and MPO shall review the previous MPO designation, State and local law, MPO bylaws, etc., to determine if this can be accomplished without a formal redesignation. If redesignation is considered necessary, the existing MPO will remain in effect until a new MPO is formally designated or the existing designation is formally revoked in accordance with the procedures of this section.


§450.308   Metropolitan planning organization: Metropolitan planning area boundaries.

(a) The metropolitan planning area boundary shall, as a minimum, cover the UZA(s) and the contiguous geographic area(s) likely to become urbanized within the twenty year forecast period covered by the transportation plan described in §450.322 of this part. The boundary may encompass the entire metropolitan statistical area or consolidated metropolitan statistical area, as defined by the Bureau of the Census. For geographic areas designated as nonattainment or maintenance areas (as created by the Clean Air Act Amendments of 1990 (CAAA)) for transportation related pollutants under the CAA, the boundaries of the metropolitan planning area shall include at least the boundaries of the nonattainment or maintenance areas, except as otherwise provided by agreement between the MPO and the Governor under the procedures specified in §450.310(f) of this part. In the absence of a formal agreement between the Governor and the MPO to reduce the metropolitan planning area to an area less than the boundaries of the nonattainment or maintenance area, the entire nonattainment or maintenance area is subject to the applicable provisions of this part. Where a portion of the nonattainment or maintenance area is excluded from the metropolitan planning area boundary, the STP funds suballocated to urbanized areas greater than 200,000 in population shall not be utilized for projects outside the metropolitan planning area boundary.

(b) The metropolitan planning area for a new UZA served by an existing or new MPO shall be established in accordance with these criteria. The current planning area boundaries for previously designated UZAs shall be reviewed and modified if necessary to comply with these criteria.

(c) In addition to the criteria in paragraph (a) of this section, the planning areas currently in use for all transportation modes should be reviewed before establishing the metropolitan planning area boundary. Where appropriate, adjustments should be made to reflect the most comprehensive boundary to foster an effective planning process that ensures connectivity between modes, reduces access disadvantages experienced by modal systems, and promotes efficient overall transportation investment strategies.

(d) Approval of metropolitan planning area boundaries by the FHWA or the FTA is not required. However, metropolitan planning area boundary maps must be submitted to the FHWA and the FTA after their approval by the MPO and the Governor.


§450.310   Metropolitan planning organization: Agreements.

(a) The responsibilities for cooperatively carrying out transportation planning (including corridor and subarea studies) and programming shall be clearly identified in an agreement or memorandum of understanding between the State and the MPO.

(b) There shall be an agreement between the MPO and operators of publicly owned transit services which specifies cooperative procedures for carrying out transportation planning (including corridor and subarea studies) and programming as required by this subpart.

(c) In nonattainment or maintenances areas, if the MPO is not designated for air quality planning under section 174 of the Clean Air Act (42 U.S.C. 7504), there shall be an agreement between the MPO and the designated agency describing their respective roles and responsibilities for air quality related transportation planning.

(d) To the extent possible, there shall be one cooperative agreement containing the understandings required by paragraphs (a) through (c) of this section among the State, MPO, publicly owned operators of mass transportation services, and air quality agencies.

(e) Where the parties involved agree, the requirement for agreements specified in paragraphs (a), (b), and (c) of this section may be satisfied by including the responsibilities and procedures for carrying out a cooperative process in the unified planning work program or a prospectus as defined in §450.314(c).

(f) If the metropolitan planning area does not include the entire nonattainment or maintenance area, there shall be an agreement among the State department of transportation, State air quality agency, affected local agencies, and the MPO describing the process for cooperative planning and analysis of all projects outside the metropolitan planning area but within the nonattainment or maintenance area. The agreement also must indicate how the total transportation related emissions for the nonattainment or maintenance area, including areas both within and outside the metropolitan planning area, will be treated for the purposes of determining conformity in accordance with the U.S. EPA conformity regulation (40 CFR part 51). The agreement shall address policy mechanisms for resolving conflicts concerning transportation related emissions that may arise between the metropolitan planning area and the portion of the nonattainment or maintenance area outside the metropolitan planning area. Proposals to exclude a portion of the nonattainment or maintenance area from the planning area boundary shall be coordinated with the FHWA, the FTA, the EPA, and the State air quality agency before a final decision is made.

(g) Where more than one MPO has authority within a metropolitan planning area or a nonattainment or maintenance area, there shall be an agreement between the State department(s) of transportation and the MPOs describing how the processes will be coordinated to assure the development of an overall transportation plan for the metropolitan planning area. In metropolitan planning areas that are nonattainment or maintenance areas, the agreement shall include State and local air quality agencies. The agreement shall address policy mechanisms for resolving potential conflicts that may arise between the MPOs, e.g., issues related to the exclusion of a portion of the nonattainment area from the planning area boundary.

(h) For all requirements specified in paragraphs (a) through (g) of this section, existing agreements shall be reviewed for compliance and reaffirmed or modified as necessary to ensure participation by all appropriate modes.


§450.312   Metropolitan transportation planning: Responsibilities, cooperation, and coordination.

(a) The MPO in cooperation with the State and with operators of publicly owned transit services shall be responsible for carrying out the metropolitan transportation planning process. The MPO, the State and transit operator(s) shall cooperatively determine their mutual responsibilities in the conduct of the planning process, including corridor refinement studies, described in §§450.316 through 450.318. They shall cooperatively develop the unified planning work program, transportation plan, and transportation improvement program specified in §§450.314 through 450.318. In addition, the development of the plan and TIP shall be coordinated with other providers of transportation, e.g., sponsors of regional airports, maritime port operators, rail freight operators, etc.

(b) The MPO shall approve the metropolitan transportation plan and its periodic updates. The MPO and the Governor shall approve the metropolitan transportation improvement program and any amendments.

(c) In nonattainment or maintenance areas, the MPO shall coordinate the development of the transportation plan with the SIP development process including the development of the transportation control measures. The MPO shall develop or assist in developing the transportation control measures.

(d) In nonattainment or maintenance areas for transportation related pollutants, the MPO shall not approve any transportation plan or program which does not conform with the SIP, as determined in accordance with the U.S. EPA conformity regulation (40 CFR Part 51).

(e) If more than one MPO has authority in a metropolitan planning area (including multi-State metropolitan planning areas) or in an area which is designated as nonattainment or maintenance for transportation related pollutants, the MPOs and the Governor(s) shall cooperatively establish the boundaries of the metropolitan planning area (including the twenty year planning horizon and relationship to the nonattainment or maintenance areas) and the respective jurisdictional responsibilities of each MPO. The MPOs shall consult with each other and the State(s) to assure the preparation of integrated plans and transportation improvement programs for the entire metropolitan planning area. An individual MPO plan and program may be developed separately. However, each plan and program must be consistent with the plans and programs of other MPOs in the metropolitan planning area. For the overall metropolitan planning area, the individual MPO planning process shall reflect coordinated data collection, analysis and development. In those areas where this provision is applicable, coordination efforts shall be initiated and the process and outcomes documented in subsequent transmittals of the UPWP and various planning products (the plan, TIP, etc.) to the State, the FHWA, and the FTA.

(f) The Secretary must designate as transportation management areas all UZAs over 200,000 population as determined by the most recent decennial census. The Secretary designated TMAs by publishing a notice in the FEDERAL REGISTER. Copies of this notice may be obtained from the FHWA Metropolitan Planning Division or Office of Planning FTA. The TMAs so designated and those designated subsequently by the FHWA and the FTA (including those designated upon request of the MPO and the Governor) must comply with the special requirements applicable to such areas regarding congestion management systems, project selection, and certification. The TMA designation applies to the entire metropolitan planning area boundary. If a metropolitan planning area encompasses a TMA and other UZA(s), the designation applies to the entire metropolitan planning area regardless of the population of constituent UZAs.

(g) As required by 23 CFR part 500, the required management systems shall be developed cooperatively by the State, the MPOs and transit operators for each metropolitan planning area. In TMAs, the congestion management system will be developed as part of the metropolitan transportation planning process.

(h) The State shall cooperatively participate in the development of metropolitan transportation plans. The relationship of the statewide transportation plan and the metropolitan plan is specified in subpart B of this part.

(i) Where a metropolitan planning area includes Federal public lands and/or Indian tribal lands, the affected Federal agencies and Indian tribal governments shall be involved appropriately in the development of transportation plans and programs.


§450.314   Metropolitan transportation planning process: Unified planning work programs.

(a) In TMAs, the MPO(s) in cooperation with the State and operators of publicly owned transit shall develop unified planning work programs (UPWPs) that meet the requirements of 23 CFR part 420, subpart A, and:

(1) Discuss the planning priorities facing the metropolitan planning area and describe all metropolitan transportation and transportation-related air quality planning activities (including the corridor and subarea studies discussed in §450.318) anticipated within the area during the next one or two year period, regardless of funding sources or agencies conducting activities, in sufficient detail to indicate who will perform the work, the schedule for completing it and the products that will be produced;

(2) Document planning activities to be performed with funds provided under title 23, U.S.C., and the Federal Transit Act.

(b) Arrangements may be made with the FHWA and the FTA to combine the UPWP requirements with the work program for other Federal sources of planning funds.

(c) The metropolitan transportation planning process may include the development of a prospectus that establishes a multiyear framework within which the UPWP is accomplished. The prospectus may be used to satisfy the requirements of §450.310 and paragraph (a)(1) of this section.

(d) In areas not designated as TMAs, the MPO in cooperation with the State and transit operators, with the approval of the FHWA and the FTA, may prepare a simplified statement of work, in lieu of a UPWP, that describes who will perform the work and the work that will be accomplished using Federal funds. If a simplified statement of work is used, it may be submitted as part of the Statewide planning work program, in accordance with 23 CFR part 420.


§450.316   Metropolitan transportation planning process: Elements.

(a) Section 134(f) of title 23, U.S.C., and Federal Transit Act section 8(f) (49 U.S.C. app. 1607(f)) list 15 factors that must be considered as part of the planning process for all metropolitan areas. The following factors shall be explicitly considered, analyzed as appropriate, and reflected in the planning process products:

(1) Preservation of existing transportation facilities and, where practical, ways to meet transportation needs by using existing transportation facilities more efficiently;

(2) Consistency of transportation planning with applicable Federal, State, and local energy conservation programs, goals, and objectives;

(3) The need to relieve congestion and prevent congestion from occurring where it does not yet occur including:

(i) The consideration of congestion management strategies or actions which improve the mobility of people and goods in all phases of the planning process; and

(ii) In TMAs, a congestion management system that provides for effective management of new and existing transportation facilities through the use of travel demand reduction and operation management strategies (e.g., various elements of IVHS) shall be developed in accordance with §450.320;

(4) The likely effect of transportation policy decisions on land use and development and the consistency of transportation plans and programs with the provisions of all applicable short- and long-term land use and development plans (the analysis should include projections of metropolitan planning area economic, demographic, environmental protection, growth management, and land use activities consistent with metropolitan and local/central city development goals (community, economic, housing, etc.), and projections of potential transportation demands based on the interrelated level of activity in these areas);

(5) Programming of expenditures for transportation enhancement activities as required under 23 U.S.C. 133;

(6) The effects of all transportation projects to be undertaken within the metropolitan planning area, without regard to the source of funding (the analysis shall consider the effectiveness, cost effectiveness, and financing of alternative investments in meeting transportation demand and supporting the overall efficiency and effectiveness of transportation system performance and related impacts on community/central city goals regarding social and economic development, housing, and employment);

(7) International border crossings and access to ports, airports, intermodal transportation facilities, major freight distribution routes, national parks, recreation areas, monuments and historic sites, and military installations (supporting technical efforts should provide an analysis of goods and services movement problem areas, as determined in cooperation with appropriate private sector involvement, including, but not limited to, addressing interconnected transportation access and service needs of intermodal facilities);

(8) Connectivity of roads within metropolitan planning areas with roads outside of those areas;

(9) Transportation needs identified through the use of the management systems required under 23 U.S.C. 303 (strategies identified under each management system will be analyzed during the development of the transportation plan, including its financial component, for possible inclusion in the metropolitan plan and TIP);

(10) Preservation of rights-of-way for construction of future transportation projects, including future transportation corridors;

(11) Enhancement of the efficient movement of freight;

(12) The use of life-cycle costs in the design and engineering of bridges, tunnels, or pavement (operating and maintenance costs must be considered in analyzing transportation alternatives);

(13) The overall social, economic, energy, and environmental effects of transportation decisions (including consideration of the effects and impacts of the plan on the human, natural and man-made environment such as housing, employment and community development, consultation with appropriate resource and permit agencies to ensure early and continued coordination with environmental resource protection and management plans, and appropriate emphasis on transportation-related air quality problems in support of the requirements of 23 U.S.C. 109(h), and section 14 of the Federal Transit Act (49 U.S.C. 1610), section 4(f) of the DOT Act (49 U.S.C. 303) and section 174(b) of the Clean Air Act (42 U.S.C. 7504(b)));

(14) Expansion, enhancement, and increased use of transit services;

(15) Capital investments that would result in increased security in transit systems; and

(16) Recreational travel and tourism.

(b) In addition, the metropolitan transportation planning process shall:

(1) Include a proactive public involvement process that provides complete information, timely public notice, full public access to key decisions, and supports early and continuing involvement of the public in developing plans and TIPs and meets the requirements and criteria specified as follows:

(i) Require a minimum public comment period of 45 days before the public involvement process is initially adopted or revised;

(ii) Provide timely information about transportation issues and processes to citizens, affected public agencies, representatives of transportation agency employees, private providers of transportation, other interested parties and segments of the community affected by transportation plans, programs and projects (including but not limited to central city and other local jurisdiction concerns);

(iii) Provide reasonable public access to technical and policy information used in the development of plans and TIPs and open public meetings where matters related to the Federal-aid highway and transit programs are being considered;

(iv) Require adequate public notice of public involvement activities and time for public review and comment at key decision points, including, but not limited to, approval of plans and TIPs (in nonattainment areas, classified as serious and above, the comment period shall be at least 30 days for the plan, TIP and major amendment(s));

(v) Demonstrate explicit consideration and response to public input received during the planning and program development processes;

(vi) Seek out and consider the needs of those traditionally underserved by existing transportation systems, including but not limited to low-income and minority households;

(vii) When significant written and oral comments are received on the draft transportation plan or TIP (including the financial plan) as a result of the public involvement process or the interagency consultation process required under the U.S. EPA's conformity regulations, a summary, analysis, and report on the disposition of comments shall be made part of the final plan and TIP;

(viii) If the final transportation plan or TIP differs significantly from the one which was made available for public comment by the MPO and raises new material issues which interested parties could not reasonably have foreseen from the public involvement efforts, an additional opportunity for public comment on the revised plan or TIP shall be made available;

(ix) Public involvement processes shall be periodically reviewed by the MPO in terms of their effectiveness in assuring that the process provides full and open access to all;

(x) These procedures will be reviewed by the FHWA and the FTA during certification reviews for TMAs, and as otherwise necessary for all MPOs, to assure that full and open access is provided to MPO decisionmaking processes;

(xi) Metropolitan public involvement processes shall be coordinated with statewide public involvement processes wherever possible to enhance public consideration of the issues, plans, and programs and reduce redundancies and costs;

(2) Be consistent with Title VI of the Civil Rights Act of 1964 and the Title VI assurance executed by each State under 23 U.S.C. 324 and 29 U.S.C. 794, which ensure that no person shall, on the grounds of race, color, sex, national origin, or physical handicap, be excluded from participation in, be denied benefits of, or be otherwise subjected to discrimination under any program receiving Federal assistance from the United States Department of Transportation;

(3) Identify actions necessary to comply with the Americans With Disabilities Act of 1990 (Pub. L. 101-336, 104 Stat. 327, as amended) and U.S. DOT regulations "Transportation for Individuals With Disabilities" (49 CFR parts 27, 37, and 38);

(4) Provide for the involvement of traffic, ridesharing, parking, transportation safety and enforcement agencies; commuter rail operators; airport and port authorities; toll authorities; appropriate private transportation providers, and where appropriate city officials; and

(5) Provide for the involvement of local, State, and Federal environment resource and permit agencies as appropriate.

(c) In attainment areas not designated as TMAs simplified procedures for the development of plans and programs, if considered appropriate, shall be proposed by the MPO in cooperation with the State and transit operator, and submitted by the State for approval by the FHWA and the FTA. In developing proposed simplified planning procedures, consideration shall be given to the transportation problems in the area and their complexity, the growth rate of the area (e.g., fast, moderate or slow), the appropriateness of the factors specified for consideration in this subpart including air quality, and the desirability of continuing any planning process that has already been established. Areas experiencing fast growth should give consideration to a planning process that addresses all of the general requirements specified in this subpart. As a minimum, all areas employing a simplified planning process will need to develop a transportation plan to be approved by the MPO and a TIP to be approved by the MPO and the Governor.

(d) The metropolitan transportation planning process shall include preparation of technical and other reports to assure documentation of the development, refinement, and update of the transportation plan. The reports shall be reasonably available to interested parties, consistent with §450.316(b)(1).

[58 FR 58064, Oct. 28, 1993, as amended at 61 FR 67175, Dec. 19, 1996]



§450.318   Metropolitan transportation planning process: Major metropolitan transportation investments.

(a) Where the need for a major metropolitan transportation investment is identified, and Federal funds are potentially involved, major investment (corridor or subarea) studies shall be undertaken to develop or refine the plan and lead to decisions by the MPO, in cooperation with participating agencies, on the design concept and scope of the investment. Where the studies have not been completed prior to plan approval, the provisions of §450.322(b)(8) apply.

(b) When any of the implementing agencies or the MPO wish to initiate a major investment study, a meeting will be convened to determine the extent of the analyses and agency roles in a cooperative process which involves the MPO, the State department of transportation, public transit operators, environmental, resource and permit agencies, local officials, the FHWA and the FTA and where appropriate community development agencies, major governmental housing bodies, and such other related agencies as may be impacted by the proposed scope of analysis. A reasonable opportunity, consistent with §450.316(b)(1), shall be provided for citizens and interested parties including affected public agencies, representatives of transportation agency employees, and private providers of transportation to participate in the cooperative process. This cooperative process shall establish the range of alternatives to be studied, such as alternative modes and technologies (including intelligent vehicle and highway systems), general alignment, number of lanes, the degree of demand management, and operating characteristics.

(c) To the extent appropriate as determined under paragraph (b) of this section, major investment studies shall evaluate the effectiveness and cost-effectiveness of alternative investments or strategies in attaining local, State and national goals and objectives. The analysis shall consider the direct and indirect costs of reasonable alternatives and such factors as mobility improvements; social, economic, and environmental effects; safety; operating efficiencies; land use and economic development; financing; and energy consumption.

(d) These major investment studies will serve as the "alternatives analyses" required by section 3(i)(1)(A) of the Federal Transit Act (49 U.S.C. app. 1602(i)) for certain projects for which discretionary section 3 "New Start" funding is being sought. The studies will also be used as the primary source of information for the other section 3(i)(1)(A) Secretarial findings on cost-effectiveness, local financial commitment and capacity, mobility improvements, environmental benefits, economic development, operating efficiency, etc.

(e) These major investment studies also will, when appropriate, serve as the analysis of demand reduction and operational management strategies pursuant to 23 CFR 500.109(b).

(f) A major investment study will include environmental studies which will be used for environmental documents as described in paragraphs (f)(1) and (2) of this section:

(1) As a minimum the participating agencies will use the major investment study as input to an environmental impact statement or environmental assessment prepared subsequent to the completion of the study. In such a case, the major investment study reports shall document the consideration given to alternatives and their impacts; or

(2) The participating agencies may elect to develop a draft environmental impact statement or environmental assessment as part of the major investment study. At any time after the completion of the study and the inclusion of the major transportation investment in the plan and the TIP the participating agencies may request the development of final environmental decision documents required under NEPA for such major transportation investments, culminating in the execution of a Record of Decision or Finding of No Significant Impact by the FHWA and/or the FTA.

(g) Major investment studies may lead to decisions that modify the project design concept and scope assumed in the plan development process. In this case, the study shall lead to the specification of a project's design concept and scope in sufficient detail to meet the requirements of the U.S. EPA conformity regulations (40 CFR part 51).

(h) Major investment studies are eligible for funds authorized under sections 8, 9 and 26 of the Federal Transit Act (49 U.S.C. app. 1607, 16072, and 1622) and planning and capital funds apportioned under title 23, U.S.C., and shall be included in the UPWP. If CMAQ, STP, NHS, or other capital funds administered by the FHWA are utilized for this purpose, the study must also be included in the TIP.

(i) Where the environmental process has been completed and a Record of Decision or Finding of No Significant Impact has been signed, §450.318 does not apply. Where the environmental process has been initiated but not completed, the FHWA and the FTA shall be consulted on appropriate modifications to meet the requirements of this section.

[58 FR 58064, Oct. 28, 1993, as amended at 61 FR 67175, Dec. 19, 1996]



§450.320   Metropolitan transportation planning process: Relation to management systems.

(a) Within all metropolitan areas, congestion, public transportation, and intermodal management systems, to the extent appropriate, shall be part of the metropolitan transportation planning process required under the provisions of 23 U.S.C. 134 and 49 U.S.C. 5303-5305.

(b) In TMAs designated as nonattainment for ozone or carbon monoxide, Federal funds may not be programmed for any project that will result in a significant increase in carrying capacity for single occupant vehicles (a new general purpose highway on a new location or adding general purpose lanes, with the exception of safety improvements or the elimination of bottlenecks) unless the project results from a congestion management system (CMS) meeting the requirements of 23 CFR part 500. Such projects shall incorporate all reasonably available strategies to manage the SOV facility effectively (or to facilitate its management in the future). Other travel demand reduction and operational management strategies, as appropriate for the corridor, but not appropriate for incorporation into the SOV facility itself, shall be committed to by the State and the MPO for implementation in a timely manner, but no later than the completion date for the SOV project. Projects that had advanced beyond the NEPA stage prior to April 6, 1992, and which are actively advancing to implementation, e.g., right-of-way acquisition has been approved, shall be deemed programmed and not subject to this provision.

(c) In TMAs, the planning process must include the development of a CMS that provides for effective management of new and existing transportation facilities through the use of travel demand reduction and operational management strategies and meets the requirements of 23 CFR part 500.

(d) The effectiveness of the management systems in enhancing transportation investment decisions and improving the overall efficiency of the metropolitan area's transportation systems and facilities shall be evaluated periodically, preferably as part of the metropolitan planning process.

[58 FR 58064, Oct. 28, 1993, as amended at 61 FR 67175, Dec. 19, 1996]



§450.322   Metropolitan transportation planning process: Transportation plan.

(a) The metropolitan transportation planning process shall include the development of a transportation plan addressing at least a twenty year planning horizon. The plan shall include both long-range and short-range strategies/actions that lead to the development of an integrated intermodal transportation system that facilitates the efficient movement of people and goods. The transportation plan shall be reviewed and updated at least triennially in nonattainment and maintenance areas and at least every five years in attainment areas to confirm its validity and its consistency with current and forecasted transportation and land use conditions and trends and to extend the forecast period. The transportation plan must be approved by the MPO.

(b) In addition, the plan shall:

(1) Identify the projected transportation demand of persons and goods in the metropolitan planning area over the period of the plan;

(2) Identify adopted congestion management strategies including, as appropriate, traffic operations, ridesharing, pedestrian and bicycle facilities, alternative work schedules, freight movement options, high occupancy vehicle treatments, telecommuting, and public transportation improvements (including regulatory, pricing, management, and operational options), that demonstrate a systematic approach in addressing current and future transportation demand;

(3) Identify pedestrian walkway and bicycle transportation facilities in accordance with 23 U.S.C. 217(g);

(4) Reflect the consideration given to the results of the management systems, including in TMAs that are nonattainment areas for carbon monoxide and ozone, identification of SOV projects that result from a congestion management system that meets the requirements of 23 CFR part 500;

(5) Assess capital investment and other measures necessary to preserve the existing transportation system (including requirements for operational improvements, resurfacing, restoration, and rehabilitation of existing and future major roadways, as well as operations, maintenance, modernization, and rehabilitation of existing and future transit facilities) and make the most efficient use of existing transportation facilities to relieve vehicular congestion and enhance the mobility of people and goods;

(6) Include design concept and scope descriptions of all existing and proposed transportation facilities in sufficient detail, regardless of the source of funding, in nonattainment and maintenance areas to permit conformity determinations under the U.S. EPA conformity regulations at 40 CFR part 51. In all areas, all proposed improvements shall be described in sufficient detail to develop cost estimates;

(7) Reflect a multimodal evaluation of the transportation, socioeconomic, environmental, and financial impact of the overall plan, including all major transportation investments in accordance with §450.318;

(8) For major transportation investments for which analyses are not complete, indicate that the design concept and scope (mode and alignment) have not been fully determined and will require further analysis. The plan shall identify such study corridors and subareas and may stipulate either a set of assumptions (assumed alternatives) concerning the proposed improvements or a no-build condition pending the completion of a corridor or subarea level analysis under §450.318. In nonattainment and maintenance areas, the set of assumed alternatives shall be in sufficient detail to permit plan conformity determinations under the U.S. EPA conformity regulations (40 CFR part 51);

(9) Reflect, to the extent that they exist, consideration of: the area's comprehensive long-range land use plan and metropolitan development objectives; national, State, and local housing goals and strategies, community development and employment plans and strategies, and environmental resource plans; local, State, and national goals and objectives such as linking low income households with employment opportunities; and the area's overall social, economic, environmental, and energy conservation goals and objectives;

(10) Indicate, as appropriate, proposed transportation enhancement activities as defined in 23 U.S.C. 101(a); and

(11) Include a financial plan that demonstrates the consistency of proposed transportation investments with already available and projected sources of revenue. The financial plan shall compare the estimated revenue from existing and proposed funding sources that can reasonably be expected to be available for transportation uses, and the estimated costs of constructing, maintaining and operating the total (existing plus planned) transportation system over the period of the plan. The estimated revenue by existing revenue source (local, State, and Federal and private) available for transportation projects shall be determined and any shortfalls identified. Proposed new revenues and/or revenue sources to cover shortfalls shall be identified, including strategies for ensuring their availability for proposed investments. Existing and proposed revenues shall cover all forecasted capital, operating, and maintenance costs. All cost and revenue projections shall be based on the data reflecting the existing situation and historical trends. For nonattainment and maintenance areas, the financial plan shall address the specific financial strategies required to ensure the implementation of projects and programs to reach air quality compliance.

(c) There must be adequate opportunity for public official (including elected officials) and citizen involvement in the development of the transportation plan before it is approved by the MPO, in accordance with the requirements of §450.316(b)(1). Such procedures shall include opportunities for interested parties (including citizens, affected public agencies, representatives of transportation agency employees, and private providers of transportation) to be involved in the early stages of the plan development/update process. The procedures shall include publication of the proposed plan or other methods to make it readily available for public review and comment and, in nonattainment TMAs, an opportunity for at least one formal public meeting annually to review planning assumptions and the plan development process with interested parties and the general public. The procedures also shall include publication of the approved plan or other methods to make it readily available for information purposes.

(d) In nonattainment and maintenance areas for transportation related pollutants, the FHWA and the FTA, as well as the MPO, must make a conformity determination on any new/revised plan in accordance with the Clean Air Act and the EPA conformity regulations (40 CFR part 51).

(e) Although transportation plans do not need to be approved by the FHWA or the FTA, copies of any new/revised plans must be provided to each agency.

[58 FR 58064, Oct. 28, 1993, as amended at 61 FR 67175, Dec. 19, 1996]



§450.324   Transportation improvement program: General.

(a) The metropolitan transportation planning process shall include development of a transportation improvement program (TIP) for the metropolitan planning area by the MPO in cooperation with the State and public transit operators.

(b) The TIP must be updated at least every two years and approved by the MPO and the Governor. The frequency and cycle for updating the TIP must be compatible with the STIP development and approval process. Since the TIP becomes part of the STIP, the TIP lapses when the FHWA and FTA approval for the STIP lapses. In the case of extenuating circumstances, FHWA and FTA will consider and take appropriate action on requests to extend the STIP approval period for all or part of the STIP in accordance with §450.220(d). Although metropolitan TIPs, unlike statewide TIPs, do not need to be approved by the FHWA or the FTA, copies of any new or amended TIPs must be provided to each agency. Additionally, in nonattainment and maintenance areas for transportation related pollutants, the FHWA and the FTA, as well as the MPO, must make a conformity determination on any new or amended TIPs (unless the amendment consists entirely of exempt projects) in accordance with the Clean Air Act requirements and the EPA conformity regulations (40 CFR part 51).

(c) There must be reasonable opportunity for public comment in accordance with the requirements of §450.316(b)(1) and, in nonattainment TMAs, an opportunity for at least one formal public meeting during the TIP development process. This public meeting may be combined with the public meeting required under §450.322(c). The proposed TIP shall be published or otherwise made readily available for review and comment. Similarly, the approved TIP shall be published or otherwise made readily available for information purposes.

(d) The TIP shall cover a period of not less than 3 years, but may cover a longer period if it identifies priorities and financial information for the additional years. The TIP must include a priority list of projects to be carried out in the first three years. As a minimum, the priority list shall group the projects that are to be undertaken in each of the years, i.e., year 1, year 2, year 3. In nonattainment and maintenance areas, the TIP shall give priority to eligible TCMs identified in the approved SIP in accordance with the U.S. EPA conformity regulation (40 CFR part 51) and shall provide for their timely implementation.

(e) The TIP shall be financially constrained by year and include a financial plan that demonstrates which projects can be implemented using current revenue sources and which projects are to be implemented using proposed revenue sources (while the existing transportation system is being adequately operated and maintained). The financial plan shall be developed by the MPO in cooperation with the State and the transit operator. The State and the transit operator must provide MPOs with estimates of available Federal and State funds which the MPOs shall utilize in developing financial plans. It is expected that the State would develop this information as part of the STIP development process and that the estimates would be refined through this process. Only projects for which construction and operating funds can reasonably be expected to be available may be included. In the case of new funding sources, strategies for ensuring their availability shall be identified. In developing the financial analysis, the MPO shall take into account all projects and strategies funded under title 23, U.S.C., and the Federal Transit Act, other Federal funds, local sources, State assistance, and private participation. In nonattainment and maintenance areas, projects included for the first two years of the current TIP shall be limited to those for which funds are available or committed.

(f) The TIP shall include:

(1) All transportation projects, or identified phases of a project, (including pedestrian walkways, bicycle transportation facilities and transportation enhancement projects) within the metropolitan planning area proposed for funding under title 23, U.S.C., (including Federal Lands Highway projects) and the Federal Transit Act, excluding safety projects funded under 23 U.S.C. 402, emergency relief projects (except those involving substantial functional, locational and capacity changes), and planning and research activities (except those funded with NHS, STP, and/or MA funds). Planning and research activities funded with NHS, STP and/or MA funds, other than those used for major investment studies, may be excluded from the TIP by agreement of the State and the MPO;

(2) Only projects that are consistent with the transportation plan;

(3) All regionally significant transportation projects for which an FHWA or the FTA approval is required whether or not the projects are to be funded with title 23, U.S.C., or Federal Transit Act funds, e.g., addition of an interchange to the Interstate System with State, local, and/or private funds, demonstration projects not funded under title 23, U.S.C., or the Federal Transit Act, etc.;

(4) For informational purposes and air quality analysis in nonattainment and maintenance areas, all regionally significant transportation projects proposed to be funded with Federal funds, including intermodal facilities, not covered in paragraphs (f)(1) or (f)(3) of this section; and

(5) For informational purposes and air quality analysis in nonattainment and maintenance areas, all regionally significant projects to be funded with non-Federal funds.

(g) With respect to each project under paragraph (f) of this section the TIP shall include:

(1) Sufficient descriptive material (i.e., type of work, termini, length, etc.) to identify the project or phase;

(2) Estimated total cost;

(3) The amount of Federal funds proposed to be obligated during each program year;

(4) Proposed source of Federal and non-Federal funds;

(5) Identification of the recipient/subrecipient and State and local agencies responsible for carrying out the project;

(6) In nonattainment and maintenance areas, identification of those projects which are identified as TCMs in the applicable SIP; and

(7) In areas with Americans with Disabilities Act required Paratransit and key station plans, identification of those projects which will implement the plans.

(h) In nonattainment and maintenance areas, projects included shall be specified in sufficient detail (design concept and scope) to permit air quality analysis in accordance with the U.S. EPA conformity requirements (40 CFR part 51).

(i) Projects proposed for FHWA and/or FTA funding that are not considered by the State and MPO to be of appropriate scale for individual identification in a given program year may be grouped by function, geographic area, and work type using applicable classifications under 23 CFR 771.117 (c) and (d). In nonattainment and maintenance areas, classifications must be consistent with the exempt project classifications contained in the U.S. EPA conformity requirements (40 CFR part 51).

(j) Projects utilizing Federal funds that have been allocated to the area pursuant to 23 U.S.C. 133(d)(3)(E) shall be identified.

(k) The total Federal share of projects included in the TIP proposed for funding under section 9 of the Federal Transit Act (49 U.S.C. app. 1607a) may not exceed section 9 authorized funding levels available to the area for the program year.

(l) Procedures or agreements that distribute suballocated Surface Transportation Program or section 9 funds to individual jurisdictions or modes within the metropolitan area by predetermined percentages or formulas are inconsistent with the legislative provisions that require MPOs in cooperation with the State and transit operators to develop a prioritized and financially constrained TIP and shall not be used unless they can be clearly shown to be based on considerations required to be addressed as part of the planning process.

(m) For the purpose of including Federal Transit Act section 3 funded projects in a TIP the following approach shall be followed:

(1) The total Federal share of projects included in the first year of the TIP shall not exceed levels of funding committed to the area; and

(2) The total Federal share of projects included in the second, third and/or subsequent years of the TIP may not exceed levels of funding committed, or reasonably expected to be available, to the area.

(n) As a management tool for monitoring progress in implementing the transportation plan, the TIP shall:

(1) Identify the criteria and process for prioritizing implementation of transportation plan elements (including intermodal trade-offs) for inclusion in the TIP and any changes in priorities from previous TIPs;

(2) List major projects from the previous TIP that were implemented and identify any significant delays in the planned implementation of major projects;

(3) In nonattainment and maintenance areas, describe the progress in implementing any required TCMs, including the reasons for any significant delays in the planned implementation and strategies for ensuring their advancement at the earliest possible time; and

(4) In nonattainment and maintenance areas, include a list of all projects found to conform in a previous TIP and are now part of the base case for the purpose of air quality conformity analyses. Projects shall be included in this list until construction or acquisition has been fully authorized, except when a three-year period has elapsed subsequent to the NEPA approval without any major action taking place to advance the project.

(o) In order to maintain or establish operations, in the absence of an approved metropolitan TIP, the FTA and/or the FHWA Administrators, as appropriate, may approve operating assistance.


§450.326   Transportation improvement program: Modification.

The TIP may be modified at any time consistent with the procedures established in this part for its development and approval. In nonattainment or maintenance areas for transportation related pollutants if the TIP is amended by adding or deleting projects which contribute to and/or reduce transportation related emissions or replaced with a new TIP, new conformity determinations by the MPO and the FHWA and the FTA will be necessary. Public involvement procedures consistent with §450.316(b)(1) shall be utilized in amending the TIP, except that these procedures are not required for TIP amendments that only involve projects of the type covered in §450.324(i).


§450.328   Transportation improvement program: Relationship to statewide TIP.

(a) After approval by the MPO and the Governor, the TIP shall be included without modification, directly or by reference, in the STIP program required under 23 U.S.C. 135 and consistent with §450.220, except that in nonattainment and maintenance areas, a conformity finding by the FHWA and the FTA must be made before it is included in the STIP. After approval by the MPO and the Governor, a copy shall be provided to the FHWA and the FTA.

(b) The State shall notify the appropriate MPO and Federal Lands Highways Program agencies, e.g., Bureau of Indian Affairs and/or National Park Service, when a TIP including projects under the jurisdiction of these agencies has been included in the STIP.


§450.330   Transportation improvement program: Action required by FHWA/FTA.

(a) The FHWA and the FTA must jointly find that each metropolitan TIP is based on a continuing, comprehensive transportation process carried on cooperatively by the States, MPOs and transit operators in accordance with the provisions of 23 U.S.C. 134 and section 8 of the Federal Transit Act (49 U.S.C. app. 1607). This finding shall be based on the self-certification statement submitted by the State and MPO under §450.334 and upon other reviews as deemed necessary by the FHWA and the FTA.

(b) In nonattainment and maintenance areas, the FHWA and the FTA must also jointly find that the metropolitan TIP conforms with the adopted SIP and that priority has been given to the timely implementation of transportation control measures contained in the SIP in accordance with 40 CFR part 51. As part of their review in nonattainment areas requiring TCMs, the FHWA and the FTA will specifically consider any comments relating to the financial plans for the plan and TIP contained in the summary of significant comments required under §450.316(b). If the TIP is found to be in nonconformance with the SIP, the TIP shall be returned to the Governor and the MPO with the joint finding. If the TIP is found to conform with the SIP, the Governor/MPO shall be notified of the joint finding. After the FHWA and the FTA find the TIP to be in conformance, the TIP shall be incorporated, without modification, into the STIP, directly or by reference.


§450.332   Project selection for implementation.

(a) In areas not designated as TMAs and when §450.332(c) does not apply, projects to be implemented using title 23 funds other than Federal lands projects or Federal Transit Act funds shall be selected by the State and/or the transit operator, in cooperation with the MPO from the approved metropolitan TIP. Federal Lands Highways program projects shall be selected in accordance with 23 U.S.C. 204.

(b) In areas designated as TMAs where §450.332(c) does not apply, all title 23 and Federal Transit Act funded projects, except projects on the NHS and projects funded under the bridge, interstate maintenance, and Federal Lands Highways programs, shall be selected by the MPO in consultation with the State and transit operator from the approved metropolitan TIP and in accordance with the priorities in the approved metropolitan TIP. Projects on the NHS, and projects funded under the bridge and Interstate maintenance programs shall be selected by the State in cooperation with the MPO, from the approved metropolitan TIP. Federal Lands Highway Program projects shall be selected in accordance with 23 U.S.C. 204.

(c) Once a TIP that meets the requirements of §450.324 has been developed and approved, the first year of the TIP shall constitute an "agreed to" list of projects for project selection purposes and no further project selection action is required for the implementing agency to proceed with projects, except where the appropriated Federal funds available to the metropolitan planning area are significantly less than the authorized amounts. In this case, a revised "agreed to" list of projects shall be jointly developed by the MPO, State, and the transit operator if requested by the MPO, State, or the transit operator. If the State or transit operator wishes to proceed with a project in the second or third year of the TIP, the specific project selection procedures stated in paragraphs (a) and (b) of this section must be used unless the MPO, State, and transit operator jointly develop expedited project selection procedures to provide for the advancement of projects from the second or third year of the TIP.

(d) Projects not included in the Federally approved STIP will not be eligible for funding with title 23, U.S.C., or Federal Transit Act funds.

(e) In nonattainment and maintenance areas, priority will be given to the timely implementation of TCMs contained in the applicable SIP in accordance with the U.S. EPA conformity regulations at 40 CFR part 51.


§450.334   Metropolitan transportation planning process: Certification.

(a) The State and the MPO shall annually certify to the FHWA and the FTA that the planning process is addressing the major issues facing the area and is being conducted in accordance with all applicable requirements of:

(1) Section 134 of title 23, U.S.C., section 8 of the Federal Transit Act (49 U.S.C. app. 1607) and this part;

(2) Sections 174 and 176 (c) and (d) of the Clean Air Act (42 U.S.C. 7504, 7506 (c) and (d));

(3) Title VI of the Civil Rights Act of 1964 and the Title VI assurance executed by each State under 23 U.S.C. 324 and 29 U.S.C. 794;

(4) Section 1003(b) of the Intermodal Surface Transportation Efficiency Act of 1991 (Pub. L. 102-240) regarding the involvement of disadvantaged business enterprises in the FHWA and the FTA funded planning projects (sec. 105(f), Pub. L. 97-424, 96 Stat. 2100; 49 CFR part 23); and

(5) The provisions of the Americans with Disabilities Act of 1990 (Pub. L. 101-336, 104 Stat. 327, as amended) and U.S. DOT regulations "Transportation for Individuals with Disabilities" (49 CFR parts 27, 37, and 38).

(b) The FHWA and the FTA jointly will review and evaluate the transportation planning process for each TMA (as appropriate but no less than once every three years) to determine if the process meets the requirements of this subpart.

(c) In TMAs that are nonattainment or maintenance areas for transportation related pollutants, the FHWA and the FTA will also review and evaluate the transportation planning process to assure that the MPO has an adequate process to ensure conformity of plans and programs in accordance with procedures contained in 40 CFR part 51.

(d) Upon the review and evaluation conducted under paragraphs (b) and (c) of this section, if the FHWA and the FTA jointly determine that the transportation planning process in a TMA meets or substantially meets the requirements of this part, they will take one of the following actions, as appropriate:

(1) Jointly certify the transportation planning process;

(2) Jointly certify the transportation planning process subject to certain specified corrective actions being taken; or

(3) Jointly certify the planning process as the basis for approval of only those categories of programs or projects that the Administrators may jointly determine and subject to certain specified corrective actions being taken.

(e) A certification action under this section will remain in effect for three years unless a new certification determination is made sooner.

(f) If, upon the review and evaluation conducted under paragraph (b) or (c) of this section, the FHWA and the FTA jointly determine that the transportation planning process in a TMA does not substantially meet the requirements, they may take the following action as appropriate, if after September 30, 1993, the transportation planning process is not certified:

(1) Withhold in whole or in part the apportionment attributed to the relevant metropolitan planning area under 23 U.S.C. 133(d)(3), capital funds apportioned under section 9 of the Federal Transit Act, and section 3 funds under the Federal Transit Act (49 U.S.C. 1607(a)); or

(2) Withhold approval of all or certain categories of projects.

(g) If a transportation planning process remains uncertified for more than two consecutive years after September 30, 1994, 20 percent of the apportionment attributed to the metropolitan planning area under 23 U.S.C. 133(d)(3) and capital funds apportioned under the formula program of section 9 of the Federal Transit Act (49 U.S.C. app. 1607a) will be withheld.

(h) The State and the MPO shall be notified of the actions taken under paragraphs (f) and (g) of this section. Upon full, joint certification by the FHWA and the FTA, all funds withheld will be restored to the metropolitan area, unless they have lapsed.


§450.336   Phase-in of new requirements.

(a) Except for reflecting the consideration given the results of the management systems, the planning process and plans in nonattainment areas requiring TCMs shall comply, to the extent possible, with the requirements of this subpart by October 1, 1994. All other metropolitan areas shall comply to the extent possible with the requirements of this subpart by December 18, 1994. Where time does not permit a quantitative analysis of certain factors, a qualitative analysis of those factors will be acceptable. If a forecast period of less than twenty years is acceptable for SIP development and air quality conformity purposes, that same time period will be acceptable for transportation planning. The initial plan update shall be financially feasible, taking into account capital costs and the funds reasonably available for capital improvements, as well as addressing to the extent possible the costs of and revenues available for operating and maintenance of the transportation system. Where TCMs are required, the plan update process shall be coordinated with the process for developing TCMs. The planning process for subsequent updates of the plan and the updated plans shall comply with the requirements of this subpart. Plan updates performed in all areas must consider the results of the management systems (specified in 23 CFR part 500) as they become available. The plan shall reflect this consideration.

(b)(1) During the period prior to the full implementation of the CMS in a TMA, the MPO in cooperation with the State, the public transit operators, and other operators of major modes of transportation shall identify the location of the most serious congestion problems in the metropolitan area and proceed with the development of actions to address these problems.

(2) Prior to the full implementation of a CMS, an adequate interim CMS in a TMA designated as nonattainment for carbon monoxide and/or ozone shall, as a minimum, include a process that results in an appropriate analysis of all reasonably available (including multimodal) travel demand reduction and operational management strategies for the corridor in which a project that will result in a significant increase in SOV capacity is proposed. This analysis must demonstrate how far such strategies can go in eliminating the need for additional SOV capacity in the corridor. If the analysis demonstrates that additional SOV capacity is warranted, then all reasonable strategies to manage the facility effectively (or to facilitate its management in the future) shall be incorporated into the proposed facility. Other travel demand reduction and operational management strategies appropriate for the corridor, but not appropriate for incorporation into the SOV facility itself must be committed to by the State and the MPO for implementation in a timely manner but no later than completion of construction of the SOV facility. If the area does not already have a traffic management and carpool/vanpool program, the establishment of such programs must be a part of the commitment.

(3) In TMAs that are nonattainment for carbon monoxide and/or ozone, the MPO, a State and/or transit operator may not advance a project utilizing Federal funds that provides a significant capacity increase for SOVs (adding general purpose lanes, with the exception of safety improvements or the elimination of bottlenecks, or a new highway on a new location) beyond the NEPA process unless an interim CMS is in place that meets the criteria in paragraphs (b)(1) and (b)(2) of this section and the project results from this interim CMS.

(4) Projects that are part of or consistent with a State mandated congestion management system/plan are not subject to the requirements in paragraphs (b)(1) and (b)(2) of this section.

(5) Projects advanced beyond the NEPA process as of April 6, 1992 and which are being implemented, e.g., right-of-way acquisition has been approved, will be deemed to be programmed and not subject to this requirement.

[58 FR 58064, Oct. 28, 1993, as amended at 61 FR 67175, Dec. 19, 1996]






PART 460 -- PUBLIC ROAD MILEAGE FOR APPORTIONMENT OF HIGHWAY SAFETY FUNDS


Sec.
460.1   Purpose.
460.2   Definitions.
460.3   Procedures.

Authority: 23 U.S.C. 315, 402(c); 49 CFR 1.48.

Source: 40 FR 44322, Sept. 26, 1975, unless otherwise noted.


§460.1   Purpose.

The purpose of this part is to prescribe the policies and procedures followed in identifying and reporting public road mileage for utilization in the statutory formula for the apportionment of highway safety funds under 23 U.S.C. 402(c).


§460.2   Definitions.

As used in this part:

(a) Public road means any road under the jurisdiction of and maintained by a public authority and open to public travel.

(b) Public authority means a Federal, State, county, town, or township, Indian tribe, municipal or other local government or instrumentality thereof, with authority to finance, build, operate or maintain toll or toll-free highway facilities.

(c) Open to public travel means that the road section is available, except during scheduled periods, extreme weather or emergency conditions, passable by four-wheel standard passenger cars, and open to the general public for use without restrictive gates, prohibitive signs, or regulation other than restrictions based on size, weight, or class of registration. Toll plazas of public toll roads are not considered restrictive gates.

(d) Maintenance means the preservation of the entire highway, including surfaces, shoulders, roadsides, structures, and such traffic control devices as are necessary for its safe and efficient utilization.

(e) State means any one of the 50 States, the District of Columbia, Puerto Rico, the Virgin Islands, Guam, and American Samoa. For the purpose of the application of 23 U.S.C. 402 on Indian reservations, State and Governor of a State include the Secretary of the Interior.


§460.3   Procedures.

(a) General requirements. 23 U.S.C. 402(c) provides that funds authorized to carry out section 402 shall be apportioned according to a formula based on population and public road mileage of each State. Public road mileage shall be determined as of the end of the calendar year preceding the year in which the funds are apportioned and shall be certified to by the Governor of the State or his designee and subject to the approval of the Federal Highway Administrator.

(b) State public road mileage. Each State must annually submit a certification of public road mileage within the State to the Federal Highway Administration Division Administrator by the date specified by the Division Administrator. Public road mileage on Indian reservations within the State shall be identified and included in the State mileage and in computing the State's apportionment.

(c) Indian reservation public road mileage. The Secretary of the Interior or his designee will submit a certification of public road mileage within Indian reservations to the Federal Highway Administrator by June 1 of each year.

(d) Action by the Federal Highway Administrator. (1) The certification of Indian reservation public road mileage, and the State certifications of public road mileage together with comments thereon, will be reviewed by the Federal Highway Administrator. He will make a final determination of the public road mileage to be used as the basis for apportionment of funds under 23 U.S.C. 402(c). In any instance in which the Administrator's final determination differs from the public road mileage certified by a State or the Secretary of the Interior, the Administrator will advise the State or the Secretary of the Interior of his final determination and the reasons therefor.

(2) If a State fails to submit a certification of public road mileage as required by this part, the Federal Highway Administrator may make a determination of the State's public road mileage for the purpose of apportioning funds under 23 U.S.C. 402(c). The State's public road mileage determined by the Administrator under this subparagraph may not exceed 90 percent of the State's public road mileage utilized in determining the most recent apportionment of funds under 23 U.S.C. 402(c).




PART 470 -- HIGHWAY SYSTEMS



Subpart A -- Federal-aid Highway Systems


   Sec.
470.101   Purpose.
470.103   Definitions.
470.105   Urban area boundaries and highway functional classification.
470.107   Federal-aid highway systems.
470.109   System procedures -- General.
470.111   Interstate System procedures.
470.113   National Highway System procedures.
470.115   Approval authority.
Appendix A to Subpart A -- Guidance Criteria for Evaluating Requests for Interstate System Designations under 23 U.S.C. 139 (A) and (B).
Appendix B to Subpart A -- Designation of Segments of Section 332(A)(2) Corridors as Parts of the Interstate System.
Appendix C to Subpart A of Part 470 -- Policy for the Signing and Numbering of Future Interstate Corridors Designated by Section 332 of the NHS Designation Act of 1995 or Designated Under 23 U.S.C. 139(B).
Appendix D to Subpart A -- Guidance Criteria for Evaluating Requests for Modifications to the National Highway System.

Subparts B-C [Reserved]

Authority: 23 U.S.C. 103(b)(2), 103 (e)(1), (e)(2), and (e)(3), 103(f), 134, 135, and 315; and 49 CFR 1.48(b)(2).

Source: 40 FR 42344, Sept. 12, 1975, unless otherwise noted. Redesignated at 41 FR 51396, Nov. 22, 1976.

Subpart A -- Federal-aid Highway Systems


Source: 62 FR 33355, June 19, 1997, unless otherwise noted.


§470.101   Purpose.

This part sets forth policies and procedures relating to the identification of Federal-aid highways, the functional classification of roads and streets, the designation of urban area boundaries, and the designation of routes on the Federal-aid highway systems.


§470.103   Definitions.

Except as otherwise provided in this part, terms defined in 23 U.S.C. 101(a) are used in this part as so defined.

Consultation means that one party confers with another identified party and, prior to taking action(s), considers that party's views.

Cooperation means that the parties involved in carrying out the planning, programming and management systems processes work together to achieve a common goal or objective.

Coordination means the comparison of the transportation plans, programs, and schedules of one agency with related plans, programs, and schedules of other agencies or entities with legal standing, and adjustment of plans, programs, and schedules to achieve general consistency.

Federal-aid highway systems means the National Highway System and the Dwight D. Eisenhower National System of Interstate and Defense Highways (the "Interstate System").

Federal-aid highways means highways on the Federal-aid highway systems and all other public roads not classified as local roads or rural minor collectors.

Governor means the chief executive of the State and includes the Mayor of the District of Columbia.

Metropolitan planning organization (MPO) means the forum for cooperative transportation decisionmaking for the metropolitan planning area in which the metropolitan transportation planning process required by 23 U.S.C. 134 and 49 U.S.C. 5303-5305 must be carried out.

Responsible local officials means --

(1) In urbanized areas, principal elected officials of general purpose local governments acting through the Metropolitan Planning Organization designated by the Governor, or

(2) In rural areas and urban areas not within any urbanized area, principal elected officials of general purpose local governments.

State means any one of the fifty States, the District of Columbia, Puerto Rico, or, for purposes of functional classification of highways, the Virgin Islands, American Samoa, Guam, or the Commonwealth of the Northern Marianas.


§470.105   Urban area boundaries and highway functional classification.

(a) Urban area boundaries. Routes on the Federal-aid highway systems may be designated in both rural and urban areas. Guidance for determining the boundaries of urbanized and nonurbanized urban areas is provided in the "Federal-Aid Policy Guide," Chapter 4 [G 4063.0], dated December 9, 1991. 1

1The "Federal-aid Policy Guide" is available for inspection and copying as prescribed in 49 CFR part 7, Appendix D.

(b) Highway Functional Classification. (1) The State transportation agency shall have the primary responsibility for developing and updating a statewide highway functional classification in rural and urban areas to determine functional usage of the existing roads and streets. Guidance criteria and procedures are provided in the FHWA publication "Highway Functional Classification -- Concepts, Criteria and Procedures." 2 The State shall cooperate with responsible local officials, or appropriate Federal agency in the case of areas under Federal jurisdiction, in developing and updating the functional classification.

2This publication, revised in March 1989, is available on request to the FHWA, Office of Environment and Planning, HEP-10, 400 Seventh Street, SW., Washington, DC 20590.

(2) The results of the functional classification shall be mapped and submitted to the Federal Highway Administration (FHWA) for approval and when approved shall serve as the official record for Federal-aid highways and the basis for designation of the National Highway System.


§470.107   Federal-aid highway systems.

(a) Interstate System. (1) The Dwight D. Eisenhower National System of Interstate and Defense Highways (Interstate System) shall consist of routes of highest importance to the Nation, built to the uniform geometric and construction standards of 23 U.S.C. 109(h), which connect, as directly as practicable, the principal metropolitan areas, cities, and industrial centers, including important routes into, through, and around urban areas, serve the national defense and, to the greatest extent possible, connect at suitable border points with routes of continental importance in Canada and Mexico.

(2) The portion of the Interstate System designated under 23 U.S.C. 103 (e)(1), (e)(2), and (e)(3) shall not exceed 69,230 kilometers (43,000 miles). Additional Interstate System segments are permitted under the provisions of 23 U.S.C. 139 (a) and (c) and section 1105(e)(5)(A) of the Intermodal Surface Transportation Efficiency Act of 1991 (ISTEA), Pub. L. 102-240, 105 Stat. 1914, as amended.

(b) National Highway System. (1) The National Highway System shall consist of interconnected urban and rural principal arterials and highways (including toll facilities) which serve major population centers, international border crossings, ports, airports, public transportation facilities, other intermodal transportation facilities and other major travel destinations; meet national defense requirements; and serve interstate and interregional travel. All routes on the Interstate System are a part of the National Highway System.

(2) The National Highway System shall not exceed 286,983 kilometers (178,250 miles).

(3) The National Highway System shall include the Strategic Highway Corridor Network (STRAHNET) and its highway connectors to major military installations, as designated by the Administrator in consultation with appropriate Federal agencies and the States. The STRAHNET includes highways which are important to the United States strategic defense policy and which provide defense access, continuity, and emergency capabilities for the movement of personnel, materials, and equipment in both peace time and war time.

(4) The National Highway System shall include all high priority corridors identified in section 1105(c) of the ISTEA.


§470.109   System procedures -- General.

(a) The State transportation agency, in consultation with responsible local officials, shall have the responsibility for proposing to the Federal Highway Administration all official actions regarding the designation, or revision, of the Federal-aid highway systems.

(b) The routes of the Federal-aid highway systems shall be proposed by coordinated action of the State transportation agencies where the routes involve State-line connections.

(c) The designation of routes on the Federal-aid highway systems shall be in accordance with the planning process required, pursuant to the provisions at 23 U.S.C. 135, and, in urbanized areas, the provisions at 23 U.S.C. 134(a). The State shall cooperate with local and regional officials. In urbanized areas, the local officials shall act through the metropolitan planning organizations designated for such areas under 23 U.S.C. 134.

(d) In areas under Federal jurisdiction, the designation of routes on the Federal-aid highway systems shall be coordinated with the appropriate Federal agency.


§470.111   Interstate System procedures.

(a) Proposals for system actions on the Interstate System shall include a route description and a statement of justification. Proposals shall also include statements regarding coordination with adjoining States on State-line connections, with responsible local officials, and with officials of areas under Federal jurisdiction.

(b) Proposals for Interstate or future Interstate designation under 23 U.S.C. 139(a) or (b), as logical additions or connections, shall consider the criteria contained in appendix A of this subpart. For designation as a part of the Interstate system, 23 U.S.C. 139(a) requires that a highway meet all the standards of a highway on the Interstate System, be a logical addition or connection to the Interstate System, and have the affirmative recommendation of the State or States involved. For designation as a future part of the Interstate System, 23 U.S.C. 139(b) requires that a highway be a logical addition or connection to the Interstate System, have the affirmative recommendation of the State or States involved, and have the written agreement of the State or States involved that such highway will be constructed to meet all the standards of a highway on the Interstate System within twelve years of the date of the agreement between the FHWA Administrator and the State or States involved. Such highways must also be on the National Highway System.

(c) Proposals for Interstate designation under 23 U.S.C. 139(c) shall pertain only to Alaska or Puerto Rico. For designation as parts of the Interstate System, 23 U.S.C. 139(c) requires that highway segments be in States which have no Interstate System; be logical components to a system serving the State's principal cities, national defense needs and military installations, and traffic generated by rail, water, and air transportation modes; and have been constructed to the geometric and construction standards adequate for current and probable future traffic demands and the needs of the locality of the segment. Such highways must also be on the National Highway System.

(d) Routes proposed for Interstate designation under section 332(a)(2) of the NHS Designation Act of 1995 (NHS Act) shall be constructed to Interstate standards and connect to the Interstate System. Proposals shall consider the criteria contained in appendix B of this subpart.

(e) Proposals for Interstate route numbering shall be submitted by the State transportation agency to the Route Numbering Committee of the American Association of State Highway and Transportation Officials.

(f) Signing of corridors federally designated as future Interstate routes can follow the criteria contained in appendix C of this subpart. No law, rule, regulation, map, document, or other record of the United States, or of any State or political subdivision thereof, shall refer to any highway under 23 U.S.C. 139, nor shall any such highway be signed or marked, as a highway on the Interstate System until such time as such highway is constructed to the geometric and construction standards for the Interstate System and has been designated as a part of the Interstate System.


§470.113   National Highway System procedures.

(a) Proposals for system actions on the National Highway System shall include a route description, a statement of justification, and statements of coordination with adjoining States on State-line connections, with responsible local officials, and with officials of areas under Federal jurisdiction.

(b) Proposed modifications to the National Highway System shall enhance the national transportation characteristics of the National Highway System and shall follow the criteria listed in §470.107. Proposals shall also consider the criteria contained in appendix D of this subpart.


§470.115   Approval authority.

(a) The Federal Highway Administrator will approve Federal-aid highway system actions involving the designation, or revision, of routes on the Interstate System, including route numbers, future Interstate routes, and routes on the National Highway System.

(b) The Federal Highway Administrator will approve functional classification actions.

Appendix A to Subpart A of Part 470 -- Guidance Criteria for Evaluating Requests for Interstate System Designations Under 23 U.S.C. 139 (A) and (B)

Section 139 (a) and (b), of title 23, U.S.C., permits States to request the designation of National Highway System routes as parts or future parts of the Interstate System. The FHWA Administrator may approve such a request if the route is a logical addition or connection to the Interstate System and has been, or will be, constructed to meet Interstate standards. The following are the general criteria to be used to evaluate 23 U.S.C. 139 requests for Interstate System designations.

1. The proposed route should be of sufficient length to serve long-distance Interstate travel, such as connecting routes between principal metropolitan cities or industrial centers important to national defense and economic development.

2. The proposed route should not duplicate other Interstate routes. It should serve Interstate traffic movement not provided by another Interstate route.

3. The proposed route should directly serve major highway traffic generators. The term "major highway traffic generator" means either an urbanized area with a population over 100,000 or a similar major concentrated land use activity that produces and attracts long-distance Interstate and statewide travel of persons and goods. Typical examples of similar major concentrated land use activities would include a principal industrial complex, government center, military installation, or transportation terminal.

4. The proposed route should connect to the Interstate System at each end, with the exception of Interstate routes that connect with continental routes at an international border, or terminate in a "major highway traffic generator" that is not served by another Interstate route. In the latter case, the terminus of the Interstate route should connect to routes of the National Highway System that will adequately handle the traffic. The proposed route also must be functionally classified as a principal arterial and be a part of the National Highway System system.

5. The proposed route must meet all the current geometric and safety standards criteria as set forth in 23 CFR part 625 for highways on the Interstate System, or a formal agreement to construct the route to such standards within 12 years must be executed between the State(s) and the Federal Highway Administration. Any proposed exceptions to the standards shall be approved at the time of designation.

6. A route being proposed for designation under 23 U.S.C. 139(b) must have an approved final environmental document (including, if required, a 49 U.S.C. 303(c) [Section 4(f)] approval) covering the route and project action must be ready to proceed with design at the time of designation. Routes constructed to Interstate standards are not necessarily logical additions to the Interstate System unless they clearly meet all of the above criteria.

Appendix B to Subpart A of Part 470 -- Designation of Segments of Section 332(A)(2) Corridors as Parts of the Interstate System

The following guidance is comparable to current procedures for Interstate System designation requests under 23 U.S.C. 139(a). All Interstate System additions must be approved by the Federal Highway Administrator. The provisions of section 332(a)(2) of the NHS Act have also been incorporated into the ISTEA as section 1105(e)(5)(A).

1. The request must be submitted through the appropriate FHWA Division and Regional Offices to the Associate Administrator for Program Development (HEP-10). Comments and recommendations by the division and regional offices are requested.

2. The State DOT secretary (or equivalent) must request that the route segment be added to the Interstate System. The exact location and termini must be specified. If the route segment involves more than one State, each affected State must submit a separate request.

3. The request must provide information to support findings that the segment (a) is built to Interstate design standards and (b) connects to the existing Interstate System. The segment should be of sufficient length to provide substantial service to the travelling public.

4. The request must also identify and justify any design exceptions for which approval is requested.

5. Proposed Interstate route numbering for the segment must be submitted to FHWA and the American Association of State Highway and Transportation Officials Route Numbering

Appendix C to Subpart A of Part 470 -- Policy for the Signing and Numbering of Future Interstate Corridors Designated by Section 332 of the NHS Designation Act of 1995 or Designated Under 23 U.S.C. 139(B)

POLICY

State transportation agencies are permitted to erect informational Interstate signs along a federally designated future Interstate corridor only after the specific route location has been established for the route to be constructed to Interstate design standards.

CONDITIONS

1. The corridor must have been designated a future part of the Interstate System under section 332(a)(2) of the NHS Designation Act of 1995 or 23 U.S.C. 139(b).

2. The specific route location to appropriate termini must have received Federal Highway (FHWA) environmental clearance. Where FHWA environmental clearance is not required or Interstate standards have been met, the route location must have been publicly announced by the State.

3. Numbering of future Interstate route segments must be coordinated with affected States and be approved by the American Association of State Highway and Transportation Officials and the FHWA at Headquarters. Short portions of a multistate corridor may require use of an interim 3-digit number.

4. The State shall coordinate the location and content of signing near the State line with the adjacent State.

5. Signing and other identification of a future Interstate route segment must not indicate, nor imply, that the route is on the Interstate System.

6. The FHWA Regional Office must confirm in advance that the above conditions have been met and approve the general locations of signs.

SIGN DETAILS

1. Signs may not be used to give directions and should be away from directional signs, particularly at interchanges.

2. An Interstate shield may be located on a green informational sign of a few words. For example: Future Interstate Corridor or Future I-00 Corridor.

3. The Interstate shield may not include the word "Interstate."

4. The FHWA Division Office must approve the signs as to design, wording, and detailed location.

Appendix D to Subpart A of Part 470 -- Guidance Criteria for Evaluating Requests for Modifications to the National Highway System

Section 103(b), of title 23, U.S.C., allows the States to propose modifications to the National Highway System (NHS) and authorizes the Secretary to approve such modifications provided that they meet the criteria established for the NHS and enhance the characteristics of the NHS. In proposing modifications under 23 U.S.C. 103(b), the States must cooperate with local and regional officials. In urbanized areas, the local officials must act through the metropolitan planning organization (MPO) designated for such areas under 23 U.S.C. 134. The following guidance criteria should be used by the States to develop proposed modifications to the NHS.

1. Proposed additions to the NHS should be included in either an adopted State or metropolitan transportation plan or program.

2. Proposed additions should connect at each end with other routes on the NHS or serve a major traffic generator.

3. Proposals should be developed in consultation with local and regional officials.

4. Proposals to add routes to the NHS should include information on the type of traffic served (i.e., percent of trucks, average trip length, local, commuter, interregional, interstate) by the route, the population centers or major traffic generators served by the route, and how this service compares with existing NHS routes.

5. Proposals should include information on existing and anticipated needs and any planned improvements to the route.

6. Proposals should include information concerning the possible effects of adding or deleting a route to or from the NHS might have on other existing NHS routes that are in close proximity.

7. Proposals to add routes to the NHS should include an assessment of whether modifications (adjustments or deletions) to existing NHS routes, which provide similar service, may be appropriate.

8. Proposed modifications that might affect adjoining States should be developed in cooperation with those States.

9. Proposed modifications consisting of connections to major intermodal facilities should be developed using the criteria set forth below. These criteria were used for identifying initial NHS connections to major intermodal terminals. The primary criteria are based on annual passenger volumes, annual freight volumes, or daily vehicular traffic on one or more principal routes that serve the intermodal facility. The secondary criteria include factors which underscore the importance of an intermodal facility within a specific State.

PRIMARY CRITERIA

Commercial Aviation Airports

1. Passengers -- scheduled commercial service with more than 250,000 annual enplanements.

2. Cargo -- 100 trucks per day in each direction on the principal connecting route, or 100,000 tons per year arriving or departing by highway mode.

Ports

1. Terminals that handle more than 50,000 TEUs (a volumetric measure of containerized cargo which stands for twenty-foot equivalent units) per year, or other units measured that would convert to more than 100 trucks per day in each direction. (Trucks are defined as large single-unit trucks or combination vehicles handling freight.)

2. Bulk commodity terminals that handle more than 500,000 tons per year by highway or 100 trucks per day in each direction on the principal connecting route. (If no individual terminal handles this amount of freight, but a cluster of terminals in close proximity to each other does, then the cluster of terminals could be considered in meeting the criteria. In such cases, the connecting route might terminate at a point where the traffic to several terminals begins to separate.)

3. Passengers -- terminals that handle more than 250,000 passengers per year or 1,000 passengers per day for at least 90 days during the year.

Truck/Rail

1. 50,000 TEUs per year, or 100 trucks per day, in each direction on the principal connecting route, or other units measured that would convert to more than 100 trucks per day in each direction. (Trucks are defined as large single-unit trucks or combination vehicles carrying freight.)

Pipelines

1. 100 trucks per day in each direction on the principal connecting route.

Amtrak

1. 100,000 passengers per year (entrainments and detrainments). Joint Amtrak, intercity bus and public transit terminals should be considered based on the combined passenger volumes. Likewise, two or more separate facilities in close proximity should be considered based on combined passenger volumes.

Intercity Bus

1. 100,000 passengers per year (boardings and deboardings).

Public Transit

1. Stations with park and ride lots with more than 500 vehicle parking spaces, or 5,000 daily bus or rail passengers, with significant highway access (i.e., a high percentage of the passengers arrive by cars and buses using a route that connects to another NHS route), or a major hub terminal that provides for the transfer of passengers among several bus routes. (These hubs should have a significant number of buses using a principal route connecting with the NHS.)

Ferries

1. Interstate/international -- 1,000 passengers per day for at least 90 days during the year. (A ferry which connects two terminals within the same metropolitan area should be considered as local, not interstate.)

2. Local -- see public transit criteria above.

SECONDARY CRITERIA

Any of the following criteria could be used to justify an NHS connection to an intermodal terminal where there is a significant highway interface:

1. Intermodal terminals that handle more than 20 percent of passenger or freight volumes by mode within a State;

2. Intermodal terminals identified either in the Intermodal Management System or the State and metropolitan transportation plans as a major facility;

3. Significant investment in, or expansion of, an intermodal terminal; or

4. Connecting routes targeted by the State, MPO, or others for investment to address an existing, or anticipated, deficiency as a result of increased traffic.

PROXIMATE CONNECTIONS

Intermodal terminals, identified under the secondary criteria noted above, may not have sufficient highway traffic volumes to justify an NHS connection to the terminal. States and MPOs should fully consider whether a direct connection should be identified for such terminals, or whether being in the proximity (2 to 3 miles) of an NHS route is sufficient.

Subparts B-C    [Reserved]




PART 476 -- INTERSTATE HIGHWAY SYSTEM



Subpart A -- General


   Sec.
476.2   Definitions.

Subparts B-C [Reserved]


Subpart D -- Withdrawal of Interstate Segments and Substitution of Public Mass Transit or Highway Projects or Both

476.300   Purpose.
476.302   Applicability.
476.304   Withdrawal request.
476.306   Withdrawal approval.
476.308   Concept approval for substitute projects.
476.310   Proposals for substitute public mass transit and highway projects.
476.312   Combined proposal.
476.314   Administrator's review and approval of substitute projects.

Authority: 23 U.S.C. 103(e)(2), 103(e)(4), 103(g), 103(h) and 315; 49 CFR 1.48(b) and 1.50(f).

Subpart A -- General



§476.2   Definitions.

(a) Except as otherwise provided, terms defined in 23 U.S.C. 101(a) are used in this part as so defined.

(b) The following terms, where used in the regulations in this part, have the following meaning:

(1) Base cost year for the latest Interstate System cost estimate approved by Congress shall be the calendar year specified in the Interstate Cost Estimate Manual 1 for that estimate. For example, the base cost year for the 1972 estimate is 1970.

1The "Instructional Manual for the Preparation and Submission of the (Year) Estimate of the Cost of Completing the Interstate System in Accordance with section 104(b)(5) of title 23 U.S.C., Highways," published by the Federal Highway Administration, U.S. Department of Transportation, is available for inspection and copying as prescribed in 49 CFR part 7, appendix D.

(2) Concurrence means written agreement which is currently binding on the concurring party and which addresses the specific proposal being submitted for approval.

(3) Governor means the Governor of any one of the fifty States and the Mayor of the District of Columbia. It also refers to any State or local entity specifically designated by the Governor for the purpose of executing any of his/her responsibilities under this part.

(4) Interstate segment means any designated, toll-free route, or portion thereof, of the Interstate System.

(5) Local governments concerned means local units of general purpose government under State law within whose jurisdiction the Interstate segment lies, or is to be withdrawn.

(6) Open to traffic means a segment which has been constructed or has had major improvements with Federal-aid Interstate funds and open to normal Interstate traffic; or a segment which was an existing freeway, meeting acceptable Interstate geometric standards and recognized as the final location of the route, when incorporated into the System. Open to traffic does not mean a segment of existing highway that is ultimately planned to be replaced by an entirely new facility.

(7) Responsible local officials means:

(i) In urbanized areas, principal elected officials of general purpose local governments acting through the Metropolitan Planning Organization in accordance with part 450, subpart A of this title, and;

(ii) In rural areas and urban areas not within any urbanized area, principal elected officials of general purpose local governments.

(8) Substitute highway project means any undertaking for highway construction, which may encompass phases of work including preliminary engineering, right-of-way, and actual construction, individually or any combination thereof, on any of the Federal-aid systems described in 23 U.S.C. 103 and which is eligible for Federal financial assistance under title 23, U.S.C. A substitute highway project may include the construction of exclusive or preferential bus lanes, high occupancy vehicle lanes, highway traffic control devices, bus passenger loading areas and facilities (including shelters), and fringe and corridor parking facilities to serve bus and other public mass transportation passengers. A substitute highway project may also be a carpool and vanpool project including but not limited to, providing carpooling opportunities to the elderly and handicapped, systems for locating potential riders and informing them of convenient carpool opportunities, acquiring vehicles appropriate for carpool use, designating existing highway lanes as preferential carpool highway lanes, providing related traffic control devices, and designating existing facilities for use as preferential parking for carpools.

(9) Substitute nonhighway public mass transit project means any undertaking to develop or improve public mass transit facilities or equipment. A project in an urbanized area must be included in and related to the transportation improvement program (TIP) required under 23 CFR part 450, subpart B. The TIP in urbanized areas and all projects in nonurbanized areas must include either the construction of fixed rail facilities, or the purchase of passenger equipment, or both. Passenger equipment includes buses, fixed rail rolling stock, and other transportation equipment for passenger use.

(10) Under construction or under contract for construction means funds for physical construction have been obligated (for highway projects) or have been included in an approved grant (for transit projects) which would commit the final development of the ultimate project in both length and scope. When projects do not involve physical construction, under construction or under contract for construction means the obligation of funds (for highway projects) or grant approval (for transit projects) has occurred.

[45 FR 69396, Oct. 20, 1980, as amended at 51 FR 39748, Oct. 31, 1986]




Subparts B-C [Reserved]

Subpart D -- Withdrawal of Interstate Segments and Substitution of Public Mass Transit or Highway Projects or Both


Source: 45 FR 69397, Oct. 20, 1980, unless otherwise noted.


§476.300   Purpose.

The purpose of the regulations in this subpart is to prescribe policies and procedures for implementation of 23 U.S.C. 103(e)(4), which permits the withdrawal of Interstate System segments and the substitution of public mass transit or highway projects or both.


§476.302   Applicability.

(a) Except as provided in paragraph (b) of this section, this subpart applies to an Interstate segment at any stage of development if:

(1) The segment is within an urbanized area; or

(2) The segment passes through and connects urbanized areas within a State.

(b) The regulations in this subpart shall not apply to:

(1) A segment removed from the Interstate System prior to August 13, 1973;

(2) A segment added to the Interstate System after May 5, 1976, under the provisions of 23 U.S.C. 103(e)(2);

(3) Interstate segments designated under 23 U.S.C. 139;

(4) A toll bridge, tunnel, or approach thereto for which funds were advanced in accordance with 23 U.S.C. 124(b); or

(5) After September 30, 1979, an Interstate segment open to traffic before the date of the proposed withdrawal. If only a portion of an Interstate segment (between logical termini) is open to traffic the regulations of this subpart are applicable to the portion not open to traffic. The open to traffic portion will be removed from the Interstate System under 23 U.S.C. 103(f).

(6) Any segment added to the Interstate System by specific legislation unless a comparable statute permitting its withdrawal is enacted.

(7) A segment added to the Interstate System after August 13, 1973, under the provisions of 23 U.S.C. 103(e)(1).

(c) Withdrawal requests may not be approved under this subpart after September 30, 1983, unless the route segment was under a court injunction prohibiting its construction as of November 6, 1978. For segments under such injunction, withdrawal requests may not be approved under this subpart after September 30, 1986. However, as indicated in §476.310(g), the September 30, 1986, substitute project construction time limitation remains applicable to these segments.

[45 FR 69397, Oct. 20, 1980, as amended at 46 FR 45603, Sept. 14, 1981]



§476.304   Withdrawal request.

(a) A request to withdraw an Interstate segment within a State under this subpart shall be submitted jointly by the Governor and local governments concerned. For those segments within urbanized areas, the concurrence of responsible local officials is also required. The withdrawal request shall be submitted to the Federal Highway Admininstrator and the Urban Mass Transportation Administrator, through the Federal Highway Administrator.

(b) Joint submittal may be accomplished by a single request prepared by the Governor and concurred in by the local governments concerned. This may also be accomplished by a request by the Governor with separate concurrence documentation by the local governments concerned. In either case, for those segments within urbanized areas, the concurrence of responsible local officials is also required. While unanimous local action is not required, the withdrawal request is expected to have substantial support.

(c) The request for withdrawal shall include the following:

(1) A statement that the request is filed pursuant to 23 U.S.C. 103(e)(4).

(2) Reasons why the segment is not essential to the completion of a unified and connected Interstate System.

(3) A detailed statement of mileage and cost of the segment to be withdrawn as included in the latest Interstate cost estimate approved by Congress.

(4) An assurance that a toll road will not be constructed in the traffic corridor which would be served by the segment.


§476.306   Withdrawal approval.

(a) The Federal Highway Administrator and the Urban Mass Transportation Administrator may approve the withdrawal of an Interstate segment under the provisions of this subpart after considering the impact of the withdrawal on national defense needs if:

(1) The requirements of §476.304 are met; and

(2) The Federal Highway Administrator determines that the segment is not essential to completion of a unified and connected Interstate System.

(b) When the withdrawal of an Interstate segment is approved under paragraph (a) of this section, an amount equal to the Federal share of the cost to complete the withdrawn segment as shown in the latest Interstate System cost estimate approved by Congress is authorized for substitute projects. The amount authorized will be increased or decreased, as determined by the Federal Highway Administrator, based on changes in construction costs of the withdrawn route occurring between the base cost year of the latest cost estimate approved by Congress which included the costs of the withdrawn route and the date of approval of each substitute project. The changes in construction costs will be computed on the basis of the Composite Index shown in the quarterly publication "Price Trends for Federal- Aid Highway Construction." 1 For purposes of cost adjustments, the Composite Index for the calendar quarter within which the approval of the substitute project occurs will be used in computing the change in construction costs.

1Published by FHWA, Interstate Reports Branch, and available for inspection and copying as prescribed in 49 CFR part 7, appendix D.

(c) Authorizations of funds made available by the withdrawal of an Interstate route under 23 U.S.C. 103(e)(4) shall remain available until expended within the limitations described in §476.310 (f) and (g).

(d) Effective as of date of approval of the withdrawal of an Interstate segment, the unobligated apportionments for the Interstate System of the State receiving the approval will be reduced in the proportion that the Federal share of the cost of the withdrawn segment bears to the Federal share of the total cost of all Interstate routes in the State as reported in the latest Interstate System cost estimate approved by Congress.

(e) Mileage withdrawn under the provisions of this subpart may not be redesignated in any State under any provision of title 23 U.S.C.

(f) The payback of Federal-aid Interstate funds expended on a segment withdrawn under this subpart shall be governed by 23 CFR part 480, Use and Disposition of Property Acquired by States for Modified or Terminated Highway Projects.

(g) Segments withdrawn under the provisions of this subpart may not be redesignated under the provisions of 23 U.S.C. 139.


§476.308   Concept approval for substitute projects.

(a) A concept program which identifies the proposed substitute projects to be approved in concept and which, as a minimum, accounts for all unobligated funding made available by this subpart must be submitted as soon as practicable after the effective date of this subpart or after a withdrawal is formally approved.

(1) The substitute project concepts included in the program must be selected in a manner consistent with the procedures provided in §476.310(b) and (c).

(2) The concept program submission must contain:

(i) A proposed split, if any, of Interstate withdrawal authorizations between transit and highway projects;

(ii) A concept description (e.g., type of work, termini, length, estimated cost, number and type of vehicles, size and type of facility, identification of major transportation investment, etc.) of the proposed transit and/or highway projects for which concept approval is requested; and

(iii) A summary of the anticipated level of overall funding needs by individual fiscal year, as estimated on a general transit and/or highway basis.

(3) The concept program shall be endorsed by the Governor and the responsible local officials.

(4) The concept program should be submitted by the Governor to the Federal Highway Administrator and the Urban Mass Transportation Administrator, through the Federal Highway Administrator.

(b) Approval of substitute project concepts must be given jointly by the Federal Highway Administrator and the Urban Mass Transportation Administrator by September 30, 1983. This time limitation does not apply to segments which were under court injunction prohibiting construction as of November 6, 1978.

(1) Adjustments and refinements to the previously approved project concepts may be permitted after September 30, 1983.

(2) Approval of the project concepts does not commit funding under this subpart nor does such approval constitute an obligation on the State or local governments to fully implement the project concepts. Approval of a project concept is processed as a categorical exclusion under 23 CFR part 771.


§476.310   Proposals for substitute public mass transit and highway projects.

(a) The proposed substitute projects must serve the urbanized area or connecting nonurbanized area corridor, or both, from which the Interstate segment was withdrawn.

(b) Substitute projects in or serving urbanized areas shall be based on an urban transportation planning process in accordance with 23 CFR part 450, subpart A (and policies and regulations pertaining thereto), and shall be selected by the responsible local officials of the urbanized area in accordance with 23 CFR part 450, subpart B. Substitute projects located outside but serving the urbanized area shall also have the concurrence of the responsible local officials of the jurisdiction in which the project is located.

(c) Substitute projects in or serving the nonurbanized area corridor shall be selected by the responsible local officials of the nonurbanized area corridor. Substitute projects located outside but serving the nonurbanized area corridor shall also have the concurrence of the responsible local officials of the jurisdiction in which the project is located.

(d) Applications for substitute nonhighway public mass transit projects shall be developed either by the principal elected officials of general purpose local units of government in consultation with local transit officials or by local transit officials. Substitute highway projects shall be developed in accordance with the policies and procedures established for the Federal-aid highway system of which they will be a part. Substitute highway projects need not appear in the statewide Federal-aid program described in 23 CFR part 630, subpart A.

(e) Applications for substitute nonhighway public mass transit projects are submitted to the Urban Mass Transportation Administrator by the Governor. Requests for authorization to proceed with substitute highway projects are submitted to the Federal Highway Administrator by the Governor.

(f) After September 30, 1983, only applications for those substitute projects which have previously received concept approval under §476.308 should be submitted.

(g) Substitute projects (for which sufficient funds are available) must be under construction or under contract for construction by September 30, 1986. This time limitation is applicable to all substitute projects, including those related to Interstate segments which were under court injunction prohibiting construction on November 6, 1978. Approval for substitute projects not meeting this requirement will be withdrawn or not issued, and no funds will be appropriated or authorized for these projects.

[45 FR 69397, Oct. 20, 1980, as amended at 51 FR 39748, Oct. 31, 1986]



§476.312   Combined proposal.

A proposal for one or more substitute projects may be combined with projects utilizing other Federal funds available including, but not limited to, financial assistance available under either the Urban Mass Transportation Act of 1964, as amended, or 23 U.S.C. 104. Only the funds available from a withdrawal under this subpart are constrained by the limiting amount described in §476.306(b).


§476.314   Administrator's review and approval of substitute projects.

(a) The Urban Mass Transportation Administrator shall review substitute nonhighway public mass transit projects and the Federal Highway Administrator shall review substitute highway projects to determine that the projects meet the following requirements.

(1) The proposed projects serve the urbanized area or connecting nonurbanized area corridor or both from which the Interstate segment was withdrawn.

(2) The Federal share of the costs of the proposed projects which is to be provided under this subpart by virtue of the withdrawal of an Interstate segment does not exceed the Federal share of the cost of the withdrawn segment, as determined in §476.306(b).

(b) Approval of substitute projects can be given only to the extent that authority to obligate the funds is available.

(c) For substitute nonhighway public mass transit projects, the approval of the plans, specifications, and estimates of a project, or any phase thereof, shall be deemed to occur on the date the Urban Mass Transportation Administrator approved the substitute project or phase thereof in accordance with the policies and procedures established for the UMTA section 3 capital grant program.

(d) Substitute highway projects will be approved by the Federal Highway Administrator in accordance with policies and procedures established for the Federal-aid highway program.

(e) Approval of a substitute project or phase thereof obligates the United States to pay its proportional share of the cost of the project or phase thereof out of the general funds in the Treasury.

(f) The Federal share for substitute projects approved after November 6, 1978, shall not exceed 85 percentum, notwithstanding the Federal share for nonhighway public mass transit projects established under the Urban Mass Transportation Act of 1964, as amended, and highway projects under title 23 U.S.C.

(g) The labor protective provisions of section 3(e)(4) of the UMT Act of 1964, as amended, (49 U.S.C. section 1602(e)(4)) are applicable to nonhighway public mass transit projects funded under the provisions of this subpart.


SUBCHAPTER F -- TRANSPORTATION INFRASTRUCTURE MANAGEMENT




PART 500 -- MANAGEMENT AND MONITORING SYSTEMS



Subpart A -- Management systems


   Sec.
500.101   Purpose.
500.102   Policy.
500.103   Definitions.
500.104   State option.
500.105   Requirements.
500.106   PMS.
500.107   BMS.
500.108   SMS.
500.109   CMS.
500.110   PTMS.
500.111   IMS.

Subpart B -- Traffic Monitoring System


   Sec.
500.201   Purpose.
500.202   TMS definitions.
500.203   TMS general requirements.
500.204   TMS components for highway traffic data.

Authority: 23 U.S.C. 134, 135, 303 and 315; 49 U.S.C. 5303-5305; 23 CFR 1.32; and 49 CFR 1.48 and 1.51.

Source: 61 FR 67170, Dec. 19, 1996, unless otherwise noted.

Subpart A -- Management Systems



§500.101   Purpose.

The purpose of this part is to implement the requirements of 23 U.S.C. 303(a) which directs the Secretary of Transportation (the Secretary) to issue regulations for State development, establishment, and implementation of systems for managing highway pavement of Federal-aid highways (PMS), bridges on and off Federal-aid highways (BMS), highway safety (SMS), traffic congestion (CMS), public transportation facilities and equipment (PTMS), and intermodal transportation facilities and systems (IMS). This regulation also implements 23 U.S.C. 303(b) which directs the Secretary to issue guidelines and requirements for State development, establishment, and implementation of a traffic monitoring system for highways and public transportation facilities and equipment (TMS).


§500.102   Policy.

(a) Federal, State, and local governments are under increasing pressure to balance their budgets and, at the same time, respond to public demands for quality services. Along with the need to invest in America's future, this leaves transportation agencies with the task of trying to manage current transportation systems as cost-effectively as possible to meet evolving, as well as backlog needs. The use of existing or new transportation management systems provides a framework for cost-effective decision making that emphasizes enhanced service at reduced public and private life-cycle cost. The primary outcome of transportation management systems is improved system performance and safety. The Federal Highway Administration (FHWA) and the Federal Transit Administration (FTA) strongly encourage implementation of transportation management systems consistent with State, metropolitan planning organization, transit operator, or local government needs.

(b) Whether the systems are developed under the provisions of this part or under a State's own procedures, the following categories of FHWA administered funds may be used for development, establishment, and implementation of any of the management systems and the traffic monitoring system: National highway system; surface transportation program; State planning and research and metropolitan planning funds (including the optional use of minimum allocation funds authorized under 23 U.S.C. 157(c) and restoration funds authorized under §202(f) of the National Highway System Designation Act of 1995 (Pub.L. 104-59) for carrying out the provisions of 23 U.S.C. 307(c)(1) and 23 U.S.C. 134(a)); congestion mitigation and air quality improvement program funds for those management systems that can be shown to contribute to the attainment of a national ambient air quality standard; and apportioned bridge funds for development and establishment of the bridge management system. The following categories of FTA administered funds may be used for development, establishment, and implementation of the CMS, PTMS, IMS, and TMS: Metropolitan planning; State planning and research, and formula transit funds.


§500.103   Definitions.

Unless otherwise specified in this part, the definitions in 23 U.S.C. 101(a) are applicable to this part. As used in this part:

Federal-aid highways means those highways eligible for assistance under title 23, U.S.C., except those functionally classified as local or rural minor collectors.

Metropolitan planning organization (MPO) means the forum for cooperative transportation decision making for a metropolitan planning area.

National Highway System (NHS) means the system of highways designated and approved in accordance with the provisions of 23 U.S.C. 103(b).

State means any one of the fifty States, the District of Columbia, or Puerto Rico.

Transportation management area (TMA) means an urbanized area with a population over 200,000 (as determined by the latest decennial census) or other area when TMA designation is requested by the Governor and the MPO (or affected local officials), and officially designated by the Administrators of the FHWA and the FTA. The TMA designation applies to the entire metropolitan planning area(s).


§500.104   State option.

Except as specified in §500.105 (a) and (b), a State may elect at any time not to implement any one or more of the management systems required under 23 U.S.C. 303, in whole or in part.


§500.105   Requirements.

(a) The metropolitan transportation planning process (23 U.S.C. 134 and 49 U.S.C. 5303-5005) in TMAs shall include a CMS that meets the requirements of §500.109 of this regulation.

(b) States shall develop, establish, and implement a TMS that meets the requirements of subpart B of this regulation.

(c) Any of the management systems that the State chooses to implement under 23 U.S.C. 303 and this regulation shall be developed in cooperation with MPOs in metropolitan areas, affected agencies receiving assistance under the Federal Transit Act (49 U.S.C., Chapter 53), and other agencies (including private owners and operators) that have responsibility for operation of the affected transportation systems or facilities.

(d) The results (e.g., policies, programs, projects, etc.) of any of the management systems that a State chooses to develop under 23 U.S.C. 303 and this regulation shall be considered in the development of metropolitan and statewide transportation plans and improvement programs and in making project selection decisions under title 23, U.S.C., and under the Federal Transit Act. Plans and programs adopted after September 30, 1997, shall demonstrate compliance with this requirement.


§500.106   PMS.

An effective PMS for Federal-aid highways is a systematic process that provides information for use in implementing cost-effective pavement reconstruction, rehabilitation, and preventative maintenance programs and that results in pavements designed to accommodate current and forecasted traffic in a safe, durable, and cost-effective manner. The PMS should be based on the "AASHTO Guidelines for Pavement Management Systems." 1

1AASHTO Guidelines for Pavement Management Systems, July 1990, can be purchased from the American Association of State Highway and Transportation Officials, 444 N. Capitol Street, NW., Suite 249, Washington, D.C. 20001. Available for inspection as prescribed in 49 CFR part 7, appendix D.


§500.107   BMS.

An effective BMS for bridges on and off Federal-aid highways that should be based on the "AASHTO Guidelines for Bridge Management Systems" 2 and that supplies analyses and summaries of data, uses mathematical models to make forecasts and recommendations, and provides the means by which alternative policies and programs may be efficiently considered. An effective BMS should include, as a minimum, formal procedures for:

2AASHTO Guidelines for Bridge Management Systems, 1992, can be purchased from the American Association of State Highway and Transportation Officials, 444 N. Capitol Street, NW., Suite 249, Washington, D.C. 20001. Available for inspection as prescribed in 49 CFR part 7, appendix D.

(a) Collecting, processing, and updating data;

(b) Predicting deterioration;

(c) Identifying alternative actions;

(d) Predicting costs;

(e) Determining optimal policies;

(f) Performing short- and long-term budget forecasting; and

(g) Recommending programs and schedules for implementation within policy and budget constraints.


§500.108   SMS.

An SMS is a systematic process with the goal of reducing the number and severity of traffic crashes by ensuring that all opportunities to improve highway safety are identified, considered, implemented as appropriate, and evaluated in all phases of highway planning, design, construction, maintenance, and operation and by providing information for selecting and implementing effective highway safety strategies and projects. The development of the SMS may be based on the guidance in "Safety Management Systems: Good Practices for Development and Implementation." 3 An effective SMS should include, at a minimum:

3Safety Management Systems: Good Practices for Development and Implementation, FHWA and NHTSA, May 1996. Available for inspection and copying as prescribed in 49 CFR part 7, appendix D.

(a) Communication, coordination, and cooperation among the organizations responsible for the roadway, human, and vehicle safety elements;

(b) A focal point for coordination of the development, establishment, and implementation of the SMS among the agencies responsible for these major safety elements;

(c) Establishment of short- and long-term highway safety goals to address identified safety problems;

(d) Collection, analysis, and linkage of highway safety data;

(e) Identification of the safety responsibilities of units and positions;

(f) Public information and education activities; and

(g) Identification of skills, resources, and training needs to implement highway safety programs.


§500.109   CMS.

(a) For purposes of this regulation, congestion means the level at which transportation system performance is no longer acceptable due to traffic interference. The level of system performance deemed acceptable by State and local officials may vary by type of transportation facility, geographic location (metropolitan area or subarea, rural area), and/or time of day. An effective CMS is a systematic process for managing congestion that provides information on transportation system performance and on alternative strategies for alleviating congestion and enhancing the mobility of persons and goods to levels that meet State and local needs. The CMS results in serious consideration of implementation of strategies that provide the most efficient and effective use of existing and future transportation facilities. In both metropolitan and non-metropolitan areas, consideration needs to be given to strategies that reduce SOV travel and improve existing transportation system efficiency. Where the addition of general purpose lanes is determined to be an appropriate strategy, explicit consideration is to be given to the incorporation of appropriate features into the SOV project to facilitate future demand management and operational improvement strategies that will maintain the functional integrity of those lanes.

(b) In addition to the criteria in paragraph (a) of this section, in all TMAs, the CMS shall be developed, established and implemented as part of the metropolitan planning process in accordance with 23 CFR 450.320(c) and shall include:

(1) Methods to monitor and evaluate the performance of the multimodal transportation system, identify the causes of congestion, identify and evaluate alternative actions, provide information supporting the implementation of actions, and evaluate the efficiency and effectiveness of implemented actions;

(2) Definition of parameters for measuring the extent of congestion and for supporting the evaluation of the effectiveness of congestion reduction and mobility enhancement strategies for the movement of people and goods. Since levels of acceptable system performance may vary among local communities, performance measures and service thresholds should be tailored to the specific needs of the area and established cooperatively by the State, affected MPO(s), and local officials in consultation with the operators of major modes of transportation in the coverage area;

(3) Establishment of a program for data collection and system performance monitoring to define the extent and duration of congestion, to help determine the causes of congestion, and to evaluate the efficiency and effectiveness of implemented actions. To the extent possible, existing data sources should be used, as well as appropriate application of the real-time system performance monitoring capabilities available through Intelligent Transportation Systems (ITS) technologies;

(4) Identification and evaluation of the anticipated performance and expected benefits of appropriate traditional and nontraditional congestion management strategies that will contribute to the more efficient use of existing and future transportation systems based on the established performance measures. The following categories of strategies, or combinations of strategies, should be appropriately considered for each area: Transportation demand management measures, including growth management and congestion pricing; traffic operational improvements; public transportation improvements; ITS technologies; and, where necessary, additional system capacity.

(5) Identification of an implementation schedule, implementation responsibilities, and possible funding sources for each strategy (or combination of strategies) proposed for implementation; and

(6) Implementation of a process for periodic assessment of the efficiency and effectiveness of implemented strategies, in terms of the area's established performance measures. The results of this evaluation shall be provided to decision makers to provide guidance on selection of effective strategies for future implementation.

(c) In a TMA designated as nonattainment for carbon monoxide and/or ozone, the CMS shall provide an appropriate analysis of all reasonable (including multimodal) travel demand reduction and operational management strategies for the corridor in which a project that will result in a significant increase in capacity for SOVs (adding general purpose lanes to an existing highway or constructing a new highway) is proposed. If the analysis demonstrates that travel demand reduction and operational management strategies cannot fully satisfy the need for additional capacity in the corridor and additional SOV capacity is warranted, then the CMS shall identify all reasonable strategies to manage the SOV facility effectively (or to facilitate its management in the future). Other travel demand reduction and operational management strategies appropriate for the corridor, but not appropriate for incorporation into the SOV facility itself shall also be identified through the CMS. All identified reasonable travel demand reduction and operational management strategies shall be incorporated into the SOV project or committed to by the State and MPO for implementation.

(d)(1) Compliance with the requirement that the planning process in all TMAs include a CMS will be addressed during metropolitan planning process certification reviews for all TMAs specified in 23 CFR 450.334. If the metropolitan planning process in a TMA does not include a CMS that meets the requirements of this section, deficiencies will be noted and corrections will need to be made in accordance with the schedule established in the certification review.

(2) Until October 1, 1997, the interim CMS procedures in 23 CFR 450.336(b) may be used to meet the requirement in 23 U.S.C. 134(l) that Federal funds may not be programmed in a carbon monoxide and/or ozone nonattainment TMA for any highway project that will result in a significant increase in single-occupant-vehicle capacity unless the project is based on an approved CMS. After September 30, 1997, such projects must be based on a CMS that meets the requirements of this part.


§500.110   PTMS.

An effective PTMS for public transportation facilities (e.g., maintenance facilities, stations, terminals, transit related structures), equipment, and rolling stock is a systematic process that collects and analyzes information on the condition and cost of transit assets on a continual basis, identifies needs, and enables decision makers to select cost-effective strategies for providing and maintaining transit assets in serviceable condition. The PTMS should cover public transportation systems operated by the State, local jurisdictions, public transportation agencies and authorities, and private (for profit and non-profit) transit operators receiving funds under the Federal Transit Act and include, at a minimum:

(a) Development of transit asset condition measures and standards;

(b) An inventory of the transit assets including age, condition, remaining useful life, and replacement cost; and

(c) Identification, evaluation, and implementation of appropriate strategies and projects.


§500.111   IMS.

An effective IMS for intermodal facilities and systems provides efficient, safe, and convenient movement of people and goods through integration of transportation facilities and systems and improvement in the coordination in planning, and implementation of air, water, and the various land-based transportation facilities and systems. An IMS should include, at a minimum:

(a) Establishment of performance measures;

(b) Identification of key linkages between one or more modes of transportation, where the performance or use of one mode will affect another;

(c) Definition of strategies for improving the effectiveness of these modal interactions; and

(d) Evaluation and implementation of these strategies to enhance the overall performance of the transportation system.

Subpart B -- Traffic Monitoring System



§500.201   Purpose.

The purpose of this subpart is to set forth requirements for development, establishment, implementation, and continued operation of a traffic monitoring system for highways and public transportation facilities and equipment (TMS) in each State in accordance with the provisions of 23 U.S.C. 303 and subpart A of this part.


§500.202   TMS definitions.

Unless otherwise specified in this part, the definitions in 23 U.S.C. 101(a) and §500.103 are applicable to this subpart. As used in this part:

Highway traffic data means data used to develop estimates of the amount of person or vehicular travel, vehicle usage, or vehicle characteristics associated with a system of highways or with a particular location on a highway. These types of data support the estimation of the number of vehicles traversing a section of highway or system of highways during a prescribed time period (traffic volume), the portion of such vehicles that may be of a particular type (vehicle classification), the weights of such vehicles including the weight of each axle and associated distances between axles on a vehicle (vehicle weight), or the average number of persons being transported in a vehicle (vehicle occupancy).

Traffic monitoring system means a systematic process for the collection, analysis, summary, and retention of highway and transit related person and vehicular traffic data.

Transit traffic data means person and vehicular data for public transportation on public highways and streets and the number of vehicles and ridership for dedicated transit rights-of-way (e.g., rail and busways), at the maximum load points for the peak period in the peak direction and for the daily time period.


§500.203   TMS general requirements.

(a) Each State shall develop, establish, and implement, on a continuing basis, a TMS to be used for obtaining highway traffic data when:

(1) The data are supplied to the U.S. Department of Transportation (U.S. DOT);

(2) The data are used in support of transportation management systems;

(3) The data are used in support of studies or systems which are the responsibility of the U.S. DOT;

(4) The collection of the data is supported by the use of Federal funds provided from programs of the U.S. DOT;

(5) The data are used in the apportionment or allocation of Federal funds by the U.S. DOT;

(6) The data are used in the design or construction of an FHWA funded project; or

(7) The data are required as part of a federally mandated program of the U.S. DOT.

(b) The TMS for highway traffic data should be based on the concepts described in the American Association of State Highway and Transportation Officials (AASHTO) "AASHTO Guidelines for Traffic Data Programs" 4 and the FHWA "Traffic Monitoring Guide (TMG)," 5 and shall be consistent with the FHWA "Highway Performance Monitoring System Field Manual." 6

4AASHTO Guidelines for Traffic Data Programs, 1992, ISBN 1-56051-054-4, can be purchased from the American Association of State Highway and Transportation Officials, 444 N. Capitol Street, NW., Suite 249, Washington, D.C. 20001. Available for inspection as prescribed in 49 CFR part 7, appendix D.

5Traffic Monitoring Guide, DOT/FHWA, publication No. FHWA-PL-95-031, February 1995. Available for inspection and copying as prescribed in 49 CFR part 7, appendix D.

6Highway Performance Monitoring System (HPMS) Field Manual for the Continuing Analytical and Statistical Data Base, DOT/FHWA, August 30, 1993 (FHWA Order M5600.1B). Available for inspection and copying as prescribed in 49 CFR part 7, appendix D.

(c) The TMS shall cover all public roads except those functionally classified as local or rural minor collector or those that are federally owned. Coverage of federally owned public roads shall be determined cooperatively by the State, the FHWA, and the agencies that own the roads.

(d) The State's TMS shall apply to the activities of local governments and other public or private non-State government entities collecting highway traffic data within the State if the collected data are to be used for any of the purposes enumerated in §500.203(a) of this subpart.

(e) Procedures other than those referenced in this subpart may be used if the alternative procedures are documented by the State to furnish the precision levels as defined for the various purposes enumerated in §500.203(a) of this subpart and are found acceptable by the FHWA.

(f) Nothing in this subpart shall prohibit the collection of additional highway traffic data if such data are needed in the administration or management of a highway activity or are needed in the design of a highway project.

(g) Transit traffic data shall be collected in cooperation with MPOs and transit operators.

(h) The TMS for highways and public transportation facilities and equipment shall be fully operational and in use by October 1, 1997.


§500.204   TMS components for highway traffic data.

(a) General. Each State's TMS, including those using alternative procedures, shall address the components in paragraphs (b) through (h) of this section.

(b) Precision of reported data. Traffic data supplied for the purposes identified in §500.203(a) of this subpart shall be to the statistical precision applicable at the time of the data's collection as specified by the data users at various levels of government. A State's TMS shall meet the statistical precisions established by FHWA for the HPMS.

(c) Continuous counter operations. Within each State, there shall be sufficient continuous counters of traffic volumes, vehicle classification, and vehicle weight to provide estimates of changes in highway travel patterns and to provide for the development of day-of-week, seasonal, axle correction, growth factors, or other comparable factors approved by the FHWA that support the development of traffic estimates to meet the statistical precision requirements of the data uses identified in §500.203(a) of this subpart. As appropriate, sufficient continuous counts of vehicle classification and vehicle weight should be available to address traffic data program needs.

(d) Short term traffic monitoring. (1) Count data for traffic volumes collected in the field shall be adjusted to reflect annual average conditions. The estimation of annual average daily traffic will be through the appropriate application of only the following: Seasonal factors, day-of-week factors, and, when necessary, axle correction and growth factors or other comparable factors approved by the FHWA. Count data that have not been adjusted to represent annual average conditions will be noted as being unadjusted when they are reported. The duration and frequency of such monitoring shall comply to the data needs identified in §500.203(a) of this subpart.

(2) Vehicle classification activities on the National Highway System (NHS), shall be sufficient to assure that, on a cycle of no greater than three years, every major system segment (i.e., segments between interchanges or intersections of principal arterials of the NHS with other principal arterials of the NHS) will be monitored to provide information on the numbers of single-trailer combination trucks, multiple-trailer combination trucks, two-axle four-tire vehicles, buses and the total number of vehicles operating on an average day. If it is determined that two or more continuous major system segments have both similar traffic volumes and distributions of the vehicle types identified above, a single monitoring session will be sufficient to monitor these segments.

(e) Vehicle occupancy monitoring. As deemed appropriate to support the data uses identified in §500.203(a) of this subpart, data will be collected on the average number of persons per automobile, light two-axle truck, and bus. The duration, geographic extent, and level of detail shall be consistent with the intended use of the data, as cooperatively agreed to by the organizations that will use the data and the organizations that will collect the data. Such vehicle occupancy data shall be reviewed at least every three years and updated as necessary. Acceptable data collection methods include roadside monitoring, traveler surveys, the use of administrative records (e.g., accident reports or reports developed in support of public transportation programs), or any other method mutually acceptable to the responsible organizations and the FHWA.

(f) Field operations. (1) Each State's TMS for highway traffic data shall include the testing of equipment used in the collection of the data. This testing shall be based on documented procedures developed by the State. This documentation will describe the test procedure as well as the frequency of testing. Standards of the American Society for Testing and Materials or guidance from the AASHTO may be used. Only equipment passing the test procedures will be used for the collection of data for the purposes identified in §500.203(a) of this subpart.

(2) Documentation of field operations shall include the number of counts, the period of monitoring, the cycle of monitoring, and the spatial and temporal distribution of count sites. Copies of the State's documentation shall be provided to the FHWA Division Administrator when it is initially developed and after each revision.

(g) Source data retention. For estimates of traffic or travel, the value or values collected during a monitoring session, as well as information on the date(s) and hour(s) of monitoring, will remain available until the traffic or travel estimates based on the count session are updated. Data shall be available in formats that conform to those in the version of the TMG current at the time of data collection or as then amended by the FHWA.

(h) Office factoring procedures. (1) Factors to adjust data from short term monitoring sessions to estimates of average daily conditions shall be used to adjust for month, day of week, axle correction, and growth or other comparable factors approved by the FHWA. These factors will be reviewed annually and updated at least every three years.

(2) The procedures used by a State to edit and adjust highway traffic data collected from short term counts at field locations to estimates of average traffic volume shall be documented. The documentation shall include the factors discussed in paragraph (d)(1) of this section. The documentation shall remain available as long as the traffic or travel estimates discussed in paragraph (g) of this section remain current. Copies of the State's documentation shall be provided to the FHWA Division Administrator when it is initially developed and after each revision.




PART 511 [RESERVED]


SUBCHAPTER G -- ENGINEERING AND TRAFFIC OPERATIONS



PART 620 -- ENGINEERING



Subpart A -- Highway Improvements in the Vicinity of Airports


   Sec.
620.101   Purpose.
620.102   Applicability.
620.103   Policy.
620.104   Standards.

Subpart B -- Relinquishment of Highway Facilities

620.201   Purpose.
620.202   Applicability.
620.203   Procedures.

Authority: 23 U.S.C. 315 and 318; 49 CFR 1.48, 23 CFR 1.32.

Source: 39 FR 33311, Sept. 17, 1974, unless otherwise noted.

Subpart A -- Highway Improvements in the Vicinity of Airports


Source: 39 FR 35145, Sept. 30, 1974, unless otherwise noted.


§620.101   Purpose.

The purpose of this section is to implement title 23 U.S.C., section 318 which requires coordination of airport and highway developments to insure (a) that airway-highway clearances are adequate for the safe movement of air and highway traffic, and (b) that the expenditure of public funds for airport and highway improvements is in the public interest.


§620.102   Applicability.

The requirements of this section apply to all projects on which Federal-aid highway funds are to be expended and to both civil and military airports.


§620.103   Policy.

(a) Federal-aid highway funds shall not participate in the costs of reconstruction or relocation of any highway to which this section applies unless the Federal Highway Administration (FHWA) and State officials, in cooperation with the Federal Aviation Administration (FAA) or appropriate military authority, or in the case of privately owned airports, the owner of that airport, determine that the location or extension of the airport in question and the consequent relocation or reconstruction of the highway is in the public interest.

(b) In addition to complying with 23 U.S.C. 318 and insuring the prudent use of public funds, it is the policy of FHWA to provide a high degree of safety in the location, design, construction and operation of highways and airports.

(c) Federal-aid funds shall not participate in projects where substandard clearances are created or will continue to exist.


§620.104   Standards.

A finding of public interest by FHWA will be based on compliance with airway-highway clearances which conform to FAA standards for aeronautical safety.

Subpart B -- Relinquishment of Highway Facilities


Source: 39 FR 33311, Sept. 17, 1974, unless otherwise noted.


§620.201   Purpose.

To prescribe Federal Highway Administration (FHWA) procedures relating to relinquishment of highway facilities.


§620.202   Applicability.

The provisions of this subpart apply to highway facilities where Federal-aid funds have participated in either right-of-way or physical construction costs of a project. The provisions of this subpart apply only to relinquishment of facilities for continued highway purposes. Other real property disposals and modifications or disposal of access rights are governed by the requirements of 23 CFR part 710.

[64 FR 71289, Dec. 21, 1999]



§620.203   Procedures.

(a) After final acceptance of a project on the Federal-aid primary, urban, or secondary system or after the date that the plans, specifications and estimates (PS&E) for the physical construction on the right-of-way for a Federal-aid Interstate project have been approved by the FHWA, relinquishment of the right-of-way or any change made in control of access shall be in accordance with the provisions of this section. For the purposes of this section, final acceptance for a project involving physical construction is the date of the acceptance of the physical construction by the FHWA and for right-of-way projects, the date the division engineer determines to be the date of the completion of the acquisition of the right-of-way shown on the final plans.

(b) For the purposes of this section, relinquishment is defined as the conveyance of a portion of a highway right-of-way or facility by a State highway agency (SHA) to another Government agency for highway use.

(c) The following facilities may be relinquished in accordance with paragraph 203(f):

(1) Sections of a State highway which have been superseded by construction on new location and removed from the Federal-aid system and the replaced section thereof is approved by the FHWA as the new location of the Federal-aid route. Federal-aid funds may not participate in rehabilitation work performed for the purpose of placing the superseded section of the highway in a condition acceptable to the local authority. The relinquishment of any Interstate mileage shall be submitted to the Federal Highway Administrator as a special case for prior approval.

(2) Sections of reconstructed local facilities that are located outside the control of access lines, such as turn-arounds of severed local roads or streets adjacent to the Federal-aid project's right-of-way, and local roads and streets crossing over or under said project that have been adjusted in grade and/or alignment, including new right-of-way required for adjustments. Eligibility for Federal-aid participation in the costs of the foregoing adjustments is as determined at the time of PS&E approval under policies of the FHWA.

(3) Frontage roads or portions thereof that are constructed generally parallel to and outside the control of access lines of a Federal-aid project for the purpose of permitting access to private properties rather than to serve as extensions of ramps to connect said Federal-aid project with the nearest crossroad or street.

(d) The following facilities may be relinquished only with the approval of the Federal Highway Administrator in accordance with paragraph 203(g).

(1) Frontage roads or portions thereof located outside the access control lines of a Federal-aid project that are constructed to service (in lieu of or in addition to the purposes outlined under paragraph (c)(3) of this section) as connections between ramps to or from the Federal-aid project and existing public roads or streets.

(2) Ramps constructed to serve as connections for interchange of traffic between the Federal-aid project and local roads or streets.

(e) Where a frontage road is not on an approved Federal-aid system title to the right-of-way may be acquired initially in the name of the political subdivision which is to assume control thus eliminating the necessity of a formal transfer later. Such procedure would be subject to prior FHWA approval and would be limited to those facilities which meet the criteria set forth in paragraphs (c) (2) and (3) of this section.

(f) Upon presentation by a State that it intends to relinquish facilities such as described in paragraph (c) (1), (2) or (3) of this section to local authorities, the division engineer of the FHWA shall have appropriate field and office examination made thereof to assure that such relinquishments are in accordance with the provisions of the cited paragraphs. Relinquishments of the types described in paragraph (c) (1), (2) or (3) of this section may be made on an individual basis or on a project or route basis subject to the following conditions and understandings:

(1) Immediately following action by the State in approving a relinquishment, it shall furnish to the Division Administrator for record purposes a copy of a suitable map or maps identified by the Federal-aid project number, with the facilities to be relinquished and the date of such relinquishment action clearly delineated thereon.

(2) If it is found at any time after relinquishment that a relinquished facility is in fact required for the safe and proper operation of the Federal-aid highway, the State shall take immediate action to restore such facility to its jurisdiction without cost to Federal-aid highway funds.

(3) If it is found at any time that a relinquished frontage road or portion thereof or any part of the right-of-way therefor has been abandoned by local governmental authority and a showing cannot be made that such abandoned facility is no longer required as a public road, it is to be understood that the Federal Highway Administrator may cause to be withheld from Federal-aid highway funds due to the State an amount equal to the Federal-aid participation in the abandoned facility.

(4) In no case shall any relinquishment include any portion of the right-of-way within the access control lines as shown on the plans for a Federal-aid project approved by the FHWA, without the prior approval of the Federal Highway Administrator.

(5) There cannot be additional Federal-aid participation in future construction or reconstruction on any relinquished "off the Federal-aid system" facility unless the underlying reason for such future work is caused by future improvement of the associated Federal-aid highway.

(g) In the event that a State desires to apply for approval by the Federal Highway Administrator for the relinquishment of a facility such as described in paragraph (d) (1) and (2) of this section, the facts pertinent to such proposal are to be presented to the division engineer of the FHWA. The division engineer shall have appropriate review made of such presentation and forward the material presented by the State together with his findings thereon through the Regional Federal Highway Administrator for consideration by the Federal Highway Administrator and determination of action to be taken.

(h) No change may be made in control of access, without the joint determination and approval of the SHA and FHWA. This would not prevent the relinquishment of title, without prior approval of the FHWA, of a segment of the right-of-way provided there is an abandonment of a section of highway inclusive of such segment.

(i) Relinquishments must be justified by the State's finding concurred in by the FHWA, that:

(1) The subject land will not be needed for Federal-aid highway purposes in the foreseeable future;

(2) That the right-of-way being retained is adequate under present day standards for the facility involved;

(3) That the release will not adversely affect the Federal-aid highway facility or the traffic thereon;

(4) That the lands to be relinquished are not suitable for retention in order to restore, preserve, or improve the scenic beauty adjacent to the highway consonant with the intent of 23 U.S.C. 319 and Pub. L. 89-285, Title III, sections 302-305 (Highway Beautification Act of 1965).

(j) If a relinquishment is to a Federal, State, or local government agency for highway purposes, there need not be a charge to the said agency, nor in such event any credit to Federal funds. If for any reason there is a charge, the STD may retain the Federal share of the proceeds if used for projects eligible under title 23 of the United States Code.

[39 FR 33311, Sept. 17, 1974, as amended at 64 FR 71289, Dec. 21, 1999]






PART 625 -- DESIGN STANDARDS FOR HIGHWAYS


Sec.
625.1   Purpose.
625.2   Policy.
625.3   Application.
625.4   Standards, policies, and standard specifications.

Authority: 23 U.S.C. 109, 315, and 402; Sec. 1073 of Pub. L. 102-240, 105 Stat. 1914, 2012; 49 CFR 1.48(b) and (n).

Source: 62 FR 15397, Apr. 1, 1997, unless otherwise noted.


§625.1   Purpose.

To designate those standards, policies, and standard specifications that are acceptable to the Federal Highway Administration (FHWA) for application in the geometric and structural design of highways.


§625.2   Policy.

(a) Plans and specifications for proposed National Highway System (NHS) projects shall provide for a facility that will --

(1) Adequately serve the existing and planned future traffic of the highway in a manner that is conducive to safety, durability, and economy of maintenance; and

(2) Be designed and constructed in accordance with criteria best suited to accomplish the objectives described in paragraph (a)(1) of this section and to conform to the particular needs of each locality.

(b) Resurfacing, restoration, and rehabilitation (RRR) projects, other than those on the Interstate system and other freeways, shall be constructed in accordance with standards which preserve and extend the service life of highways and enhance highway safety. Resurfacing, restoration, and rehabilitation work includes placement of additional surface material and/or other work necessary to return an existing roadway, including shoulders, bridges, the roadside, and appurtenances to a condition of structural or functional adequacy.

(c) An important goal of the FHWA is to provide the highest practical and feasible level of safety for people and property associated with the Nation's highway transportation systems and to reduce highway hazards and the resulting number and severity of accidents on all the Nation's highways.


§625.3   Application.

(a) Applicable Standards. (1) Design and construction standards for new construction, reconstruction, resurfacing (except for maintenance resurfacing), restoration, or rehabilitation of a highway on the NHS (other than a highway also on the Interstate System or other freeway) shall be those approved by the Secretary in cooperation with the State highway departments. These standards may take into account, in addition to the criteria described in §625.2(a), the following:

(i) The constructed and natural environment of the area;

(ii) The environmental, scenic, aesthetic, historic, community, and preservation impacts of the activity; and

(iii) Access for other modes of transportation.

(2) Federal-aid projects not on the NHS are to be designed, constructed, operated, and maintained in accordance with State laws, regulations, directives, safety standards, design standards, and construction standards.

(b) The standards, policies, and standard specifications cited in §625.4 of this part contain specific criteria and controls for the design of NHS projects. Deviations from specific minimum values therein are to be handled in accordance with procedures in paragraph (f) of this section. If there is a conflict between criteria in the documents enumerated in §625.4 of this part, the latest listed standard, policy, or standard specification will govern.

(c) Application of FHWA regulations, although cited in §625.4 of this part as standards, policies, and standard specifications, shall be as set forth therein.

(d) This regulation establishes Federal standards for work on the NHS regardless of funding source.

(e) The Division Administrator shall determine the applicability of the roadway geometric design standards to traffic engineering, safety, and preventive maintenance projects which include very minor or no roadway work. Formal findings of applicability are expected only as needed to resolve controversies.

(f) Exceptions. (1) Approval within the delegated authority provided by FHWA Order M1100.1A may be given on a project basis to designs which do not conform to the minimum criteria as set forth in the standards, policies, and standard specifications for:

(i) Experimental features on projects; and

(ii) Projects where conditions warrant that exceptions be made.

(2) The determination to approve a project design that does not conform to the minimum criteria is to be made only after due consideration is given to all project conditions such as maximum service and safety benefits for the dollar invested, compatibility with adjacent sections of roadway and the probable time before reconstruction of the section due to increased traffic demands or changed conditions.


§625.4   Standards, policies, and standard specifications.

The documents listed in this section are incorporated by reference with the approval of the Director of the Federal Register in accordance with 5 U.S.C. 552(a) and 1 CFR part 51 and are on file at the Office of the Federal Register in Washington, DC. They are available as noted in paragraph (d) of this section. The other CFR references listed in this section are included for cross-reference purposes only.

(a) Roadway and appurtenances. (1) A Policy on Geometric Design of Highways and Streets, AASHTO 1994. [See §625.4(d)(1)]

(2) A Policy on Design Standards -- Interstate System, AASHTO 1991. [See §625.4(d)(1)]

(3) The geometric design standards for resurfacing, restoration, and rehabilitation (RRR) projects on NHS highways other than freeways shall be the procedures and the design or design criteria established for individual projects, groups of projects, or all nonfreeway RRR projects in a State, and as approved by the FHWA. The other geometric design standards in this section do not apply to RRR projects on NHS highways other than freeways, except as adopted on an individual State basis. The RRR design standards shall reflect the consideration of the traffic, safety, economic, physical, community, and environmental needs of the projects.

(4) Erosion and Sediment Control on Highway Construction Projects, refer to 23 CFR part 650, subpart B.

(5) Location and Hydraulic Design of Encroachments on Flood Plains, refer to 23 CFR part 650, subpart A.

(6) Procedures for Abatement of Highway Traffic Noise and Construction Noise, refer to 23 CFR part 772.

(7) Accommodation of Utilities, refer to 23 CFR part 645, subpart B.

(8) Pavement Design, refer to 23 CFR part 626.

(b) Bridges and structures. (1) Standard Specifications for Highway Bridges, Fifteenth Edition, AASHTO 1992. [See §625.4(d)(1)]

(2) Interim Specifications -- Bridges, AASHTO 1993. [See §625.4(d)(1)]

(3) Interim Specifications -- Bridges, AASHTO 1994. [See §625.4(d)(1)]

(4) Interim Specifications -- Bridges, AASHTO 1995. [See §625.4(d)(1)]

(5) AASHTO LRFD Bridge Design Specifications, First Edition, AASHTO 1994 (U.S. Units). [See §625.4(d)(1)]

(6) AASHTO LRFD Bridge Design Specifications, First Edition, AASHTO 1994 (SI Units). [See §625.4(d)(1)]

(7) Standard Specifications for Movable Highway Bridges, AASHTO 1988. [See §625.4(d)(1)]

(8) Bridge Welding Code, ANSI/AASHTO/AWS D1.5-95, AASHTO. [See §625.4(d) (1) and (2)]

(9) Structural Welding Code -- Reinforcing Steel, ANSI/AWS D1.4-92, 1992. [See §625.4(d)(2)]

(10) Standard Specifications for Structural Supports for Highway Signs, Luminaires and Traffic Signals, AASHTO 1994. [See §625.4(d)(1)]

(11) Navigational Clearances for Bridges, refer to 23 CFR part 650, subpart H.

(c) Materials. (1) General Materials Requirements, refer to 23 CFR part 635, subpart D.

(2) Standard Specifications for Transportation Materials and Methods of Sampling and Testing, parts I and II, AASHTO 1995. [See §625.4(d)(1)]

(3) Sampling and Testing of Materials and Construction, refer to 23 CFR part 637, subpart B.

(d) Availability of documents incorporated by reference. The documents listed in §625.4 are incorporated by reference and are on file and available for inspection at the Office of the Federal Register, 800 North Capitol Street, NW., Suite 700, Washington, DC. These documents may also be reviewed at the Department of Transportation Library, 400 Seventh Street, SW., Washington, DC, in Room 2200. These documents are also available for inspection and copying as provided in 49 CFR part 7, appendix D. Copies of these documents may be obtained from the following organizations:

(1) American Association of State Highway and Transportation Officials (AASHTO), Suite 249, 444 North Capitol Street, NW., Washington, DC 20001.

(2) American Welding Society (AWS), 2501 Northwest Seventh Street, Miami, FL 33125.




PART 626 -- PAVEMENT POLICY


Sec.
626.1   Purpose.
626.2   Definitions.
626.3   Policy.

Authority: 23 U.S.C. 101(e), 109, and 315; 49 CFR 1.48(b)

Source: 61 FR 67174, Dec. 19, 1996, unless otherwise noted.


§626.1   Purpose.

To set forth pavement design policy for Federal-aid highway projects.


§626.2   Definitions.

Unless otherwise specified in this part, the definitions in 23 U.S.C. 101(a) are applicable to this part. As used in this part:

Pavement design means a project level activity where detailed engineering and economic considerations are given to alternative combinations of subbase, base, and surface materials which will provide adequate load carrying capacity. Factors which are considered include: Materials, traffic, climate, maintenance, drainage, and life-cycle costs.


§626.3   Policy.

Pavement shall be designed to accommodate current and predicted traffic needs in a safe, durable, and cost effective manner.




PART 627 -- VALUE ENGINEERING


Sec.
627.1   Purpose and applicability.
627.3   Definitions.
627.5   General principles and procedures.

Authority: 23 U.S.C. 106(d), 106(f), 302, 307, and 315; 49 CFR 18.

Source: 62 FR 6868, Feb. 14, 1997, unless otherwise noted.


§627.1   Purpose and applicability.

(a) This regulation will establish a program to improve project quality, reduce project costs, foster innovation, eliminate unnecessary and costly design elements, and ensure efficient investments by requiring the application of value engineering (VE) to all Federal-aid highway projects on the National Highway System (NHS) with an estimated cost of $25 million or more.

(b) In accordance with the Federal-State relationship established under the Federal-aid highway program, State highway agencies (SHA) shall assure that a VE analysis has been performed on all applicable projects and that all resulting, approved recommendations are incorporated into the plans, specifications and estimate.


§627.3   Definitions.

Project. A portion of a highway that a State proposes to construct, reconstruct, or improve as described in the preliminary design report or applicable environmental document. A project may consist of several contracts or phases over several years.

Value engineering. The systematic application of recognized techniques by a multi-disciplined team to identify the function of a product or service, establish a worth for that function, generate alternatives through the use of creative thinking, and provide the needed functions to accomplish the original purpose of the project, reliably, and at the lowest life-cycle cost without sacrificing safety, necessary quality, and environmental attributes of the project.


§627.5   General principles and procedures.

(a) State VE programs. State highway agencies must establish programs to assure that VE studies are performed on all Federal-aid highway projects on the NHS with an estimated cost of $25 million or more. Program procedures should provide for the identification of candidate projects for VE studies early in the development of the State's multi-year Statewide Transportation Improvement Program.

(1) Project selection. The program may, at the State's discretion, establish specific criteria and guidelines for selecting other highway projects for VE studies.

(2) Studies. Value engineering studies shall follow the widely recognized systematic problem-solving analysis process that is used throughout private industry and governmental agencies. Studies must be performed using multi-disciplined teams of individuals not personally involved in the design of the project. Study teams should consist of a team leader and individuals from different speciality areas, such as design, construction, environment, planning, maintenance, right-of-way, and other areas depending upon the type of project being reviewed. Individuals from the public and other agencies may also be included on the team when their inclusion is found to be in the public interest.

(i) Each team leader should be trained and knowledgeable in VE techniques and be able to serve as the coordinator and facilitator of the team.

(ii) Studies should be employed as early as possible in the project development or design process so that accepted VE recommendations can be implemented without delaying the progress of the project.

(iii) Studies should conclude with a formal report outlining the study team's recommendations for improving the project and reducing its overall cost.

(3) Recommendations. The program should include procedures to approve or reject recommendations and ensure the prompt review of VE recommendations by staff offices whose speciality areas are implicated in proposed changes and by offices responsible for implementing accepted recommendations. Reviews by these offices should be performed promptly to minimize delays to the project.

(4) Incentives. The program may include a VE or cost reduction incentive clause in an SHA's standard specifications or project special provisions that allows construction contractors to submit change proposals and share the resulting cost savings with the SHA.

(5) Monitoring. The program should include procedures for monitoring the implementation of VE study team recommendations and VE change proposal recommendations submitted by construction contractors.

(b) State VE coordinators. Individuals knowledgeable in VE shall be assigned responsibilities to coordinate and monitor the SHA's program and be actively involved in all phases of the program.

(c) Use of consultants. Consultants or firms with experience in VE may be retained by SHAs to conduct the studies of Federal-aid highway projects or elements of Federal-aid highway projects required under §627.1(a) of this part. Consultants or firms should not be retained to conduct studies of their own designs unless they maintain separate and distinct organizational separation of their VE and design sections.

(d) Funding eligibility. The cost of performing VE studies is project related and is, therefore, eligible for reimbursement with Federal-aid highway funds at the appropriate pro-rata share for the project studied.




PART 630 -- PRECONSTRUCTION PROCEDURES



Subpart A -- Project Authorization and Agreements


   Sec.
630.102   Purpose.
630.104   Applicability.
630.106   Authorization to proceed.
630.108   Preparation of agreement.
630.110   Modification of original agreement.
630.112   Agreement provisions.

Subpart B -- Plans, Specifications, and Estimates

630.201   Purpose.
630.203   Applicability.
630.205   Preparation, submission, and approval.

Subpart C      [Reserved]


Subpart D -- Geodetic Markers

630.401   Purpose.
630.402   Policy.
630.403   Initiation of projects.
630.404   Standards.

Subparts E-F [Reserved]


Subpart G -- Advance Construction of Federal-Aid Projects

630.701   Purpose.
630.703   Eligibility.
630.705   Procedures.
630.707   Limitation.
630.709   Conversion to a regular Federal-aid project.
630.711   Payment of bond interest.

Subpart H -- Bridges on Federal Dams

630.801   Purpose.
630.802   Applicability.
630.803   Procedures.

Subpart I [Reserved]


Subpart J -- Traffic Safety in Highway and Street Work Zones

630.1002   Purpose.
630.1004   Background.
630.1006   Policy.
630.1008   Implementation.
630.1010   Contents of the agency procedures.

Authority: 23 U.S.C. 106, 109, 115, 315, 320, and 402(a); 23 CFR 1.32; and 49 CFR 1.48(b).

Subpart A -- Project Authorization and Agreements


Source: 66 FR 23847, May 10, 2001, unless otherwise noted.


§630.102   Purpose.

The purpose of this subpart is to prescribe policies for authorizing Federal-aid projects through execution of the project agreement required by 23 U.S.C. 106(a)(2).


§630.104   Applicability.

(a) This subpart is applicable to all Federal-aid projects unless specifically exempted.

(b) Other projects which involve special procedures are to be approved, or authorized as set out in the implementing instructions or regulations for those projects.


§630.106   Authorization to proceed.

(a)(1) The State transportation department (STD) must obtain an authorization to proceed from the FHWA before beginning work on any Federal-aid project. The STD may request an authorization to proceed in writing or by electronic mail for a project or a group of projects.

(2) The FHWA will issue the authorization to proceed either through or after the execution of a formal project agreement with the State. The agreement can be executed only after applicable prerequisite requirements of Federal laws and implementing regulations and directives are satisfied. Except as provided in paragraphs (c)(1) through (c)(4) of this section, the FHWA will obligate Federal funds in the project or group of projects upon execution of the project agreement.

(b) Federal funds shall not participate in costs incurred prior to the date of a project agreement except as provided by 23 CFR 1.9(b).

(c) The execution of the project agreement shall be deemed a contractual obligation of the Federal government under 23 U.S.C. 106 and shall require that appropriate funds be available at the time of authorization for the agreed Federal share, either pro rata or lump sum, of the cost of eligible work to be incurred by the State except as follows:

(1) Advance construction projects authorized under 23 U.S.C. 115.

(2) Projects for preliminary studies for the portion of the preliminary engineering and right-of-way (ROW) phase(s) through the selection of a location.

(3) Projects for ROW acquisition in hardship and protective buying situations through the selection of a particular location. This includes ROW acquisition within a potential highway corridor under consideration where necessary to preserve the corridor for future highway purposes. Authorization of work under this paragraph shall be in accord with the provisions of 23 CFR part 710.

(4) In special cases where the Federal Highway Administrator determines it to be in the best interest of the Federal-aid highway program.

(d) For projects authorized to proceed under paragraphs (c)(1) through (c)(4) of this section, the executed project agreement shall contain the following statement: "Authorization to proceed is not a commitment or obligation to provide Federal funds for that portion of the undertaking not fully funded herein."

(e) For projects authorized under paragraphs (c)(2) and (c)(3) of this section, subsequent authorizations beyond the location stage shall not be given until appropriate available funds have been obligated to cover eligible costs of the work covered by the previous authorization.

(f)(1) The Federal-aid share of eligible project costs shall be established at the time the project agreement is executed in one of the following manners:

(i) Pro rata, with the agreement stating the Federal share as a specified percentage; or

(ii) Lump sum, with the agreement stating that Federal funds are limited to a specified dollar amount not to exceed the legal pro rata.

(2) The pro-rata or lump sum share may be adjusted before or shortly after contract award to reflect any substantive change in the bids received as compared to the STD's estimated cost of the project at the time of FHWA authorization, provided that Federal funds are available.

(3) Federal participation is limited to the agreed Federal share of eligible costs actually incurred by the State, not to exceed the maximum permitted by enabling legislation.

(g) The State may contribute more than the normal non-Federal share of title 23, U.S.C. projects. In general, financing proposals that result in only minimal amounts of Federal funds in projects should be avoided unless they are based on sound project management decisions.

(h)(1) Donations of cash, land, material or services may be credited to the State's non-Federal share of the participating project work in accordance with title 23, U.S.C., and implementing regulations.

(2) Contributions may not exceed the total costs incurred by the State on the project. Cash contributions from all sources plus the Federal funds may not exceed the total cost of the project.


§630.108   Preparation of agreement.

(a) The STD shall prepare a project agreement for each Federal-aid project.

(b) The STD may develop the project agreement in a format acceptable to both the STD and the FHWA provided the following are included:

(1) A description of each project location including State and project termini;

(2) The Federal-aid project number;

(3) The work covered by the agreement;

(4) The total project cost and amount of Federal funds under agreement;

(5) The Federal-aid share of eligible project costs expressed as either a pro rata percentage or a lump sum as set forth in §630.106(f)(1);

(6) A statement that the State accepts and will comply with the agreement provisions set forth in §630.112;

(7) A statement that the State stipulates that its signature on the project agreement constitutes the making of the certifications set for in §630.112; and

(8) Signatures of officials from both the State and the FHWA, and the date executed.

(c) The project agreement should also document, by comment, instances where:

(1) The State is applying amounts of credits from special accounts (such as the 23 U.S.C. 120(j) toll credits, 23 U.S.C. 144(n) off-system bridge credits and 23 U.S.C. 323 land value credits) to cover all or a portion of the normal percent non-Federal share of the project;

(2) The project involves other arrangements affecting Federal funding or non-Federal matching provisions, including tapered match, donations, or use of other Federal agency funds, if known at the time the project agreement is executed; and

(3) The State is claiming finance related costs for bond and other debt instrument financing (such as payments to States under 23 U.S.C. 122).

(d) The STD may use an electronic version of the agreement as provided by the FHWA. (Approved by the Office of Management and Budget under control number 2125-0529)


§630.110   Modification of original agreement.

(a) When changes are needed to the original project agreement, a modification of agreement shall be prepared. Agreements should not be modified to replace one Federal fund category with another unless specifically authorized by statute.

(b) The STD may develop the modification of project agreement in a format acceptable to both the STD and the FHWA provided the following are included:

(1) The Federal-aid project number and State;

(2) A sequential number identifying the modification;

(3) A reference to the date of the original project agreement to be modified;

(4) The original total project cost and the original amount of Federal funds under agreement;

(5) The revised total project cost and the revised amount of Federal funds under agreement;

(6) The reason for the modifications; and,

(7) Signatures of officials from both the State and the FHWA and date executed.

(c) The STD may use an electronic version of the modification of project agreement as provided by the FHWA.


§630.112   Agreement provisions.

(a) The State, through its transportation department, accepts and agrees to comply with the applicable terms and conditions set forth in title 23, U.S.C., the regulations issued pursuant thereto, the policies and procedures promulgated by the FHWA relative to the designated project covered by the agreement, and all other applicable Federal laws and regulations.

(b) Federal funds obligated for the project must not exceed the amount agreed to on the project agreement, the balance of the estimated total cost being an obligation of the State. Such obligation of Federal funds extends only to project costs incurred by the State after the execution of a formal project agreement with the FHWA.

(c) The State must stipulate that as a condition to payment of the Federal funds obligated, it accepts and will comply with the following applicable provisions:

(1) Project for acquisition of rights-of-way. In the event that actual construction of a road on this right-of-way is not undertaken by the close of the twentieth fiscal year following the fiscal year in which the project is authorized, the STD will repay to the FHWA the sum or sums of Federal funds paid to the transportation department under the terms of the agreement. The State may request a time extension beyond the 20-year limit with no repayment of Federal funds, and the FHWA may approve this request if it is considered reasonable.

(2) Preliminary engineering project. In the event that right-of-way acquisition for, or actual construction of, the road for which this preliminary engineering is undertaken is not started by the close of the tenth fiscal year following the fiscal year in which the project is authorized, the STD will repay to the FHWA the sum or sums of Federal funds paid to the transportation department under the terms of the agreement. The State may request a time extension for any preliminary engineering project beyond the 10-year limit with no repayment of Federal funds, and the FHWA may approve this request if it is considered reasonable.

(3) Drug-free workplace certification. By signing the project agreement, the STD agrees to provide a drug-free workplace as required by 49 CFR part 29, subpart F. In signing the project agreement, the State is providing the certification required in appendix C to 49 CFR part 29, unless the State provides an annual certification.

(4) Suspension and debarment certification. By signing the project agreement, the STD agrees to fulfill the responsibility imposed by 49 CFR 29.510 regarding debarment, suspension, and other responsibility matters. In signing the project agreement, the State is providing the certification for its principals required in appendix A to 49 CFR part 29.

(5) Lobbying certification. By signing the project agreement, the STD agrees to abide by the lobbying restrictions set forth in 49 CFR part 20. In signing the project agreement, the State is providing the certification required in appendix A to 49 CFR part 20.

Subpart B -- Plans, Specifications, and Estimates


Source: 43 FR 58564, Dec. 15, 1978, unless otherwise noted.


§630.201   Purpose.

The purpose of this subpart is to prescribe Federal Highway Administration (FHWA) procedures relating to the preparation, submission, and approval of plans, specifications and estimates (PS&E), and supporting documents for Federal-aid projects.


§630.203   Applicability.

The provisions of this regulation apply to all highway construction projects financed in whole or in part with Federal-aid highway funds and to be undertaken by a State or political subdivision, except for projects carried out pursuant to 23 U.S.C. 117 relative to certification acceptance or a secondary road plan.


§630.205   Preparation, submission, and approval.

(a) The contents and number of copies of the PS&E assembly shall be determined by the FHWA.

(b) Plans and specifications shall describe the location and design features and the construction requirements in sufficient detail to facilitate the construction, the contract control and the estimation of construction costs of the project. The estimate shall reflect the anticipated cost of the project in sufficient detail to provide an initial prediction of the financial obligations to be incurred by the State and FHWA and to permit an effectice review and comparison of the bids received.

(c) PS&E assemblies for Federal-aid highway projects shall be submitted to the FHWA for approval.

(d) The State highway agency (SHA) shall be advised of approval of the PS&E by the FHWA.

(e) No project or part thereof for actual construction shall be advertised for contract nor work commenced by force account until the PS&E has been approved by the FHWA and the SHA has been so notified.

Subpart C      [Reserved]



               

Subpart D -- Geodetic Markers


Source: 39 FR 26414, July 19, 1974, unless otherwise noted.


§630.401   Purpose.

The purpose of this subpart is to prescribe procedures for conducting geodetic control surveys when participation with Federal-aid highway funds in the cost thereof is proposed and to encourage inter-agency cooperation in setting station markers, surveying to measure their position, and preserving the control so established.


§630.402   Policy.

(a) Geodetic surveys along Federal-aid highway routes may be programmed as Federal-aid highway projects.

(b) All geodetic survey work performed as a Federal-aid highway project will conform to National Ocean Survey (NOS) specifications. NOS will, as the representative of FHWA, be responsible for the inspection and verification of the work to ascertain that the specifications for the work have been met. Final project acceptance by FHWA will be predicated on a finding of acceptability by NOS.


§630.403   Initiation of projects.

All projects shall be coordinated by the FHWA Division Administrator, the State highway department and the National Ocean Survey.


§630.404   Standards.

(a) Highway purposes may best be served by the establishment of station markings for horizontal control along Federal-aid highway routes at spacings of three to eight kilometers (about 2 to 5 miles) and station markers for vertical control of spacings no closer than one kilometer. These requirements may be waived only with the approval of the Administrator.

(b) Projects should be of sufficient scope to permit efficient use of field parties. Projects should extend at least 30 kilometers. Projects may be coordinated with adjoining States to attain greater efficiency.

(c) Where geodetic station markers cannot be established inititally at points readily accessible from the Federal-aid route, or where unavoidable circumstances result in their being established within construction limits, supplemental projects may later be approved to set and survey markers at satisfactory permanent points, preferably within the right-of-way but at points where their use does not introduce traffic hazards.

Subparts E-F [Reserved]

Subpart G -- Advance Construction of Federal-Aid Projects


Source: 60 FR 36993, July 19, 1995, unless otherwise noted.


§630.701   Purpose.

The purpose of this subpart is to prescribe procedures for advancing the construction of Federal-aid highway projects without obligating Federal funds apportioned or allocated to the State.


§630.703   Eligibility.

(a) The State Highway Agency (SHA) may proceed with a highway substitute, congestion mitigation and air quality improvement program, surface transportation program, bridge replacement and rehabilitation, or planning and research project in accordance with this subpart, provided the SHA:

(1) Has obligated all funds apportioned or allocated to it under 23 U.S.C. 103(e)(4)(H), 104(b)(2), 104(b)(3), 104(f), 144, or 307, as the case may be for the proposed project, or

(2) Has used all obligation authority distributed to it, or

(3) Demonstrates that it will use all obligation authority distributed to it.

(b) The SHA may proceed with a National Highway System (NHS) or Interstate project in accordance with this subpart without regard to apportionment or obligation authority balances. Interstate projects include Interstate construction and Interstate maintenance.


§630.705   Procedures.

(a) An advance construction project shall meet the same requirements and be processed in the same manner as a regular Federal-aid project, except,

(1) The FHWA authorization does not constitute any commitment of Federal funds on the project, and

(2) The FHWA shall not reimburse the State until the project is converted under §630.709.

(b) Project numbers shall be identified by the letters "AC" preceding the regular project number prefix.

(c) If the SHA plans to claim bond interest costs under §630.711, it shall include in its request for authorization the estimated federally participating bond interest cost.

(d) The SHA shall submit a final voucher to the FHWA upon completion of the project even though the project has not been converted. If the SHA is claiming bond interest costs under §630.711, it shall certify on the final voucher that the bond proceeds were expended in the construction of the project and shall include a computation of the eligible interest costs.


§630.707   Limitation.

A request to approve an advance construction project is limited to a State's expected apportionment of authorized funds which are eligible to finance the project.


§630.709   Conversion to a regular Federal-aid project.

(a) The SHA may submit a written request to the FHWA that a project be converted to a regular Federal-aid project at any time provided that sufficient Federal-aid funds and obligation authority are available.

(b) Subsequent to FHWA approval the SHA may claim reimbursement for the Federal share of project costs incurred, provided the project agreement has been executed. If the SHA has previously submitted a final voucher, the FHWA will process the voucher for payment.


§630.711   Payment of bond interest.

(a) For Interstate projects authorized by the FHWA after January 6, 1983, and for Interstate 4R, Interstate maintenance, primary and NHS projects authorized by the FHWA after April 2, 1987, interest earned and payable on bonds issued by a State is an eligible cost of construction as follows:

(1) Participating interest cost is based on the actual expenditure of bond proceeds on the Federal-aid project. The interest on the bonds is applied to the amount of bond proceeds expended on the project from the date of expenditure.

(2) The amount of interest determined in paragraph (a)(1) of this section shall not exceed the estimated increase in the physical construction cost of the project which would have occurred had the project been authorized on the date of conversion. The estimated increase in the physical construction cost is determined by applying the increase, if any, in the national construction cost index in effect on the date of conversion over the index in effect on the date of the FHWA authorization, to the actual cost of physical construction.

(b) For Interstate projects under physical construction on January 1, 1983, and converted to a regular Federal-aid project after January 1, 1983, bond interest is eligible in accordance with paragraph (a)(1) of this section. The restriction in paragraph (a)(2) of this section does not apply.

Subpart H -- Bridges on Federal Dams


Source: 39 FR 36474, Oct. 10, 1974, unless otherwise noted.


§630.801   Purpose.

The purpose of this subpart is to prescribe procedures for the construction and financing, by an agency of the Federal Government, of public highway bridges over dams constructed and owned by or for the United States.


§630.802   Applicability.

A proposed bridge over a dam, together with the approach roads to connect the bridge with existing public highways, must be eligible for inclusion in the Federal-aid highway system, if not already a part thereof.


§630.803   Procedures.

A State's application to qualify a project under this subpart will include:

(a) A certification that the bridge is economically desirable and needed as a link in the Federal-aid highway system.

(b) A statement showing the source and availability of funds to be used in construction of the roadway approaches.

(c) A statement of any obligation on the part of the agency constructing the dam to provide such bridge or approach roads to satisfy a legal liability incurred independently of this subpart.

Subpart I [Reserved]

Subpart J -- Traffic Safety in Highway and Street Work Zones


Source: 43 FR 47140, Oct. 12, 1978, unless otherwise noted.


§630.1002   Purpose.

The purpose of this subpart is to provide guidance and establish procedures to assure that adequate consideration is given to motorists, pedestrians, and construction workers on all Federal-aid construction projects.


§630.1004   Background.

Part VI of the manual on uniform traffic control devices (MUTCD) 1sets forth basic priniciples and prescribes standards for the design, application, installation, and maintenance of the various types of traffic control devices for highway and street construction, maintenance operation, and utility work. The manual cannot address in depth the variety of situations that occur in providing traffic control in work zones. Although agencies responsible for traffic control and work area protection have attempted to develop some guidelines, a coordinated and comprehensive effort to develop greater uniformity is desirable. National reviews have shown that more attention is needed to insure that the MUTCD is properly implemented on all highway projects.

1The MUTCD is available from the Superintendent of Documents, U.S. Government Printing Office, Washington, D.C. 20402. It is incorporated by reference at 23 CFR 655, subpart F.

[43 FR 47140, Oct. 12, 1978, as amended at 51 FR 16834, May 7, 1986]



§630.1006   Policy.

It is the policy of the Federal Highway Administration that each highway agency shall develop and implement procedures consonant with the requirements of this regulation that will assure the safety of motorists, pedestrians, and construction workers on Federal-aid highway construction projects. The procedures shall be consistent with the provisions of the MUTCD. Highway agencies should be encouraged to implement these procedures for non-Federal-aid projects and maintenance operations as well.


§630.1008   Implementation.

The FHWA Division Administrator shall review and approve the highway agency's implementation of its procedures at appropriate intervals. The FHWA shall take appropriate action to assure that the highway agency's procedures are being followed and achieve the results intended. Major revisions in established procedures shall be submitted to the FHWA Division Administrator for information.


§630.1010   Contents of the agency procedures.

The agency's procedures shall include, but not necessarily be limited to the following:

(a) Traffic control plan (TCP). (1) A traffic control plan is a plan for handling traffic through a specific highway or street work zone or project. These plans may range in scope from a very detailed TCP designed solely for a specific project, to a reference to standard plans, a section of the MUTCD, or a standard highway agency manual. The degree of detail in the TCP will depend on the project complexity and traffic interference with construction activity.

(2) Traffic control plans shall be developed for all projects and be included in plans, specifications, and estimates (P.S. & E.'s) and shall be consistent with part VI of the MUTCD.

(3) The scope of the TCP should be determined during planning and design phases of a project.

(4) Provisions may be made to permit contractors to develop their own TCP's and use them if the highway agency and FHWA find that these plans are as good as or better than those provided in the P.S. & E.

(5)(i) Two-lane, two-way operation on one roadway of a normally divided highway (TLTWO) shall be used only after careful consideration of other available methods of traffic control. Where the TLTWO is used, the TCP shall include provisions for the separation of opposing traffic except:

(A) Where the TLTWO is located on an urban type street or arterial where operating speeds are low;

(B) Where drivers entering the TLTWO can see the transition back to normal one-way operation on each roadway; or

(C) Where FHWA approves nonuse of separation devices based on unusual circumstances.

(ii) Center line striping, raised pavement markers, and complementary signing, either alone or in combination, are not considered acceptable for separation purposes.

(b) Responsible person. The highway agency shall designate a qualified person at the project level who will have the primary responsibility and sufficient authority for assuring that the TCP and other safety aspects of the contract are effectively administered. While the project or resident engineer may have this responsibility, on large complex projects another person should be assigned at the project level to handle traffic control on a full-time basis.

(c) Pay items. The P.S. & E. should include unit pay items for providing, installing, moving, replacing, maintaining, and cleaning traffic control devices required by the TCP. Suitable force account procedures may be utilized for traffic control items. Lump-sum method of payment should be used only to cover very small projects, projects of short duration, contingency, and general items. Payment for traffic control items as incidental to other items of work should be discouraged.

(d) Training. All persons responsible for the development, design, implementation, and inspection of traffic control shall be adequately trained.

(e) Process review and evaluation. (1) A review team consisting of appropriate highway agency personnel shall annually review randomly selected projects throughout its jurisdiction for the purpose of assessing the effectiveness of its procedures. The agency may elect to include an FHWA representative as a member of the team. The results of this review are to be forwarded to the FHWA Division Administrator for his review and approval of the highway agency's annual traffic safety effort.

(2) Construction zone accidents and accident data shall be analyzed and used to continually correct deficiencies which are found to exist on individual projects, and to improve the content of future traffic control plans.

[43 FR 47140, Oct. 12, 1978, as amended at 47 FR 21780, May 20, 1982]






PART 633 -- REQUIRED CONTRACT PROVISIONS



Subpart A -- Federal-Aid Construction Contracts (Other Than Appalachian Contracts)


   Sec.
633.101   Purpose.
633.102   Applicability.
633.103   Regulatory authority.
633.104   Availability.

Subpart B -- Federal-Aid Contracts (Appalachian Contracts)

633.201   Purpose.
633.202   Definitions.
633.203   Applicability of existing laws, regulations, and directives.
633.204   Fiscal allocation and obligations.
633.205   Prefinancing.
633.206   Project agreements.
633.207   Construction labor and materials.
633.208   Maintenance.
633.209   Notices to prospective Federal-aid construction contractors.
633.210   Termination of contract.
633.211   Implementation of the Clean Air Act and the Federal Water Pollution Control Act.
Appendix A to Subpart B -- Types of Contracts to Which the Civil Rights Act of 1964 Is Applicable
Appendix B to Subpart B -- Required Contract Provisions, Appalachian Development Highway System and Local Access Roads Construction Contracts
Appendix C to Subpart B -- Additional Required Contract Provisions, Appalachian Development Highway System and Local Access Roads Contracts Other Than Construction Contracts
Appendix D to Subpart B -- Federal-Aid Proposal Notices

Subpart C -- Direct Federal Construction Contracts

633.301   Purpose.
633.302   Applicability.
Appendix A to Subpart C -- Continuation of Standard Form 19-A Labor Standards Provisions (DOT-FHWA 3-74)

Subpart A -- Federal-Aid Construction Contracts (Other Than Appalachian Contracts)


Authority: 23 U.S.C. 114 and 315; 49 CFR 1.48.

Source: 52 FR 36920, Oct. 2, 1987, unless otherwise noted.


§633.101   Purpose.

To prescribe for Federal-aid highway proposals and construction contracts the method for inclusion of required contract provisions of existing regulations which cover employment, nonsegregated facilities, record of materials and supplies, subletting or assigning the contract, safety, false statements concerning highway projects, termination of a contract, and implementation of the Clean Air Act and the Federal Water Pollution Control Act, and other provisions as shall from time-to-time be required by law and regulation as conditions of Federal assistance.


§633.102   Applicability.

(a) The required contract provisions and the required proposal notices apply to all Federal-aid construction contracts other than Appalachian construction contracts.

(b) Form FHWA-1273, "Required Contract Provisions, Federal-aid Construction Contracts," contains required contract provisions and required proposal notices that are required by regulations promulgated by the FHWA or other Federal agencies. The required contract provisions of Form FHWA-1273 shall be physically incorporated in each Federal-aid highway construction contract other than Appalachian construction contracts (see §633.104 for availability of form).

(c) For contracts authorized under certification acceptance procedures, an alternate format for inclusion of required contract provisions may be used pursuant to 23 CFR part 640.

(d) The required contract provisions contained in Form FHWA-1273 shall apply to all work performed on the contract by the contractor's own organization and to all work performed on the contract by piecework, station work, or by subcontract.

(e) The contractor shall insert in each subcontract, except as excluded by law or regulation, the required contract provisions contained in Form FHWA-1273 and further require their inclusion in any lower tier subcontract that may in turn be made. The required contract provisions of Form FHWA-1273 shall not be incorporated by reference in any case. The prime contractor shall be responsible for compliance by any subcontractor or lower tier subcontractor with the requirements contained in the provisions of Form FHWA-1273.

(f) The State highway agency (SHA) shall include the notices concerning certification of nonsegregated facilities and implementation of the Clean Air Act and Federal Water Pollution Control Act, pursuant to 40 CFR part 15, in all bidding proposals for Federal-aid highway construction projects. As the notices are reproduced in Form FHWA-1273, the SHA may include Form FHWA-1273 in its entirety to meet this requirement.


§633.103   Regulatory authority.

All required contract provisions contained in Form FHWA-1273 are requirements of regulations promulgated by the FHWA or other Federal agencies.The authority for each provision will be cited in the text of Form FHWA-1273.


§633.104   Availability.

(a) Form FHWA-1273 will be maintained by the FHWA and as regulatory revisions occur, the form will be updated.

(b) Current copies of Form FHWA-1273, Required Contract Provisions, will be made available to the SHAs by the FHWA.

Subpart B -- Federal-Aid Contracts (Appalachian Contracts)


Authority: 40 U.S.C. App. 201, 402; 23 U.S.C. 315; 49 CFR 1.48(b)(35).

Source: 39 FR 35146, Sept. 30, 1974, unless otherwise noted.


§633.201   Purpose.

The purpose of the regulations in this subpart is to establish policies and outline procedures for administering projects and funds for the Appalachian Development Highway System and Appalachian local access roads.


§633.202   Definitions.

(a) The word Commission means the Appalachian Regional Commission (ARC) established by the Appalachian Regional Development Act of 1965, as amended (Act).

(b) The term division administrator" means the chief Federal Highway Administration (FHWA) official assigned to conduct FHWA business in a particular State.

[39 FR 35156, Sept. 30, 1974, as amended at 40 FR 49084, Oct. 21, 1975; 41 FR 8769, Mar. 1, 1976]



§633.203   Applicability of existing laws, regulations, and directives.

The provisions of title 23 U.S.C., that are applicable to the construction and maintenance of Federal-aid primary and secondary highways, and which the Secretary of Transportation determines are not inconsistent with the Act, shall apply, respectively, to the development highway system and the local access roads. In addition, the Regulations for the Administration of Federal-aid for Highways (title 23, Code of Federal Regulations) and directives implementing applicable provisions of title 23 U.S.C., where not inconsistent with the Act, shall be applicable to such projects.


§633.204   Fiscal allocation and obligations.

(a) Federal assistance to any project under the Act shall be as determined by the Commission, but in no event shall such Federal assistance exceed 70 per centum of the cost of such a project.

(b) The division administrator's authorization to proceed with the proposed work shall establish obligation of Federal funds with regard to a particular project.

[39 FR 35156, Sept. 30, 1974, as amended at 40 FR 49084, Oct. 21, 1975; 41 FR 8769, Mar. 1, 1976]



§633.205   Prefinancing.

(a) Under the provisions of subsection 201(h) of the Act, projects located on the Appalachian Development Highway System including preliminary engineering, right-of-way, and/or construction may be programed and advanced with interim State financing.

(b) Program approvals, plans, specifications, and estimates (PS&E) approval, authorizations to proceed, concurrence in award of contracts, and all other notifications to the State of advancement of a project shall include the statement, "There is no commitment or obligation on the part of the United States to provide funds for this highway improvement. However, this project is eligible for Federal reimbursement when sufficient funds are available from the amounts allocated by the Appalachian Regional Commission."


§633.206   Project agreements.

(a) Project agreements executed for projects under the Appalachian program shall contain the following paragraphs:

(1) "For projects constructed under section 201 of the Appalachian Regional Development Act of 1965, as amended, the State highway department agrees to comply with all applicable provisions of said Act, regulations issued thereunder, and policies and procedures promulgated by the Appalachian Regional Commission, and the Federal Highway Administration. Inasmuch as a primary objective of the Appalachian Regional Development Act of 1965 is to provide employment, the State highway department further agrees that in addition to the other applicable provisions of title 49, Code of Federal Regulations, part 21, §21.5(c)(1), and paragraphs (2)(iii) and (2)(v) of appendix C thereof, shall be applicable to all employment practices in connection with this project, and to the State's employment practices with respect to those employees connected with the Appalachian Highway Program."

(2) "For projects constructed on a section of an Appalachian development route not already on the Federal-aid Primary System, the State highway department agrees to add the section to the Federal-aid Primary System prior to, or upon completion of, construction accomplished with Appalachian funds."

(b) For prefinanced projects, the following additional provision shall be incorporated into the project agreement: "Project for Construction on the Appalachian Development Highway System in Advance of the Appropriation of Funds. This project, to be constructed pursuant to subsection 201(h) of the Appalachian Regional Development Act Amendments of 1967, will be constructed in accordance with all procedures and requirements and standards applicable to projects on the Appalachian Development Highway System financed with the aid of Appalachian funds. No obligation of Appalachian funds is created by this agreement, its purpose and intent being to provide that, upon application by the State highway department, and approval thereof by the Federal Highway Administration, any Appalachian development highway funds made available to the State by the Appalachian Regional Commission subsequent to the date of this agreement may be used to reimburse the State for the Federal share of the cost of work done on the project."


§633.207   Construction labor and materials.

(a) Construction and materials shall be in accordance with the State highway department standard construction specifications approved for use on Federal-aid primary projects and special provisions and supplemental specifications amendatory thereto approved for use on the specific projects.

(b) The provisions of 23 U.S.C. 324 and of title VI of the Civil Rights Act of 1964 (78 Stat. 252; 42 U.S.C. 2000d-2000d-4) and the implementing regulations in 49 CFR part 21, including the provisions of §21.5(c)(1), and paragraphs (2)(iii) and (2)(v) of appendix C thereof relative to employment practices, shall be applicable to all types of contracts listed in appendix A.

(c) The "Required Contract Provisions, Appalachian Development Highway System and Local Access Roads Construction Contracts," Form PR-1316 (appendix B), shall be included in all construction contracts awarded under the Act.

(d) The required contract provisions set forth in Form PR-1317 (appendix C) shall be included in all types of contracts described in appendix A, other than construction contracts.

(e) In the design and construction of highways and roads under the Act, the State may give special preference to the use of mineral resource materials native to the Appalachian region. The provisions of §635.409 of this chapter shall not apply to projects under the Act to the extent such provisions are inconsistent with sections 201(d) and (e) of the Act.

[39 FR 35146, Sept. 30, 1974, as amended at 40 FR 49084, Oct. 21, 1975; 41 FR 36204, Aug. 27, 1976]



§633.208   Maintenance.

Maintenance of all highway projects constructed under the Act, whether on the development system or local access roads, shall be the responsibility of the State. The State may arrange for maintenance of such roads or portions thereof, by agreement with a local governmental unit.


§633.209   Notices to prospective Federal-aid construction contractors.

The State highway department shall include the notices set forth in appendix D in all future bidding proposals for Appalachian Development System and Appalachian local access roads construction contracts.


§633.210   Termination of contract.

All contracts exceeding $2,500 shall contain suitable provisions for termination by the State, including the manner in which the termination will be effected and the basis for settlement. In addition, such contracts shall describe conditions under which the contract may be terminated for default as well as conditions where the contract may be terminated because of circumstances beyond the control of the contractor.


§633.211   Implementation of the Clean Air Act and the Federal Water Pollution Control Act.

Pursuant to regulations of the Environmental Protection Agency (40 CFR part 15) implementing requirements with respect to the Clean Air Act and the Federal Water Pollution Control Act are included in appendix B to this part.

[40 FR 49084, Oct. 21, 1975]




Appendix A to Subpart B of Part 633 -- Types of Contracts to Which the Civil Rights Act of 1964 Is Applicable

Section 324 of title 23 U.S.C., the Civil Rights Act of 1964, and the implementing regulations of the Department of Transportation (49 CFR part 21), including the provisions of paragraphs (2)(iii) and (2)(v) of appendix C thereof relative to employment practices, are applicable to the following types of contracts awarded by State highway departments, contractors, and first tier subcontractors, including those who supply materials and lease equipment:

1. Construction.

2. Planning.

3. Research.

4. Highway Safety.

5. Engineering.

6. Property Management.

7. Fee contracts and other commitments with persons for services incidental to the acquisition of right-of-way including, but not limited to:

a. Advertising contracts.

b. Agreements for economic studies.

c. Contracts for surveys and plats.

d. Contracts for abstracts of title certificates and title insurance.

e. Contracts for appraisal services and expert witness fees.

f. Contracts to negotiate for the acquisition of right-of-way.

g. Contracts for disposal of improvements and property management services.

h. Contracts for employment of fee attorneys for right-of-way procurement, or preparation and trial of condemnation cases.

i. Contracts for escrow and closing services.

[40 FR 49084, Oct. 21, 1975]




Appendix B to Subpart B of Part 633 -- Required Contract Provisions, Appalachian Development Highway System and Local Access Roads Construction Contracts

I. Application.
II. Employment Preference.
III. Equal Opportunity: Employment Practices.
IV. Equal Opportunity: Selection of Subcontractors, Procurement of
Materials, and Leasing of Equipment.
V. Nonsegregated Facilities.
VI. Payment of Predetermined Minimum Wages.
VII. Statements and Payrolls.
VIII. Record of Materials, Supplies and Labor.
IX. Subletting or Assigning the Contract.
X. Safety: Accident Prevention.
XI. False Statements Concerning Highway Projects.
XII. Implementation of Clean Air Act and Federal Water Pollution
Control Act.

I. Application.

1. These contract provisions shall apply to all work performed on the contract by the contractor with his own organization and with the assistance of workmen under his immediate superintendence and to all work performed on the contract by piecework, station work, or by subcontract.

2. Except as otherwise provided in sections II, III, and IV hereof, the contractor shall insert in each of his subcontracts all of the stipulations contained in these Required Contract Provisions and also a clause requiring his subcontractors to include these Required Contract Provisions in any lower tier subcontracts which they may enter into, together with a clause requiring the inclusion of these provisions in any further subcontracts that may in turn be made. The Required Contract Provisions shall in no instance be incorporated by reference.

3. A breach of any of the stipulations contained in these Required Contract Provisions may be grounds for termination of the contract.

4. A breach of the following clauses may also be grounds for debarment as provided in 29 CFR 5.6(b):

Section 1, paragraph 2.

Section VI, paragraphs 1, 2, 3, 5 and 8a.

Section VII, paragraphs 1, 5a, 5b and 5d.

II. Employment preference.

1. During the performance of this contract, the contractor undertaking to do work which is, or reasonably may be, done as on-site work, shall give preference to qualified persons who regularly reside in the labor area as designated by the United States Department of Labor wherein the contract work is situated, or the subregion, or the Appalachian counties of the State wherein the contract work is situated, except:

a. To the extent that qualified persons regularly residing in the area are not available.

b. For the reasonable needs of the contractor to employ supervisory or specially experienced personnel necessary to assure an efficient execution of the contract work.

c. For the obligation of the contractor to offer employment to present or former employees as the result of a lawful collective bargaining contract, provided that the number of nonresident persons employed under this subparagraph 1c shall not exceed 20 percent of the total number of employees employed by the contractor on the contract work, except as provided in subparagraph 4 below.

2. The contractor shall place a job order with the State Employment Service indicating (a) the classifications of laborers, mechanics and other employees he anticipates will be required to perform the contract work, (b) the number of employees required in each classification, (c) the date on which he estimates such employees will be required, and (d) any other pertinent information required by the State Employment Service to complete the job order form. The job order may be placed with the State Employment Service in writing or by telephone. If during the course of the contract work, the information submitted by the contractor in the original job order is substantially modified, he shall promptly notify the State Employment Service.

3. The contractor shall give full consideration to all qualified job applicants referred to him by the State Employment Service. The contractor is not required to grant employment to any job applicants who, in his opinion, are not qualified to perform the classification of work required.

4. If, within one week following the placing of a job order by the contractor with the State Employment Service, the State Employment Service is unable to refer any qualified job applicants to the contractor, or less than the number requested, the State Employment Service will forward a certificate to the contractor indicating the unavailability of applicants. Such certificate shall be made a part of the contractor's permanent project records. Upon receipt of this certificate, the contractor may employ persons who do not normally reside in the labor area to fill the positions covered by the certificate, notwithstanding the provisions of subparagraph 1c above.

5. The contractor shall include the provisions of section II-1 through II-4 in every subcontract for work which is, or reasonably may be, done as on-site work.

III. Equal opportunity: employment practices.

During the performance of this contract, the contractor agrees as follows:

a. The contractor will not discriminate against any employee or applicant for employment because of race, color, religion, sex, or national origin. The contractor will take affirmative action to ensure that applicants are employed, and that employees are treated during employment without regard to their race, color, religion, sex, or national origin. Such action shall include, but not be limited to the following: Employment, upgrading, demotion or transfer; recruitment or recruitment advertising; layoffs or termination; rates of pay or other forms of compensation; and selection of training, including apprenticeship. The contractor agrees to post in conspicuous places, available to employees and applicants for employment, notices to be provided by the State highway department setting forth the provisions of this nondiscrimination clause.

b. The contractor will, in all solicitations or advertisements for employees placed by or on behalf of the contractor, state that all qualified applicants will receive consideration for employment without regard to race, color, religion, sex, or national origin.

c. The contractor will send to each labor union or representative of workers with which he has a collective bargaining agreement or other contract or understanding, a notice to be provided by the State highway department advising the said labor union or workers' representative of the contractor's commitments under this section III and shall post copies of the notice in conspicuous places available to employees and applicants for employment.

d. The contractor will comply with all provisions of Executive Order 11246 of September 24, 1965, and of the rules, regulations and relevant orders of the Secretary of Labor.

e. The contractor will furnish all information and reports required by Executive Order 11246 of September 24, 1965, and by rules, regulations and orders of the Secretary of Labor or pursuant thereto, and will permit access to his books, records and accounts by the Federal Highway Administration and the Secretary of Labor for purposes of investigation to ascertain compliance with such rules, regulations and orders.

f. In the event of the contractor's noncompliance with the nondiscrimination clauses of this contract or with any of the said rules, regulations or orders, this contract may be canceled, terminated or suspended in whole or in part and the contractor may be declared ineligible for further Government contracts or federally-assisted construction contracts in accordance with procedures authorized in Executive Order 11246 of September 24, 1965, and such other sanctions may be imposed and remedies invoked as provided in Executive Order 11246 of September 24, 1965, or by rule, regulation or order of the Secretary of Labor, or as otherwise provided by law.

g. The contractor will include the provisions of this section III in every subcontract or purchase order unless exempted by rules, regulations or orders of the Secretary of Labor issued pursuant to section 204 of Executive Order 11246 of September 24, 1965, so that such provisions will be binding upon each subcontractor or vendor. The contractor will take such action with respect to any subcontract or purchase order as the State Highway Department or the Federal Highway Administration may direct as a means of enforcing such provisions including sanctions for noncompliance: Provided, however, That in the event a contractor becomes involved in, or is threatened with litigation with a subcontractor or vendor as a result of such direction by the Federal Highway Administration, the contractor may request the United States to enter into such litigation to protect the interests of the United States.

IV. Equal opportunity selection of subcontractors, procurement of materials, and leasing of equipment.

During the performance of this contract, the contractor, for itself, its assignees and successors in interest (hereinafter referred to as the contractor), agrees as follows:

1. Compliance with regulations. The contractor shall comply with the provisions of 23 U.S.C. 324 and with the regulations relative to nondiscrimination in Federally-assisted programs of the Department of Transportation (hereinafter, "DOT") title 49, Code of Federal Regulations, part 21, as they may be amended from time to time (hereinafter referred to as the Regulations), which are herein incorporated by reference and made a part of this contract.

2. Nondiscrimination. The contractor, with regard to the work performed by it during the contract, shall not discriminate on the grounds of race, color, sex, or national origin in the selection and retention of subcontractors, including procurements of materials and leases of equipments. The contractor shall not participate either directly or indirectly in the discrimination prohibited by section 21.5 of the Regulations, including employment practices.

3. Solicitations for subcontracts including procurement of materials and equipment. In all solicitations either by competitive bidding or negotiation made by the contractor for work to be performed under a subcontract, including procurements of materials or leases of equipment, each potential subcontractor or supplier, shall be notified by the contractor of the contractor's obligations under this contract and the Regulations relative to nondiscrimination on the grounds of race, color, sex, or national origin.

4. Information and reports. The contractor shall provide all information and reports required by the Regulations, or directives issued pursuant thereto, and shall permit access to its books, records, accounts, other sources of information, and its facilities as may be determined by the State highway department or the Federal Highway Administration to be pertinent to ascertain compliance with such Regulations, orders and instructions. Where any information required of a contractor is in the exclusive possession of another who fails or refuses to furnish this information, the contractor shall so certify to the State highway department, or the Federal Highway Administration, as appropriate, and shall set forth what efforts it has made to obtain the information.

5. Sanctions for noncompliance. In the event of the contractor's noncompliance with the nondiscrimination provisions of this contract, the State highway department shall impose such contract sanctions as it or the Federal Highway Administration may determine to be appropriate, including, but not limited to:

a. Withholding of payments to the contractor under the contract until the contractor complies, and/or

b. Cancellation, termination or suspension of the contract, in whole or in part.

6. Incorporation of provisions. The contractor will include the provisions of paragraphs (1) through (6) in every subcontract, including procurements of materials and leases of equipment, unless exempt by the Regulations, or directives issued pursuant thereto. The contractor shall take such action with respect to any subcontract or procurement, as the State highway department or the Federal Highway Administration may direct as a means of enforcing such provisions including sanctions for noncompliance: Provided, however, That, in the event a contractor becomes involved in, or is threatened with, litigation with a subcontractor or supplier, as a result of such direction, the contractor may request the State to enter into such litigation to protect the interests of the State, and, in addition, the contractor may request the United States to enter into such litigation to protect the interests of the United States.

V. Nonsegregated facilities.

(Applicable to Federal-aid construction contracts and related subcontracts exceeding $10,000 which are not exempt from the Equal Opportunity clause.)

By submission of this bid, the execution of this contract or subcontract, or the consummation of this material supply agreement, as appropriate, the bidder, Federal-aid construction contractor, subcontractor, or material supplier, as appropriate, certifies that he does not maintain or provide for his employees any segregated facilities at any of his establishments, and that he does not permit his employees to perform their services at any location, under his control, where segregated facilities are maintained. He certifies further that he will not maintain or provide for his employees any segregated facilities at any of his establishments, and that he will not permit his employees to perform their services at any location, under his control, where segregated facilities are maintained. He agrees that a breach of this certification is a violation of the Equal Opportunity clause in this contract. As used in this certification, the term segregated facilities means any waiting rooms, work areas, restrooms and washrooms, restaurants and other eating areas, timeclocks, locker rooms and other storage or dressing areas, parking lots, drinking fountains, recreation or entertainment areas, transportation, and housing facilities provided for employees which are segregated by explicit directive or are in fact segregated on the basis of race, creed, color, or national origin, because of habit, local custom, or otherwise. He agrees that (except where he has obtained identical certifications from proposed subcontractors and material suppliers for specific time periods), he will obtain identical certifications from proposed subcontractors or material suppliers prior to the award of subcontracts or the consummation of material supply agreements, exceeding $10,000 which are not exempt from the provisions of the Equal Opportunity clause, and that he will retain such certification in his files.

VI. Payment of predetermined minimum wages.

1. General. All mechanics and laborers employed or working upon the site of the work will be paid unconditionally and not less than once a week, and without subsequent deduction or rebate on any account, except such payroll deductions as are permitted by regulations issued by the Secretary of Labor under the Copeland Act (29 CFR part 3), the full amounts due at time of payment computed at wage rates not less than those contained in the wage determination decision of the Secretary of Labor which is attached hereto and made a part thereof, regardless of any contractual relationship which may be alleged to exist between the contractor and such laborers and mechanics; and the wage determination decision shall be posted by the contractor at the site of the work in a prominent place where it can be easily seen by the workers. For the purpose of this clause, contributions made or costs reasonably anticipated under section 1(b)(2) of the Davis-Bacon Act on behalf of laborers or mechanics are considered wages paid to such laborers or mechanics, subject to the provisions of section VI, paragraph 3b, hereof. Also for the purpose of this clause, regular contributions made or costs incurred for more than a weekly period under plans, funds, or programs, but covering the particular weekly period, are deemed to be constructively made or incurred during such weekly period.

2. Classifications -- a. The State highway department contracting officer shall require that any class of laborers or mechanics which is not listed in the wage determination and which is to be employed under the contract, shall be classified or reclassified conformably to the wage determination, and a report of the action taken shall be sent by the State highway department contracting officer to the Secretary of Labor.

b. In the event the interested parties cannot agree on the proper classification or reclassification of a particular class of laborers and mechanics to be used, the question accompanied by the recommendation of the State highway department contracting officer shall be referred to the Secretary for final determination.

3. Payment of fringe benefits -- a. The State highway department contracting officer shall require, whenever the minimum wage rate prescribed in the contract for a class of laborers or mechanics includes a fringe benefit which is not expressed as an hourly wage rate and the contractor is obligated to pay a cash equivalent of such a fringe benefit, an hourly cash equivalent thereof to be established. In the event the interested parties cannot agree upon a cash equivalent of the fringe benefits, the question, accompanied by the recommendation of the contracting officer, shall be referred to the Secretary of Labor for determination.

b. If the contractor does not make payments to a trustee or other third person, he may consider as part of the wage of any laborer or mechanic the amount of any costs reasonably anticipated in providing benefits under a plan or program of a type expressly listed in the wage determination decision of the Secretary of Labor which is part of this contract: Provided, however, The Secretary of Labor has found, upon the written request of the contractor, that the applicable standards of the Davis-Bacon Act have been met. The Secretary of Labor may require the contractor to set aside in a separate account assets for the meeting of obligations under the plan or program.

4. Payment of excess wages. While the wage rates shown are the minimum rates required by the contract to be paid during its life, this is not a representation that labor can be obtained at these rates. No increase in the contract price shall be allowed or authorized on account of the payment of wage rates in excess of those listed herein.

5. Apprentices and trainees (Programs of Department of Labor). a. Apprentices will be permitted to work at less than the predetermined rate for the work they performed when they are employed and individually registered in a bona fide apprenticeship program registered with the U.S. Department of Labor, Manpower Administration, Bureau of Apprenticeship and Training, or with a State Apprenticeship Agency recognized by the Bureau, or if a person is employed in his first 90 days of probationary employment as an apprentice in such an apprenticeship program, who is not individually registered in the program, but who has been certified by the Bureau of Apprenticeship and Training or a State Apprenticeship Agency (where appropriate) to be eligible for probationary employment as an apprentice. The allowable ratio of apprentices to journeymen in any craft classification shall not be greater than the ratio permitted to the contractor as to his entire work force under the registered program. Any employee listed on a payroll at an apprentice wage rate, who is not a trainee as defined in 29 CFR 5.2(c)(2) or is not registered or otherwise employed as stated above, shall be paid the wage rate determined by the Secretary of Labor for the classification of work he actually performed. The contractor or subcontractor will be required to furnish to the State highway department or to a representative of the Wage-Hour Division of the U.S. Department of Labor written evidence of the registration of his program and apprentices as well as the appropriate ratios and wage rates (expressed in percentages of the journeyman hourly rates), for the area of construction prior to using any apprentices on the contract work. The wage rate paid apprentices shall be not less than the appropriate percentage of the journeyman's rate contained in the applicable wage determination.

b. Trainees, except as provided in 29 CFR 5.15, will not be permitted to work at less than the predetermined rate for the work performed unless they are employed pursuant to and individually registered in a program which has received prior approval, evidenced by formal certification, by the U.S. Department of Labor, Manpower Administration, Bureau of Apprenticeship and Training. The ratio of trainees to journeymen shall not be greater than permitted under the plan approved by the Bureau of Apprenticeship and Training. Every trainee must be paid at not less than the rate specified in the approved program for his level of progress. Any employee listed on the payroll at a trainee rate who is not registered and participating in a training plan approved by the Bureau of Apprenticeship and Training shall be paid not less than the wage rate determined by the Secretary of Labor for the classification of work he actually performed. The contractor or subcontractor will be required to furnish the State highway department or a representative of the Wage-Hour Division of the U.S. Department of Labor written evidence of the certification of his program, the registration of the trainees, and the ratios and wage rates prescribed in that program. In the event the Bureau of Apprenticeship and Training withdraws approval of a training program, the contractor will no longer be permitted to utilize trainees at less than the applicable predetermined rate for the work performed until an acceptable program is approved.

c. The utilization of apprentices, trainees and journeymen shall be in conformity with the equal employment opportunity requirements of Executive Order 11246, as amended, and 29 CFR part 30.

6. Apprentices and trainees (Programs of Department of Transportation). Apprentices and trainees working under apprenticeship and skill training programs which have been certified by the Secretary of Transportation as promoting equal opportunity in connection with Federal-aid highway construction programs are not subject to the requirements of section VI, paragraph 5 above. The straight time hourly wage rates for apprentices and trainees under such programs will be established by the particular programs.

7. Withholding for unpaid wages. The State highway department contracting officer may withhold or cause to be withheld from the contractor so much of the accrued payments or advances as may be considered necessary to pay laborers, mechanics, (including apprentices and trainees) watchmen, or guards employed by the contractor or any subcontractor on the work the full amount of wages required by the contract. In the event of failure to pay any laborer, mechanic, (including apprentices and trainees) watchman or guard employed or working on the site of the work, all or part of the wages required by the contract, the State highway department contracting officer may, after written notice to the contractor, take such action as may be necessary to cause the suspension of any further payment, advance, or guarantee of funds until such violations have ceased.

8. Overtime requirements. a. No contractor or subcontractor contracting for any part of the contract work which may require or involve the employment of laborers, mechanics, watchmen or guards (including apprentices and trainees described in paragraphs 5 and 6 above) shall require or permit any laborer, mechanic, watchman or guard in any workweek in which he is employed on such work, to work in excess of eight hours in any calendar day or in excess of forty hours in such workweek unless such laborer, mechanic, watchman or guard receives compensation at a rate not less than one and one-half times his basic rate of pay for all hours worked in excess of eight hours in any calendar day or in excess of forty hours in such workweek, as the case may be.

b. In the event of any violation of paragraph 8a, the contractor and any subcontractor responsible therefor shall be liable to any affected employee for his unpaid wages. In addition, such contractor and subcontractor shall be liable to the United States for liquidated damages. Such liquidated damages shall be computed with respect to each individual laborer, mechanic, watchman or guard employed in violation of paragraph 8a, in the sum of $10 for each calendar day on which such employee was required or permitted to work in excess of eight hours or in excess of the standard workweek of forty hours without payment of the overtime wages required by paragraph 8a.

c. The State highway department contracting officer may withhold or cause to be withheld, from any moneys payable on account of work performed by the contractor or subcontractor, such sums as may administratively be determined to be necessary to satisfy any liabilities of such contractor or subcontractor for liquidated damages as provided in paragraph 8b.

VII. Statements and payrolls.

1. Compliance with Copeland Regulations (29 CFR part 3). The contractor shall comply with the Copeland Regulations (29 CFR part 3) of the Secretary of Labor which are herein incorporated by reference.

2. Weekly statement. Each contractor or subcontractor shall furnish each week a statement to the State highway department resident engineer with respect to the wages paid each of its employees, including apprentices and trainees described in section VI, paragraphs 5 and 6, and watchmen and guards on work covered by the Copeland Regulations during the preceding weekly payroll period. The statement shall be executed by the contractor or subcontractor or by an authorized officer or employee of the contractor or subcontractor who supervises the payment of wages. Contractors and subcontractors must use the certification set forth on U.S. Department of Labor Form WH-348, or the same certification appearing on the reverse of Optional U.S. Department of Labor Form WH-347, or on any form with identical wording.

3. Final labor summary. The contractor and each subcontractor shall furnish, upon the completion of the contract, a summary of all employment, indicating for the completed project the total hours worked and the total amount earned. This data shall be submitted to the State highway department resident engineer on Form PR-47 together with the data required in section VIII, hereof, relative to materials and supplies.

4. Final certificate. Upon completion of the contract, the contractor shall submit to the State highway department contracting officer, for transmission to the Federal Highway Administration with the voucher for final payment for any work performed under the contract, a certificate concerning wages and classifications for laborers, mechanics, watchmen and guards employed on the project, in the following form:

The undersigned, contractor on

(Project No.)

hereby certifies that all laborers, mechanics, apprentices, trainees, watchmen and guards employed by him or by any subcontractor performing work under the contract on the project have been paid wages at rates not less than those required by the contract provisions, and that the work performed by each such laborer, mechanic, apprentice or trainee conformed to the classifications set forth in the contract or training program provisions applicable to the wage rate paid. Signature and title_____

5. Payrolls and payroll records -- a. Payrolls and basic records relating thereto will be maintained during the course of the work and preserved for a period of three years thereafter for all laborers, mechanics, apprentices, trainees, watchmen and guards working at the site of the work.

b. The payroll records shall contain the name, social security number and address of each such employee, his correct classification, rates of pay (including rates of contributions or costs anticipated of the types described in section 1(b)(2) of the Davis-Bacon Act), daily and weekly number of hours worked, deductions made and actual wages paid. Whenever the Secretary of Labor, pursuant to section VI, paragraph 3.b., has found that the wages of any laborer or mechanic include the amount of any costs reasonably anticipated in providing benefits under a plan or program described in section I(b)(2)(B) of the Davis-Bacon Act, the contractor shall maintain records which show that the commitment to provide such benefits is enforceable, that the plan or program is financially responsible, and that the plan or program has been communicated in writing to the laborers or mechanics affected, and records which show the costs anticipated or the actual cost incurred in providing such benefits.

c. The payrolls shall contain the following information:

1. The employee's full name, address and social security number and a notation indicating whether the employee does, or does not, normally reside in the labor area as defined in section II, paragraph 1.a. (The employee's full name and social security number need only appear on the first payroll on which his name appears. The employee's address need only be shown on the first submitted payroll on which the employee's name appears, unless a change of address necessitates a submittal to reflect the new address.)

2. The employee's classification.

3. Entries indicating the employee's basic hourly wage rate and, where applicable, the overtime hourly wage rate. The payroll should indicate separately the amounts of employee and employer contributions to fringe benefits funds and/or programs. Any fringe benefits paid to the employee in cash must be indicated. There is no prescribed or mandatory form for showing the above information on payrolls.

4. The employee's daily and weekly hours worked in each classification, including actual overtime hours worked (not adjusted).

5. The itemized deductions made and

6. The net wages paid.

d. The contractor will submit weekly a copy of all payrolls to the State highway department resident engineer. The copy shall be accompanied by a statement signed by the employer or his agent indicating that the payrolls are correct and complete, that the wage rates contained therein are not less than those determined by the Secretary of Labor and the classifications set forth for each laborer or mechanic conform with the work he performed. Submission of a weekly statement which is required under this contract by section VII, paragraph 2, and the Copeland Regulations of the Secretary of Labor (29 CFR part 3) and the filing with the initial payroll or any subsequent payroll of a copy of any findings by the Secretary of Labor pursuant to section VI, paragraph 3b, shall satisfy this requirement. The prime contractor shall be responsible for the submission of copies of payrolls of all subcontractors. The contractor will make the records required under the labor standards clauses of the contract available for inspection by authorized representatives of the State highway department, the Federal Highway Administration and the Department of Labor, and will permit such representatives to interview employees during working hours on the job.

e. The wages of labor shall be paid in legal tender of the United States, except that this condition will be considered satisfied if payment is made by negotiable check, on a solvent bank, which may be cashed readily by the employee in the local community for the full amount, without discount or collection charges of any kind. Where checks are used for payment, the contractor shall make all necessary arrangements for them to be cashed and shall given information regarding such arrangements.

f. No fee of any kind shall be asked or accepted by the contractor or any of his agents from any person as a condition of employment on the project.

g. No laborers shall be charged for any tools used in performing their respective duties except for reasonably avoidable loss or damage thereto.

h. Every employee on the work covered by this contract shall be permitted to lodge, board and trade where and with whom he elects and neither the contractor nor his agents, nor his employees shall, directly or indirectly, require as a condition of employment that an employee shall lodge, board or trade at a particular place or with a particular person.

i. No charge shall be made for any transportation furnished by the contractor, or his agents, to any person employed on the work.

j. No individual shall be employed as a laborer or mechanic on this contract except on a wage basis, but this shall not be construed to prohibit the rental of teams, trucks, or other equipment from individuals.

VIII. Record of materials, supplies and labor.

1. The contractor shall maintain a record of the total cost of all materials and supplies purchased for and incorporated in the work, and also of the quantities of those specific materials and supplies listed on Form PR-47 and in the units shown. Upon completion of the contract, this record, together with the final labor summary required in section VII, paragraph 3, hereof, shall be transmitted to the State highway department resident engineer for the project on Form PR-47 in accordance with instructions attached thereto, which will be furnished for this purpose upon request. The quantities for the listed items shall be reported separately for roadway and for structures over 20 feet long as measured along the centerline of the roadway.

2. The contractor shall become familiar with the list of specific materials and supplies contained in Form PR-47 prior to the commencement of work under this contract. Any additional materials information required will be solicited through revisions of Form PR-47 with attendant explanations.

3. Where subcontracts are involved the contractor shall submit either a single report covering work both by himself and all his subcontractors, or he may submit separate reports for himself and for each of his subcontractors.

IX. Subletting or assigning the contract.

1. The contractor shall perform with his own organization contract work amounting to not less than 50 percent of the original total contract price, except that any items designated by the State as Specialty Items may be performed by subcontract and the amount of any such Specialty Items so performed may be deducted from the original total contract price before computing the amount of work required to be performed by the contractor with his own organization.

a. His own organization shall be construed to include only workmen employed and paid directly by the prime contractor and equipment owned or rented by him, with or without operators.

b. Specialty items shall be construed to be limited to work that requires highly specialized knowledge, craftsmanship or equipment not ordinarily available in contracting organizations qualified to bid on the contract as a whole and in general are to be limited to minor components of the overall contract.

2. In addition to the 50 percent requirements set forth in paragraph 1 above, the contractor shall furnish (a) a competent superintendent or foreman who is employed by him, who has full authority to direct performance of the work in accordance with the contract requirements, and who is in charge of all construction operations (regardless of who performs the work), and (b) such other of his own organizational capability and responsibility (supervision, management, and engineering services) as the State highway department contracting officer determines is necessary to assure the performance of the contract.

3. The contract amount upon which the 50 percent requirement set forth in paragraph 1 is computed includes the cost of materials and manufactured products which are to be purchased or produced by the contractor under the contract provisions.

4. Any items that have been selected as Specialty Items for the contract are listed as such in the Special Provisions, bid schedule, or elsewhere in the contract documents.

5. No portion of the contract shall be sublet, assigned or otherwise disposed of except with the written consent of the State highway department contracting officer, or his authorized representative, and such consent when given shall not be construed to relieve the contractor of any responsibility for the fulfillment of the contract. Request for permission to sublet, assign or otherwise dispose of any portion of the contract shall be in writing and accompanied by (a) a showing that the organization which will perform the work is particularly experienced and equipped for such work, and (b) an assurance by the contractor that the labor standards provisions set forth in thiscontract shall apply to labor performed on all work encompassed by the request.

X. Safety: Accident prevention.

In the performance of this contract, the contractor shall comply with all applicable Federal, State and local laws governing safety, health and sanitation. The contractor shall provide all safeguards, safety devices and protective equipment and take any other needed actions, on his own responsibility, or as the State highway department contracting officer may determine, reasonably necessary to protect the life and health of employees on the job and the safety of the public and to protect property in connection with the performance of the work covered by the contract.

It is a condition of this contract, and shall be made a condition of each subcontract entered into pursuant to this contract, that the contractor and any subcontractor shall not require any laborer or mechanic employed in performance of the contract to work in surroundings or under working conditions which are unsanitary, hazardous, or dangerous to his health or safety, as determined under construction safety and health standards (title 29, Code of Federal Regulations, part 1926, formerly part 1518, as revised from time to time), promulgated by the United States Secretary of Labor, in accordance with section 107 of the Contract Work Hours and Safety Standards Act (83 Stat. 96).

XI. False statements concerning highway projects.

In order to assure high quality and durable construction in conformity with approved plans and specifications and a high degree of reliability on statements and representations made by engineers, contractors, suppliers, and workers on Federal-aid highway projects, it is essential that all persons concerned with the project perform their functions as carefully, thoroughly and honestly as possible. Willfull falsification, distortion, or misrepresentation with respect to any facts related to the project is a violation of Federal law. To prevent any misunderstanding regarding the seriousness of these and similar acts, the following notice shall be posted on each Federal-aid highway project in one or more places where it is readily available to all personnel concerned with the project:

NOTICE TO ALL PERSONNEL ENGAGED ON FEDERAL-AID HIGHWAY PROJECTS

Title 18 U.S.C., section 1020, reads as follows:

"Whoever, being an officer, agent, or employee of the United States, or of any State or Territory, or whoever, whether a person, association, firm, or corporation, knowingly makes any false statement, false representation, or false report as to the character, quality, quantity, or cost of the material used or to be used, or the quantity or quality of the work performed or to be performed or the costs thereof in connection with the submission of plans, maps, specifications, contracts, or costs of construction of any highway or related project submitted for approval to the Secretary of Transportation; or

"Whoever knowingly makes any false statement, false representation, false report, or false claim with respect to the character, quality, quantity, or cost of any work performed or to be performed, or materials furnished or to be furnished, in connection with the construction of any highway or related project approved by the Secretary of Transportation; or

"Whoever knowingly makes any false statement or false representation as to a material fact in any statement, certificate, or report submitted pursuant to provisions of the Federal-Aid Road Act approved July 1, 1916 (39 Stat. 355), as amended and supplemented;

"Shall be fined not more than $10,000 or imprisoned not more than five years, or both."

XII. Implementation of Clean Air Act and Federal Water Pollution Control Act (applicable to contracts and subcontracts which exceed $100,000).

1. The contractor stipulates that any facility to be utilized in the performance of this contract, unless such contract is exempt under the Clean Air Act, as amended (42 U.S.C. 1857 et seq., as amended by Pub. L. 91-604), and under the Federal Water Pollution Control Act, as amended (33 U.S.C. 1251 et seq., as amended by Pub. L. 92-500), Executive Order 11738, and regulations in implementation thereof (40 CFR part 15), is listed not on the date of contract award, on the U.S. Environmental Protection Agency (EPA) List of Violating Facilities Pursuant to 40 CFR part 15.20.

2. The contractor agrees to comply with all the requirements of section 114 of the Clean Air Act and section 308 of the Federal Water Pollution Control Act and all regulations and guidelines listed thereunder.

3. The contractor shall promptly notify the State highway department of the receipt of any communication from the Director, Office of Federal Activities, EPA, indicating that a facility to be utilized for the contract is under consideration to be listed on the EPA List of Violating Facilities.

4. The contractor agrees to include or cause to be included the requirements of subparagraphs 1 through 4 of this paragraph XII in every subcontract which exceeds $100,000, and further agrees to take such action as Government may direct as a means of enforcing such requirements.

[40 FR 49084, Oct. 21, 1975]




Appendix C to Subpart B of Part 633 -- Additional Required Contract Provisions, Appalachian Development Highway System and Local Access Roads Contracts Other Than Construction Contracts

EQUAL OPPORTUNITY: EMPLOYMENT PRACTICES AND SELECTION OF SUBCONTRACTORS, SUPPLIERS OF MATERIALS, AND LESSORS OF EQUIPMENT

During the performance of this contract, the contractor agrees as follows:

1. Compliance with regulations.

The contractor will comply with the provisions of 23 U.S.C. 324 and with the Regulations of the Department of Transportation relative to nondiscrimination in Federally-assisted programs of the Department of Transportation (Title 49, Code of Federal Regulations, part 21, hereinafter referred to as the regulations), which are herein incorporated by reference and made a part of this contract.

2. Employment practices

a. The contractor will not discriminate against any employee or applicant for employment because of race, color, sex, or national origin. The contractor will take affirmative action to ensure that applicants are employed, and that employees are treated during employment without regard to their race, color, sex, or national origin. Such action shall include, but not be limited to the following: recruitment or recruitment advertising, hiring, firing, upgrading, promotion, demotion, transfer, layoff, termination, rates of pay or other forms of compensation or benefits, selection for training or apprenticeship, use of facilities and treatment of employees. The contractor agrees to post in conspicuous places, available to employees and applicants for employment, notices setting forth the provisions of this employment practices clause.

b. The contractor will, in all solicitations or advertisements for employees placed by or on behalf of the contractor, state that all qualified applicants will receive consideration for employment without regard to race, color, sex, or national origin.

c. The contractor will send to each labor union or representative of workers with which he has a collective bargaining agreement or other contract or understanding, a notice advising the said labor union or workers representative of the contractor's commitments under the employment practices provision, and shall post copies of the notice in conspicuous places available to employees and applicants for employment.

3. Selection of subcontractors, procurement of materials and leasing of equipment.

a. The contractor, with regard to the work performed by him after award and prior to completion of the contract work, will not discriminate on the ground of race, color, sex, or national origin in the selection and retention of subcontractors, including procurements of materials and leases of equipment. The contractor will not participate either directly or indirectly in the discrimination prohibited by Section 21.5 of the Regulations.

b. In all solicitations either by competitive bidding or negotiation made by the contractor for work to be performed under a subcontract, including procurements of materials or leases of equipment, each potential subcontractor, supplier, or lessor shall be notified by the contractor of the contractor's obligations under this contract and the Regulations relative to nondiscrimination on the ground of race, color, sex, or national origin.

4. Information and reports.

The contractor will provide all information and reports required by the Regulations, or orders and instructions issued pursuant thereto, and will permit access to its books, records, accounts, other sources of information, and its facilities as may be determined by the State highway department or the Federal Highway Administration to be pertinent to ascertain compliance with such Regulations, orders and instructions. Where any information required of a contractor is in the exclusive possession of another who fails or refuses to furnish this information, the contractor shall so certify to the State highway department, or the Federal Highway Administration as appropriate, and shall set forth what efforts it has made to obtain the information.

5. Incorporation of provisions.

The contractor will include these additional required contract provisions in every subcontract, including procurements of materials and leases of equipment, unless exempt by the Regulations or orders, or instructions issued pursuant thereto. The contractor will take such action with respect to any subcontract, procurement, or lease as the State highway department or the Federal Highway Administration may direct as a means of enforcing such provisions including sanctions for non-compliance: Provided, however, That, in the event a contractor becomes involved in, or is threatened with, litigation with a subcontractor, supplier, or lessor as a result of such directed action, the contractor may request the State to enter into such litigation to protect the interest of the State, and, in addition, the contractor may request the United States to enter into such litigation to protect the interest of the United States.

6. Sanctions for noncompliance.

In the event of the contractor's noncompliance with sections 1 through 5 above, the State highway department shall impose such contract sanctions as it or the Federal Highway Administration may determine to be appropriate, including but not limited to.

a. Withholding of payments to the contractor under the contract until the contractor complies, and/or

b. Cancellation, termination or suspension of the contract in whole or in part.

[40 FR 49088, Oct. 21, 1975]




Appendix D to Subpart B of Part 633 -- Federal-Aid Proposal Notices

NOTICES TO PROSPECTIVE FEDERAL-AID CONSTRUCTION CONTRACTORS

I. Certification of nonsegregated facilities.

(a) A Certification of Nonsegregated Facilities, as required by the May 9, 1967, Order of the Secretary of Labor (32 FR 7439, May 19, 1967) on Elimination of Segregated Facilities (is included in the proposal and must be submitted prior to the award of a Federal-aid highway construction contract exceeding $10,000 which is not exempt from the provisions of the Equal Opportunity clause).

(b) Bidders are cautioned as follows: By signing this bid, the bidder will be deemed to have signed and agreed to the provisions of the "Certification of Nonsegregated Facilities" in this proposal. This certification provides that the bidder does not maintain or provide for his employees facilities which are segregated on a basis of race, creed, color, or national origin, whether such facilities are segregated by directive or on a de facto basis. The certification also provides that the bidder will not maintain such segregated facilities.

(c) Bidders receiving Federal-aid highway construction contract awards exceeding $10,000 which are not exempt from the provisions of the Equal Opportunity clause, will be required to provide for the forwarding of the following notice to prospective subcontractors for construction contracts and material suppliers where the subcontracts or material supply agreements exceed $10,000 and are not exempt from the provisions of the Equal Opportunity clause.

NOTICE TO PROSPECTIVE SUBCONTRACTORS AND MATERIAL SUPPLIERS OF REQUIREMENT FOR CERTIFICATION OF NONSEGREGATED FACILITIES

(a) A Certification of Nonsegregated Facilities is required by the May 9, 1967, Order of the Secretary of Labor (32 FR 7431, May 19, 1967) on Elimination of Segregated Facilities, which is included in the proposal, or attached hereto, must be submitted by each subcontractor and material supplier prior to the award of the subcontract or consummation of a material supply agreement if such subcontract or agreement exceeds $10,000 and is not exempt from the provisions of the Equal Opportunity clause.

(b) Subcontractors and material suppliers are cautioned as follows: By signing the subcontract or entering into a material supply agreement, the subcontractor or material supplier will be deemed to have signed and agreed to the provisions of the "Certification of Nonsegregated Facilities" in the subcontract or material supply agreement. This certification provides that the subcontractor or material supplier does not maintain or provide for his employees facilities which are segregated on the basis of race, creed, color, or national origin, whether such facilities are segregated by directive or on a de facto basis. The certification also provides that the subcontractor or material supplier will not maintain such segregated facilities.

(c) Subcontractors or material suppliers receiving subcontract awards or material supply agreements exceeding $10,000 which are not exempt from the provisions of the Equal Opportunity clause will be required to provide for the forwarding of this notice to prospective subcontractors for construction contracts and material suppliers where the subcontracts or material supply agreements exceed $10,000 and are not exempt from the provisions of the Equal Opportunity clause.

II. Implementation of Clean Air Act.

(a) By signing this bid, the bidder will be deemed to have stipulated as follows:

(1) That any facility to be utilized in the performance of this contract, unless such contract is exempt under the Clean Air Act, as amended (42 U.S.C. 1857 et seq., as by Pub. L. 91-604), Executive order 11738, and regulations in implementation thereof (40 CFR part 15, is not listed on the U.S. Environmental Protection Agency (EPA) List of Violating Facilities pursuant to 40 CFR 15.20.

(2) That the State highway department shall be promptly notified prior to contract award of the receipt by the bidder of any communication from the Director, Office of Federal Activities, EPA, indicating that a facility to be utilized for the contract is under consideration to be listed on the EPA List of Violating Facilities.

Subpart C -- Direct Federal Construction Contracts


Authority: 23 U.S.C. 315; 49 CFR 1.48(b)(35).

Source: 39 FR 22418, June 24, 1974, unless otherwise noted.


§633.301   Purpose.

To prescribe for direct Federal highway construction contracts, provisions covering employment, safety, specific equal employment opportunity responsibilities and false statements concerning highway projects.


§633.302   Applicability.

(a) The form "Continuation of Standard Form 19-A, Labor Standards Provisions" (appendix A) shall be made a part of all highway construction contracts under the direct supervision of the Federal Highway Administration. The form shall be incorporated in each highway construction contract as a continuation of Standard Form 19-A, Labor Standards Provisions and the clauses set forth in paragraph 7 of appendix A shall be included in all subcontracts.

(b) Such additional labor standards provisions as hometown or imposed equal employment opportunity plans shall be added at the end of the form.

Appendix A to Subpart C of Part 633 -- Continuation of Standard Form 19-A Labor Standards Provisions (dot-fhwa 3-74)

1. Weekly Statement.

The contractor and each subcontractor shall furnish each week a statement with respect to the wages paid each of his employees engaged on work covered by the Copeland Act Regulations, 29 CFR part 3, and by 29 CFR part 5, during the preceding weekly payroll period. The statement shall be executed by the contractor or subcontractor or by an authorized officer or employee of the contractor or subcontractor who supervises the payment of wages. The statement shall be on U.S. Department of Labor Form WH 348, "Statement of Compliance," or on an identical form on the back of U.S. Department of Labor Form WH 347, "Payroll (For Contractor's Optional Use)," or on any form with identical wording. Copies of these forms may be purchased from the Government Printing Office.

2. Employment Practices.

a. The wages of labor shall be paid in legal tender of the United States, except that this condition will be considered satisfied if payment is made by a negotiable check, on a solvent bank, which may be cashed readily by the employee in the local community for the full amount, without discount or collection charges of any kind. Where checks are used for payment, the contractor and each subcontractor shall make all necessary arrangements for them to be cashed and shall give information to their employees regarding such arrangements.

b. No fee of any kind shall be asked or accepted by the contractor, or any of his agents or subcontractors, from any person as a condition of employment on the project.

c. No laborers or mechanics shall be charged for any tools used in performing their duties unless prior permission to make payroll deductions for such charges has been granted by the Secretary of Labor in accordance with Section 3.6 of the Copeland Act Regulations.

d. Every employee on the work covered by this contract shall be permitted to lodge, board, and trade where and with whom he elects and neither the contractor, his subcontractors, nor his employees shall directly or indirectly require as a condition of employment that an employee shall lodge, board or trade at a particular place or with a particular person.

e. No charge shall be made for any transportation furnished by the contractor, or his subcontractors to any person employed on the work.

f. No individual shall be employed as a laborer or mechanic on this contract except on a wage basis, but this shall not be construed to prohibit the rental of teams, trucks, or other equipment from individuals.

g. Each employee's social security number must be shown on the first payroll on which his name appears.

3. Payment of Excess Wages.

While the wage rates shown in the wage determination decision are the minimum hourly rates required by the contract to be paid during its life, it is the responsibility of bidders to inform themselves as to the local labor conditions, such as the length of workday and workweek, overtime compensation, health and welfare contributions, labor supply, and prospective changes or adjustment of wage rates. No increase in the contract price shall be allowed or authorized on account of the payment of wage rates in excess of those listed herein.

4. Safety.

It is a condition of this contract, and shall be made a condition of each subcontract entered into pursuant to this contract, that the contractor and any subcontractor shall not require any individual employed in performance of the contract to work in surroundings or under working conditions which are unsanitary, hazardous, or dangerous to his health or safety, as determined under construction safety and health standards (Title 29, Code of Federal Regulations, part 1926, as revised from time to time) promulgated by the United States Secretary of Labor, in accordance with Section 107 of the Contract Work Hours and Safety Standards Act.

5. False Statements Concerning Highway Projects.

In order to assure high quality and durable construction in conformity with approved plans and specifications and a high degree of reliability on statements and representations made by engineers, contractors, suppliers, and workers on Federal highway projects, it is essential that all persons concerned with the project perform their functions as carefully, thoroughly, and honestly as possible. Willful falsification, distortion, or misrepresentation with respect to any facts related to the project is a violation of Federal law. To prevent any misunderstanding regarding the seriousness of these and similar acts, the contractor shall post the Notice, Form PR-1022 on each Federal highway project in one or more places where it is readily available to all personnel concerned with the project.

6. Specific Equal Employment Opportunity Responsibilities.
    a. General. (1) Equal employment opportunity requirements not to discriminate and to take affirmative action to assure equal employment opportunity as required by Executive Order 11246 and Executive Order 11375 are set forth in SF 23-A, General Provisions and in these Provisions. The requirements set forth in these Provisions shall constitute the specific affirmative action requirements for project activities under this contract and supplement the equal employment opportunity requirements set forth in the General Provisions.

(2) The contractor will work with the Federal Government in carrying out equal employment opportunity obligations and in their review of his activities under the contract.

(3) The prime contractor, and all subcontractors (not including material suppliers), holding subcontracts of $10,000 or more, will comply with the minimum equal employment opportunity requirements set forth in the balance of this clause 6.
    b. Equal Employment Opportunity Policy. The contractor will accept as his operating policy the following statement which is designed to further the provision of equal employment opportunity to all persons without regard to their race, color, religion, sex, or national origin, and to promote the full realization of equal employment opportunity through a positive continuing program:

It is the policy of this Company to assure that applicants are employed, and that employees are treated during employment, without regard to their race, religion, sex, color, or national origin. Such action shall include: employment, upgrading, demotion, or transfer; recruitment or recruitment advertising; layoff or termination; rates of pay or other forms of compensation; and selection for training, including apprenticeship, preapprenticeship, and/or on-the-job training.

c. Equal Employment Opportunity Officer.

The contractor will designate and make known to the contracting officer an equal employment opportunity officer (hereinafter referred to as the EEO Officer) who must be capable of effectively administering and promoting an active contractor program of equal employment opportunity and who must be assigned adequate authority and responsibility to do so.

d. Dissemination of Policy.

(1) All members of the contractor's staff who are authorized to hire, supervise, promote, and discharge employees, or who recommend such action, or who are substantially involved in such action, will be made fully cognizant of, and will implement, the contractor's equal employment opportunity policy and contractual responsibilities. To insure that the above agreement will be met, the following actions will be taken as a minimum:

(a) Periodic meetings of supervisory and personnel office employees will be conducted before the start of work and then not less often than once every six months, at which time the contractor's equal employment opportunity policy and its implementation will be reviewed and explained. The meetings will be conducted by the EEO Officer or other knowledgeable company official.

(b) All new supervisory or personnel office employees will be given a thorough indoctrination by the EEO Officer or other knowledgeable company official covering all major aspects of the contractor's equal employment opportunity obligations within thirty days following their reporting for duty with the contractor.

(c) The EEO Officer or appropriate company official will instruct all employees engaged in the direct recruitment of employees for the project relative to the methods followed by the contractor in locating and hiring minority group employees.

(2) In order to make the contractor's equal employment opportunity policy known to all employees, prospective employees and potential sources of employees, i.e., schools, employment agencies, labor unions (where appropriate), college placement officer, etc., the contractor will take the following actions:

(a) Notices and posters setting forth the contractor's equal employment opportunity policy will be placed in areas readily accessible to employees, applicants for employment and potential employees.

(b) The contractor's equal employment opportunity policy and the procedures to implement such policy will be brought to the attention of employees by means of meetings, employee handbooks, or other appropriate means.

e. Recruitment.

(1) When advertising for employees, the contractor will include in all advertisements for employees the notation: "An Equal Opportunity Employer." He will insert all such advertisements in newspapers, or other publications, having a large circulation among minority groups in the area from which the project work force would normally be derived.

(2) The contractor will, unless precluded by a valid bargaining agreement, conduct systematic and direct recruitment through public and private employee referral sources likely to yield qualified minority group applicants, including, but not limited to, State employment agencies, schools, colleges and minority group organizations. To meet this requirement, the contractor will, through his EEO Officer, identify sources of potential minority group employees, and establish with such identified sources procedures whereby minority group applicants may be referred to the contractor for employment consideration.

(3) The contractor will encourage his present employees to refer minority group applicants for employment by posting appropriate notices or bulletins in areas accessible to all such employees. In addition, information and procedures with regard to referring minority group applicants will be discussed with employees.

f. Personnel Actions.

(1) Wages, working conditions, and employee benefits shall be established and administered, and personnel actions of every type, including hiring, upgrading, promotion, transfer, demotion, layoff, and termination, shall be taken without regard to race, color, religion, sex, or national origin. The following procedures shall be followed:

(a) The contractor will conduct periodic inspections of project sites to insure that working conditions and employee facilities do not indicate discriminatory treatment of project site personnel.

(b) The contractor will periodically evaluate the spread of wages paid within each classification to determine any evidence of discriminatory wage practices.

(c) The contractor will periodically review selected personnel actions in depth to determine whether there is evidence of discrimination. Where evidence is found, the contractor will promptly take corrective action. If the review indicates that the discrimination may extend beyond the actions reviewed, such corrective action shall include all affected persons.

(d) The contractor will investigate all complaints of alleged discrimination made to the contractor in connection with his obligations under this contract, will attempt to resolve such complaints, and will take appropriate corrective action. If the investigation indicates that the discrimination may affect persons other than the complainant, such corrective action shall include such other persons. Upon completion of each investigation the contractor will inform every complainant of all of his avenues of appeal.

g. Training and Promotion.

(1) The contractor will assist in locating, qualifying and increasing the skills of minority group employees and applicants, for employment.

(2) Consistent with his manpower requirements and as permissible under Federal and State regulations, the contractor will make full use of training programs, i.e., preapprenticeship apprenticeship, and/or on-the-job training programs for the geographical area of contract performance.

(3) The contractor will advise employees and applicants for employment of available training programs and entrance requirements for each.

(4) The contractor will periodically review the training and promotion potential of minority group employees and will encourage eligible employees to apply for such training and promotion.

h. Unions.

If the contractor relies in whole or in part upon unions as a source of his work force, he will use his best efforts to obtain the cooperation of such unions to increase minority group opportunities within the unions, and to effect referrals by such unions of minority group employees. Actions by the contractor, either directly or through a contractor's association acting as his agent, will include the procedures set forth below:

(1) Use his best efforts to develop, in cooperation with the unions, joint training programs aimed toward qualifying more minority group members for membership in the unions and increasing the skills of minority group employees so that they may qualify for higher paying employment.

(2) Use his best efforts to incorporate an equal employment opportunity clause into all union agreements to the end that such unions will be contractually bound to refer applicants without regard to their race, color, religion, sex, or national origin.

(3) In the event a union is unable to refer applicants as requested by the contractor within the time limit set forth in the union agreement, the contractor will, through his recruitment procedures, fill the employment vacancies without regard to race, color, religion, sex, or national origin, making full efforts to obtain qualified minority group persons.

i. Subcontracting.

(1) The contractor will use his best efforts to utilize minority group subcontractors or subcontractors with meaningful minority group representation among their employees.

(2) The contractor will use his best efforts to assure subcontractor compliance with their equal employment opportunity obligations.

j. Records and Reports.

(1) The contractor will keep such records as are necessary to determine compliance with the contractor's equal employment opportunity obligations. The records kept by the contractor will be designed to indicate:

(a) The number of minority and nonminority group members employed in each work classification on the project.

(b) The progress and efforts being made in cooperation with unions to increase minority group employment opportunities (applicable only to contractors who rely in whole or in part on unions, as a source of their work force).

(c) The progress and efforts being made in locating, hiring, training, qualifying, and upgrading minority group employees.

(d) The progress and efforts being made in securing the services of minority group subcontractors or subcontractors with meaningful minority group representation among their employees.

(2) All such records must be retained for a period of three years following completion of the contract work and shall be available at reasonable times and places for inspection by the contracting officer or his authorized representative.

(3) The contractor will submit to the Federal Highway Administration a monthly report for the first three months after construction begins, and thereafter upon request, for the duration of the project, indicating the number of minority and nonminority group employees currently engaged in each work classification required by the contract work. This information is to be reported on Form PR-1391.

7. Subcontracts.

The contractor shall include, verbatim, clauses 1, 2, 4, 5 and 6 of this continuation sheet in each of his subcontracts, except that Clause 6 will not be required for subcontracts less than $10,000. In addition, the contractor shall include a clause requiring each subcontractor to include these clauses in any lower tier subcontracts.




PART 635 -- CONSTRUCTION AND MAINTENANCE



Subpart A -- Contract Procedures


   Sec.
635.101   Purpose.
635.102   Definitions.
635.103   Applicability.
635.104   Method of construction.
635.105   Supervising agency.
635.106   Use of publicly owned equipment.
635.107   Small and disadvantaged business participation.
635.108   Health and safety.
635.109   Standardized changed condition clauses.
635.110   Licensing and qualification of contractors.
635.111   Tied bids.
635.112   Advertising for bids.
635.113   Bid opening and bid tabulations.
635.114   Award of contract and concurrence in award.
635.115   Agreement estimate.
635.116   Subcontracting and contractor responsibilities.
635.117   Labor and employment.
635.118   Payroll and weekly statements.
635.119   False statements.
635.120   Changes and extra work.
635.121   Contract time and contract time extensions.
635.122   Participation in progress payments.
635.123   Determination and documentation of pay quantities.
635.124   Participation in contract claim awards and settlements.
635.125   Termination of contract.
635.126   Record of materials, supplies, and labor.
635.127   Agreement provisions regarding overruns in contract time.

Subpart B -- Force Account Construction

635.201   Purpose.
635.202   Application.
635.203   Definitions.
635.204   Determination of more cost effective method or an emergency.
635.205   Finding of cost effectiveness.

Subpart C -- Physical Construction Authorization

635.301   Purpose.
635.303   Applicability.
635.305   Physical construction.
635.307   Coordination.
635.309   Authorization.

Subpart D -- General Material Requirements

635.401   Purpose.
635.403   Definitions.
635.405   Applicability.
635.407   Use of materials made available by a public agency.
635.409   Restrictions upon materials.
635.410   Buy America requirements.
635.411   Material or product selection.
635.413   Warranty clauses.
635.417   Convict produced materials.
Appendix A to Subpart D -- Summary of Acceptable Criteria for Specifying Types of Culvert Pipes

Subpart E -- Interstate Maintenance Guidelines

635.501   Purpose.
635.503   Policy.
635.505   Maintenance guidelines.
635.507   Implementation.
635.509   Deficient or unsatisfactory maintenance.

Authority: 23 U.S.C. 101(note), 109, 112, 113, 114, 116, 119, 128, and 315; 31 U.S.C. 6505; 42 U.S.C. 3334, 4601 et seq.; sec. 1041(a), Pub. L. 102-240, 105 Stat. 1914; 23 CFR 1.32; 49 CFR 1.48(b).

Subpart A -- Contract Procedures


Source: 56 FR 37004, Aug. 2, 1991, unless otherwise noted.


§635.101   Purpose.

To prescribe policies, requirements, and procedures relating to Federal-aid highway projects, from the time of authorization to proceed to the construction stage, to the time of final acceptance by the Federal Highway Administration (FHWA).


§635.102   Definitions.

As used in this subpart:

Administrator means the Federal Highway Administrator.

Calendar day means each day shown on the calendar but, if another definition is set forth in the State contract specifications, that definition will apply.

Certification acceptance means the alternative procedure which may be used for administering certain highway projects involving Federal funds pursuant to 23 U.S.C. 117.

Contract time means the number of workdays or calendar days specified in a contract for completion of the contract work. The term includes authorized time extensions.

Division Administrator means the chief FHWA official assigned to conduct business in a particular State. A State is as defined in 23 U.S.C. 101.

Force account means a basis of payment for the direct performance of highway construction work with payment based on the actual cost of labor, equipment, and materials furnished and consideration for overhead and profit.

Formal approval means approval in writing or the electronic transmission of such approval.

Incentive/disincentive for early completion as used in this subpart, describes a contract provision which compensates the contractor a certain amount of money for each day identified critical work is completed ahead of schedule and assesses a deduction for each day the contractor overruns the incentive/disincentive time. Its use is primarily intended for those critical projects where traffic inconvenience and delays are to be held to a minimum. The amounts are based upon estimates of such items as traffic safety, traffic maintenance, and road user delay costs.

Liquidated damages means the daily amount set forth in the contract to be deducted from the contract price to cover additional costs incurred by a State highway agency because of the contractor's failure to complete the contract work within the number of calendar days or workdays specified. The term may also mean the total of all daily amounts deducted under the terms of a particular contract.

Local public agency means any city, county, township, municipality, or other political subdivision that may be empowered to cooperate with the State highway agency in highway matters.

Major change or major extra work means a change which will significantly affect the cost of the project to the Federal Government or alter the termini, character or scope of the work.

Materially unbalanced bid means a bid which generates a reasonable doubt that award to the bidder submitting a mathematically unbalanced bid will result in the lowest ultimate cost to the Federal Government.

Mathematically unbalanced bid means a bid containing lump sum or unit bid items which do not reflect reasonable actual costs plus a reasonable proportionate share of the bidder's anticipated profit, overhead costs, and other indirect costs.

Public agency means any organization with administrative or functional responsibilities which are directly or indirectly affiliated with a governmental body of any nation, State, or local jurisdiction.

Publicly owned equipment means equipment previously purchased or otherwise acquired by the public agency involved primarily for use in its own operations.

Specialty items means work items identified in the contract which are not normally associated with highway construction and require highly specialized knowledge, abilities or equipment not ordinarily available in the type of contracting organizations qualified and expected to bid on the contract; in general, these items are to be limited to minor components of the overall contract.

State highway agency (SHA) means that department, commission, board, or official of any State charged by its laws with the responsibility for highway construction. The term "State" should be considered equivalent to "State highway agency" if the context so implies.

Workday means a calendar day during which construction operations could proceed for a major part of a shift, normally excluding Saturdays, Sundays, and State-recognized legal holidays.

[62 FR 6873, Feb. 14, 1997]



§635.103   Applicability.

The policies, requirements, and procedures prescribed in this subpart shall apply to all Federal-aid highway projects except for those title 23 requirements specifically discharged in an approved certification acceptance plan, in accordance with 23 U.S.C. 117.

[56 FR 37004, Aug. 2, 1991, as amended at 62 FR 6873, Feb. 14, 1997]



§635.104   Method of construction.

(a) Actual construction work shall be performed by contract awarded by competitive bidding; unless, as provided in §635.104(b), the SHA demonstrates to the satisfaction of the Division Administrator that some other method is more cost effective or that an emergency exists. The SHA shall assure opportunity for free, open, and competitive bidding, including adequate publicity of the advertisements or calls for bids. The advertising or calling for bids and the award of contracts shall comply with the procedures and requirements set forth in §§635.112 and 635.114.

(b) Approval by the Division Administrator for construction by a method other than competitive bidding shall be requested by the State in accordance with subpart B of part 635 of this chapter. Before such finding is made, the SHA shall determine that the organization to undertake the work is so staffed and equipped as to perform such work satisfactorily and cost effectively.


§635.105   Supervising agency.

(a) The SHA has responsibility for the construction of all Federal-aid projects, and is not relieved of such responsibility by authorizing performance of the work by a local public agency or other Federal agency. The SHA shall be responsible for insuring that such projects receive adequate supervision and inspection to insure that projects are completed in conformance with approved plans and specifications.

(b) Although the SHA may employ a consultant to provide construction engineering services, such as inspection or survey work on a project, the SHA shall provide a full-time employed State engineer to be in responsible charge of the project.

(c) When a project is located on a street or highway over which the SHA does not have legal jurisdiction, or when special conditions warrant, the SHA, while not relieved of overall project responsibility, may arrange for the local public agency having jurisdiction over such street or highway to perform the work with its own forces or by contract; provided the following conditions are met and the Division Administrator approves the arrangements in advance.

(1) In the case of force account work, there is full compliance with subpart B of this part.

(2) When the work is to be performed under a contract awarded by a local public agency, all Federal requirements including those prescribed in this subpart shall be met.

(3) The local public agency is adequately staffed and suitably equipped to undertake and satisfactorily complete the work; and

(4) In those instances where a local public agency elects to use consultants for construction engineering services, the local public agency shall provide a full-time employee of the agency to be in responsible charge of the project.


§635.106   Use of publicly owned equipment.

(a) Publicly owned equipment should not normally compete with privately owned equipment on a project to be let to contract. There may be exceptional cases, however, in which the use of equipment of the State or local public agency for highway construction purposes may be warranted or justified. A proposal by any SHA for the use of publicly owned equipment on such a project must be supported by a showing that it would clearly be cost effective to do so under the conditions peculiar to the individual project or locality.

(b) Where publicly owned equipment is to be made available in connection with construction work to be let to contract, Federal funds may participate in the cost of such work provided the following conditions are met:

(1) The proposed use of such equipment is clearly set forth in the Plans, Specifications and Estimate (PS&E) submitted to the Division Administrator for approval.

(2) The advertised specifications specify the items of publicly owned equipment available for use by the successful bidder, the rates to be charged, and the points of availability or delivery of the equipment; and

(3) The advertised specifications include a notification that the successful bidder has the option either of renting part or all of such equipment from the State or local public agency or otherwise providing the equipment necessary for the performance of the contract work.

(c) In the rental of publicly owned equipment to contractors, the State or local public agency shall not profit at the expense of Federal funds.

(d) Unforeseeable conditions may make it necessary to provide publicly owned equipment to the contractor at rental rates agreed to between the contractor and the State or local public agency after the work has started. Any such arrangement shall not form the basis for any increase in the cost of the project on which Federal funds are to participate.

(e) When publicly owned equipment is used on projects constructed on a force account basis, costs may be determined by agreed unit prices or on an actual cost basis. When agreed unit prices are applied the equipment need not be itemized nor rental rates shown in the estimate. However, if such work is to be performed on an actual cost basis, the SHA shall submit to the Division Administrator for approval the scheduie of rates proposed to be charged, exclusive of profit, for the publicly owned equipment made available for use.


§635.107   Small and disadvantaged business participation.

The SHA shall schedule contract lettings in a balanced program providing contracts of such size and character as to assure an opportunity for all sizes of contracting organizations to compete. In accordance with title VI of the Civil Rights Act of 1964, subsequent Federal-aid Highway Acts, and 49 CFR part 23, the SHA shall affirmatively encourage disadvantaged business enterprise participation in the highway construction program.


§635.108   Health and safety.

Contracts for projects shall include provisions designed:

(a) To insure full compliance with all applicable Federal, State, and local laws governing safety, health and sanitation; and

(b) To require that the contractor shall provide all safeguards, safety devices, and protective equipment and shall take any other actions reasonably necessary to protect the life and health of persons working at the site of the project and the safety of the public and to protect property in connection with the performance of the work covered by the contract.


§635.109   Standardized changed condition clauses.

(a) Except as provided in paragraph (b) of this section, the following changed conditions contract clauses shall be made part of, and incorporated in, each highway construction project approved under 23 U.S.C. 106:

(1) Differing site conditions. (i) During the progress of the work, if subsurface or latent physical conditions are encountered at the site differing materially from those indicated in the contract or if unknown physical conditions of an unusual nature, differing materially from those ordinarily encountered and generally recognized as inherent in the work provided for in the contract, are encountered at the site, the party discovering such conditions shall promptly notify the other party in writing of the specific differing conditions before the site is disturbed and before the affected work is performed.

(ii) Upon written notification, the engineer will investigate the conditions, and if it is determined that the conditions materially differ and cause an increase or decrease in the cost or time required for the performance of any work under the contract, an adjustment, excluding anticipated profits, will be made and the contract modified in writing accordingly. The engineer will notify the contractor of the determination whether or not an adjustment of the contract is warranted.

(iii) No contract adjustment which results in a benefit to the contractor will be allowed unless the contractor has provided the required written notice.

(iv) No contract adjustment will be allowed under this clause for any effects caused on unchanged work. (This provision may be omitted by the SHA's at their option.)

(2) Suspensions of work ordered by the engineer. (i) If the performance of all or any portion of the work is suspended or delayed by the engineer in writing for an unreasonable period of time (not originally anticipated, customary, or inherent to the construction industry) and the contractor believes that additional compensation and/or contract time is due as a result of such suspension or delay, the contractor shall submit to the engineer in writing a request for adjustment within 7 calendar days of receipt of the notice to resume work. The request shall set forth the reasons and support for such adjustment.

(ii) Upon receipt, the engineer will evaluate the contractor's request. If the engineer agrees that the cost and/or time required for the performance of the contract has increased as a result of such suspension and the suspension was caused by conditions beyond the control of and not the fault of the contractor, its suppliers, or subcontractors at any approved tier, and not caused by weather, the engineer will make an adjustment (excluding profit) and modify the contract in writing accordingly. The contractor will be notified of the engineer's determination whether or not an adjustment of the contract is warranted.

(iii) No contract adjustment will be allowed unless the contractor has submitted the request for adjustment within the time prescribed.

(iv) No contract adjustment will be allowed under this clause to the extent that performance would have been suspended or delayed by any other cause, or for which an adjustment is provided or excluded under any other term or condition of this contract.

(3) Significant changes in the character of work. (i) The engineer reserves the right to make, in writing, at any time during the work, such changes in quantities and such alterations in the work as are necessary to satisfactorily complete the project. Such changes in quantities and alterations shall not invalidate the contract nor release the surety, and the contractor agrees to perform the work as altered.

(ii) If the alterations or changes in quantities significantly change the character of the work under the contract, whether such alterations or changes are in themselves significant changes to the character of the work or by affecting other work cause such other work to become significantly different in character, an adjustment, excluding anticipated profit, will be made to the contract. The basis for the adjustment shall be agreed upon prior to the performance of the work. If a basis cannot be agreed upon, then an adjustment will be made either for or against the contractor in such amount as the engineer may determine to be fair and equitable.

(iii) If the alterations or changes in quantities do not significantly change the character of the work to be performed under the contract, the altered work will be paid for as provided elsewhere in the contract.

(iv) The term "significant change" shall be construed to apply only to the following circumstances:

(A) When the character of the work as altered differs materially in kind or nature from that involved or included in the original proposed construction; or

(B) When a major item of work, as defined elsewhere in the contract, is increased in excess of 125 percent or decreased below 75 percent of the original contract quantity. Any allowance for an increase in quantity shall apply only to that portion in excess of 125 percent of original contract item quantity, or in case of a decrease below 75 percent, to the actual amount of work performed.

(b) The provisions of this section shall be governed by the following:

(1) Where State statute does not permit one or more of the contract clauses included in paragraph (a) of this section, the State statute shall prevail and such clause or clauses need not be made applicable to Federal-aid highway contracts.

(2) Where the State highway agency has developed and implemented one or more of the contract clauses included in paragraph (a) of this section, such clause or clauses, as developed by the State highway agency may be included in Federal-aid highway contracts in lieu of the corresponding clause or clauses in paragraph (a) of this section. The State's action must be pursuant to a specific State statute requiring differing contract conditions clauses. Such State developed clause or clauses, however, must be in conformance with 23 U.S.C., 23 CFR and other applicable Federal statutes and regulations as appropriate and shall be subject to the Division Administrator's approval as part of the PS&E.

[56 FR 37004, Aug. 2, 1991, 57 FR 10062, Mar. 23, 1992]



§635.110   Licensing and qualification of contractors.

(a) The procedures and requirements a SHA proposes to use for qualifying and licensing contractors, who may bid for, be awarded, or perform Federal-aid highway contracts, shall be submitted to the Division Administrator for advance approval. Only those procedures and requirements so approved shall be effective with respect to Federal-aid highway projects. Any changes in approved procedures and requirements shall likewise be subject to approval by the Division Administrator.

(b) No procedure or requirement for bonding, insurance, prequalification, qualification, or licensing of contractors shall be approved which, in the judgment of the Division Administrator, may operate to restrict competition, to prevent submission of a bid by, or to prohibit the consideration of a bid submitted by, any responsible contractor, whether resident or nonresident of the State wherein the work is to be performed.

(c) No contractor shall be required by law, regulation, or practice to obtain a license before submission of a bid or before the bid may be considered for award of a contract. This, however, is not intended to preclude requirements for the licensing of a contractor upon or subsequent to the award of the contract if such requirements are consistent with competitive bidding. Prequalification of contractors may be required as a condition for submission of a bid or award of contract only if the period between the date of issuing a call for bids and the date of opening of bids affords sufficient time to enable a bidder to obtain the required prequalification rating.

(d) Requirements for the prequalification, qualification or licensing of contractors, that operate to govern the amount of work that may be bid upon by, or may be awarded to, a contractor, shall be approved only if based upon a full and appropriate evaluation of the contractor's capability to perform the work.

(e) Contractors who are currently suspended, debarred or voluntarily excluded under 49 CFR part 29 or otherwise determined to be ineligible, shall be prohibited from participating in the Federal-aid highway program.


§635.111   Tied bids.

(a) The SHA may tie or permit the tying of Federal-aid highway projects or Federal-aid and State-financed highway projects for bidding purposes where it appears that by so doing more favorable bids may be received. To avoid discrimination against contractors desiring to bid upon a lesser amount of work than that included in the tied combinations, provisions should be made to permit bidding separately on the individual projects whenever they are of such character as to be suitable for bidding independently.

(b) When Federal-aid and State-financed highway projects are tied or permitted to be tied together for bidding purposes, the bid schedule shall set forth the quantities separately for the Federal-aid work and the State-financed work. All proposals submitted for the tied projects must contain separate bid prices for each project individually. Federal participation in the cost of the work shall be on the basis of the lowest overall responsive bid proposal unless the analysis of bids reveals that mathematical unbalancing has caused an unsupported shift of cost liability to the Federal-aid work. If such a finding is made, Federal participation shall be based on the unit prices represented in the proposal by the individual contractor who would be the lowest responsive and responsible bidder if only the Federal-aid project were considered.

(c) Federal-aid highway projects and State-financed highway projects may be combined in one contract if the conditions of the projects are so similar that the unit costs on the Federal-aid projects should not be increased by such combinations of projects. In such cases, like quantities should be combined in the proposal to avoid the possibility of unbalancing of bids in favor of either of the projects in the combination.


§635.112   Advertising for bids.

(a) No work shall be undertaken on any Federal-aid project, nor shall any project be advertised for bids, prior to authorization by the Division Administrator.

(b) The advertisement and approved plans and specifications shall be available to bidders a minimum of 3 weeks prior to opening of bids except that shorter periods may be approved by the Division Administrator in special cases when justified.

(c) The SHA shall obtain the approval of the Division Administrator prior to issuing any addenda which contain a major change to the approved plans or specifications during the advertising period. Minor addenda need not receive prior approval but should be identified by the SHA at the time of or prior to requesting FHWA concurrence in award. The SHA shall provide assurance that all bidders have received all issued addenda.

(d) Nondiscriminatory bidding procedures shall be afforded to all qualified bidders regardless of National, State or local boundaries and without regard to race, color, religion, sex, national origin, age, or handicap. If any provisions of State laws, specifications, regulations, or policies may operate in any manner contrary to Federal requirements, including title VI of the Civil Rights Act of 1964, to prevent submission of a bid, or prohibit consideration of a bid submitted by any responsible bidder appropriately qualified in accordance with §635.110, such provisions shall not be applicable to Federal-aid projects. Where such nonapplicable provisions exist, notices of advertising, specifications, special provisions or other governing documents shall include a positive statement to advise prospective bidders of those provisions that are not applicable.

(e) No public agency shall be permitted to bid in competition or to enter into subcontracts with private contractors.

(f) The SHA shall include a noncollusion provision substantially as follows in the bidding documents:

Each bidder shall file a statement executed by, or on behalf of the person, firm, association, or corporation submitting the bid certifying that such person, firm, association, or corporation has not, either directly or indirectly, entered into any agreement, participated in any collusion, or otherwise taken any action, in restraint of free competitive bidding in connection with the submitted bid. Failure to submit the executed statement as part of the bidding documents will make the bid nonresponsive and not eligible for award consideration.

(1) The required form for the statement will be provided by the State to each prospective bidder.

(2) The statement shall either be in the form of an affidavit executed and sworn to by the bidder before a person who is authorized by the laws of the State to administer oaths or in the form of an unsworn declaration executed under penalty of perjury of the laws of the United States.

(g) The SHA shall include the lobbying certification requirement pursuant to 49 CFR part 20 and the requirements of 49 CFR part 29 regarding suspension and debarment certification in the bidding documents.

(h) The SHA shall clearly identify in the bidding documents those requirements which the bidder must assure are complied with to make the bid responsive. Failure to comply with these identified bidding requirements shall make the bid nonresponsive and not eligible for award consideration.


§635.113   Bid opening and bid tabulations.

(a) All bids received in accordance with the terms of the advertisement shall be publicly opened and announced either item by item or by total amount. If any bid received is not read aloud, the name of the bidder and the reason for not reading the bid aloud shall be publicly announced at the letting. Negotiation with contractors, during the period following the opening of bids and before the award of the contract shall not be permitted.

(b) The SHA shall prepare and forward tabulations of bids to the Division Administrator. These tabulations shall be certified by a responsible SHA official and shall show:

(1) Bid item details for at least the low three acceptable bids and

(2) The total amounts of all other acceptable bids.


§635.114   Award of contract and concurrence in award.

(a) Federal-aid contracts shall be awarded only on the basis of the lowest responsive bid submitted by a bidder meeting the criteria of responsibility as may have been established by the SHA in accordance with §635.110. Award shall be within the time established by the SHA and subject to the prior concurrence of the Division Administrator.

(b) The SHA shall formally request concurrence by the Division Administrator in the award of all Federal-aid contracts. Concurrence in award by the Division Administrator is a prerequisite to Federal participation in construction costs and is considered as authority to proceed with construction, unless specifically stated otherwise. Concurrence in award shall be formally approved and shall only be given after receipt and review of the tabulation of bids.

(c) Following the opening of bids, the SHA shall examine the unit bid prices of the apparent low bid for reasonable conformance with the engineer's estimated prices. A bid with extreme variations from the engineer's estimate, or where obvious unbalancing of unit prices has occurred, shall be thoroughly evaluated.

(d) Where obvious unbalanced bid items exist, the SHA's decision to award or reject a bid shall be supported by written justification. A bid found to be mathematically unbalanced, but not found to be materially unbalanced, may be awarded.

(e) When a low bid is determined to be both mathematically and materially unbalanced, the Division Administrator will take appropriate steps to protect the Federal interest. This action may be concurrence in a SHA decision not to award the contract. If, however, the SHA decides to proceed with the award and requests FHWA concurrence, the Division Administrator's action may range from nonconcurrence to concurrence with contingency conditions limiting Federal participation.

(f) If the SHA determines that the lowest bid is not responsive or the bidder is not responsible, it shall so notify and obtain the Division Administrator's concurrence before making an award to the next lowest bidder.

(g) If the SHA rejects or declines to read or consider a low bid on the grounds that it is not responsive because of noncompliance with a requirement which was not clearly identified in the bidding documents, it shall submit justification for its action. If such justification is not considered by the Division Administrator to be sufficient, concurrence will not be given to award to another bidder on the contract at the same letting.

(h) Any proposal by the SHA to reject all bids received for a Federal-aid contract shall be submitted to the Division Administrator for concurrence, accompanied by adequate justification.

(i) In the event the low bidder selected by the SHA for contract award forfeits the bid guarantee, the SHA may dispose of the amounts of such forfeited guarantees in accordance with its normal practices.

(j) A copy of the executed contract between the SHA and the construction contractor should be furnished to the Division Administrator as soon as practicable after execution.


§635.115   Agreement estimate.

(a) Following the award of contract, an agreement estimate based on the contract unit prices and estimated quantities shall be prepared by the SHA and submitted to the Division Administrator as soon as practicable for use in the preparation of the project agreement. The agreement estimate shall also include the actual or best estimated costs of any other items to be included in the project agreement.

(b) An agreement estimate shall be submitted by the SHA for each force account project (see 23 CFR part 635, subpart B) when the plans and specifications are submitted to the Division Administrator for approval. It shall normally be based on the estimated quantities and the unit prices agreed upon in advance between the SHA and the Division Administrator, whether the work is to be done by the SHA or by a local public agency. Such agreed unit prices shall constitute a commitment as the basis for Federal participation in the cost of the project. The unit prices shall be based upon the estimated actual cost of performing the work but shall in no case exceed unit prices currently being obtained by competitive bidding on comparable highway construction work in the same general locality. In special cases involving unusual circumstances, the estimate may be based upon the estimated costs for labor, materials, equipment rentals, and supervision to complete the work rather than upon agreed unit prices. This paragraph shall not be applicable to agreement estimates for railroad and utility force account work.


§635.116   Subcontracting and contractor responsibilities.

(a) Contracts for projects shall specify the minimum percentage of work that a contractor must perform with its own organization. This percentage shall be not less than 30 percent of the total original contract price excluding any identified specialty items. Specialty items may be performed by subcontract and the amount of any such specialty items so performed may be deducted from the total original contract before computing the amount of work required to be performed by the contractor's own organization. The contract amount upon which the above requirement is computed includes the cost of materials and manufactured products which are to be purchased or produced by the contractor under the contract provisions.

(b) The SHA shall not permit any of the contract work to be performed under a subcontract, unless such arrangement has been authorized by the SHA in writing. Prior to authorizing a subcontract, the SHA shall assure that each subcontract is evidenced in writing and that it contains all pertinent provisions and requirements of the prime contract. The Division Administrator may permit the SHA to satisfy the subcontract assurance requirements by concurrence in a SHA process which requires the contractor to certify that each subcontract arrangement will be in the form of a written agreement containing all the requirements and pertinent provisions of the prime contract. Prior to the Division Administrator's concurrence, the SHA must demonstrate that it has an acceptable plan for monitoring such certifications.

(c) To assure that all work (including subcontract work) is performed in accordance with the contract requirements, the contractor shall be required to furnish:

(1) A competent superintendent or supervisor who is employed by the firm, has full authority to direct performance of the work in accordance with the contract requirements, and is in charge of all construction operations (regardless of who performs the work), and;

(2) Such other of its own organizational resources (supervision, management, and engineering services) as the SHA contracting officer determines are necessary to assure the performance of the contract.


§635.117   Labor and employment.

(a) No construction work shall be performed by convict labor at the work site or within the limits of any Federal-aid highway construction project from the time of award of the contract or the start of work on force account until final acceptance of the work by the SHA unless it is labor performed by convicts who are on parole, supervised release, or probation.

(b) No procedures or requirement shall be imposed by any State which will operate to discriminate against the employment of labor from any other State, possession or territory of the United States, in the construction of a Federal-aid project.

(c) The selection of labor to be employed by the contractor on any Federal-aid project shall be by the contractor without regard to race, color, religion, sex, national origin, age, or handicap and in accordance with 23 CFR part 230, 41 CFR part 60 and Exec. Order No. 11246 (Sept. 24, 1965), 3 CFR 339 (1964-1965), as amended.

(d) Pursuant to 23 U.S.C. 140(d), it is permissible for SHA's to implement procedures or requirements which will extend preferential employment to Indians living on or near a reservation on eligible projects as defined in paragraph (e) of this section. Indian preference shall be applied without regard to tribal affiliation or place of enrollment. In no instance should a contractor be compelled to layoff or terminate a permanent core-crew employee to meet a preference goal.

(e) Projects eligible for Indian employment preference consideration are projects located on roads within or providing access to an Indian reservation or other Indian lands as defined under the term "Indian Reservation Roads" in 23 U.S.C. 101 and regulations issued thereunder. The terminus of a road "providing access to" is that point at which it intersects with a road functionally classified as a collector or higher classification (outside the reservation boundary) in both urban and rural areas. In the case of an Interstate highway, the terminus is the first interchange outside the reservation.

(f) The advertisement or call for bids on any contract for the construction of a project located on the Federal-aid system either shall include the minimum wage rates determined by the Secretary of Labor to be prevailing on the same type of work on similar construction in the immediate locality or shall provide that such rates are set out in the bidding documents and shall further specify that such rates are a part of the contract covering the project.


§635.118   Payroll and weekly statements.

For all projects, copies of payrolls and statements of wages paid, filed with the State as set forth in the required contract provisions for the project, are to be retained by the SHA for the time period pursuant to 49 CFR part 18 for review as needed by the Federal Highway Administration, the Department of Labor, the General Accounting Office, or other agencies.


§635.119   False statements.

The following notice shall be posted on each Federal-aid highway project in one or more places where it is readily available to and viewable by all personnel concerned with the project:

NOTICE TO ALL PERSONNEL ENGAGED ON FEDERAL-AID HIGHWAY PROJECTS

United States Code, title 18, section 1020, reads as follows:

Whoever, being an officer, agent, or employee of the United States, or of any State or Territory, or whoever, whether a person, association, firm, or corporation, knowingly makes any false statement, false representation, or false report as to the character, quality, quantity, or cost of the material used or to be used, or the quantity or quality of the work performed or to be performed, or the costs thereof in connection with the submission of plans, maps, specifications, contracts, or costs of construction of any highway or related project submitted for approval to the Secretary of Transportation; or

Whoever, knowingly makes any false statement, false representation, false report, or false claim with respect to the character, quality, quantity, or cost of any work performed or to be performed, or materials furnished or to be furnished, in connection with the construction of any highway or related project approved by the Secretary of Transportation; or

Whoever, knowingly makes any false statement or false representation as to a material fact in any statement, certificate, or report submitted pursuant to the provisions of the Federal-aid Road Act approved July 11, 1916 (39 Stat. 355), as amended and supplemented,

Shall be fined not more than $10,000 or imprisoned not more than five years, or both.


§635.120   Changes and extra work.

(a) Following authorization to proceed with a project, all major changes in the plans and contract provisions and all major extra work shall have formal approval by the Division Administrator in advance of their effective dates. However, when emergency or unusual conditions justify, the Division Administrator may give tentative advance approval orally to such changes or extra work and ratify such approval with formal approval as soon thereafter as practicable.

(b) For non-major changes and non-major extra work, formal approval is necessary but such approval may be given retroactively at the discretion of the Division Administrator. The SHA should establish and document with the Division Administrator's concurrence specific parameters as to what constitutes a non-major change and non-major extra work.

(c) Changes in contract time, as related to contract changes or extra work, should be submitted at the same time as the respective work change for approval by the Division Administrator.

(d) In establishing the method of payment for contract changes or extra work orders, force account procedures shall only be used when strictly necessary, such as when agreement cannot be reached with the contractor on the price of a new work item, or when the extent of work is unknown or is of such character that a price cannot be determined to a reasonable degree of accuracy. The reason or reasons for using force account procedures shall be documented.

(e) The SHA shall perform and adequately document a cost analysis of each negotiated contract change or negotiated extra work order. The method and degree of the cost analysis shall be subject to the approval of the Division Administrator.

(f) Proposed changes and extra work involved in nonparticipating operations that may affect the design or participating construction features of a project, shall be subject to review and concurrence by the Division Administrator.


§635.121   Contract time and contract time extensions.

(a) The SHA should have adequate written procedures for the determination of contract time. These procedures should be submitted for approval to the Division Administrator within 6 months of the effective date of this Final Rule.

(b) Contract time extensions granted by a SHA shall be subject to the concurrence of the Division Administrator and will be considered in determining the amount of Federal participation. Contract time extensions submitted for approval to the Division Administrator, shall be fully justified and adequately documented.


§635.122   Participation in progress payments.

(a) Federal funds will participate in the costs to the SHA of construction accomplished as the work progresses, based on a request for reimbursement submitted by State highway agencies. When the contract provisions provide for payment for stockpiled materials, the amount of the reimbursement request upon which participation is based may include the appropriate value of approved specification materials delivered by the contractor at the project site or at another designated location in the vicinity of such construction, provided that:

(1) The material conforms with the requirements of the plans and specifications.

(2) The material is supported by a paid invoice or a receipt for delivery of materials. If supported by a receipt of delivery of materials, the contractor must furnish the paid invoice within a reasonable time after receiving payment from the SHA; and

(3) The quantity of a stockpiled material eligible for Federal participation in any case shall not exceed the total estimated quantity required to complete the project. The value of the stockpiled material shall not exceed the appropriate portion of the value of the contract item or items in which such materials are to be incorporated.

(b) The materials may be stockpiled by the contractor at a location not in the vicinity of the project, if the SHA determines that because of required fabrication at an off-site location, it is not feasible or practicable to stockpile the materials in the vicinity of the project.


§635.123   Determination and documentation of pay quantities.

(a) The SHA shall have procedures in effect which will provide adequate assurance that the quantities of completed work are determined accurately and on a uniform basis throughout the State. All such determinations and all related source documents upon which payment is based shall be made a matter of record.

(b) Initial source documents pertaining to the determination of pay quantities are among those records and documents which must be retained pursuant to 49 CFR part 18.


§635.124   Participation in contract claim awards and settlements.

(a) The eligibility for and extent of Federal-aid participation up to the Federal statutory share in a contract claim award made by a State to a Federal-aid contractor on the basis of an arbitration or mediation proceeding, administrative board determination, court judgment, negotiated settlement, or other contract claim settlement shall be determined on a case-by-case basis. Federal funds will participate to the extent that any contract adjustments made are supported, and have a basis in terms of the contract and applicable State law, as fairly construed. Further, the basis for the adjustment and contractor compensation shall be in accord with prevailing principles of public contract law.

(b) The FHWA shall be made aware by the SHA of the details of the claim at an early stage so that coordination of efforts can be satisfactorily accomplished. It is expected that SHA's will diligently pursue the satisfactory resolution of claims within a reasonable period of time. Claims arising on projects handled on Certification Acceptance projects or on exempt non-NHS projects should be processed in accordance with the State's approved Certification Acceptance Plan or Stewardship Plan, as appropriate.

(c) When requesting Federal participation, the SHA shall set forth in writing the legal and contractual basis for the claim, together with the cost data and other facts supporting the award or settlement. Federal-aid participation in such instances shall be supported by a SHA audit of the actual costs incurred by the contractor unless waived by the FHWA as unwarranted. Where difficult, complex, or novel legal issues appear in the claim, such that evaluation of legal controversies is critical to consideration of the award or settlement, the SHA shall include in its submission a legal opinion from its counsel setting forth the basis for determining the extent of the liability under local law, with a level of detail commensurate with the magnitude and complexity of the issues involved.

(d) In those cases where the SHA receives an adverse decision in an amount more than the SHA was able to support prior to the decision or settles a claim in an amount more than the SHA can support, the FHWA will participate up to the appropriate Federal matching share, to the extent that it involves a Federal-aid participating portion of the contract, provided that:

(1) The FHWA was consulted and concurred in the proposed course of action;

(2) All appropriate courses of action had been considered; and

(3) The SHA pursued the case diligently and in a professional manner.

(e) Federal funds will not participate:

(1) If it has been determined that SHA employees, officers, or agents acted with gross negligence, or participated in intentional acts or omissions, fraud, or other acts not consistent with usual State practices in project design, plan preparation, contract administration, or other activities which gave rise to the claim;

(2) In such cost items as consequential or punitive damages, anticipated profit, or any award or payment of attorney's fees paid by a State to an opposing party in litigation; and

(3) In tort, inverse condemnation, or other claims erroneously styled as claims "under a contract."

(f) Payment of interest associated with a claim will be eligible for participation provided that the payment to the contractor for interest is allowable by State statute or specification and the costs are not a result of delays caused by dilatory action of the State or the contractor. The interest rates must not exceed the rate provided for by the State statute or specification.

(g) In cases where SHA's affirmatively recover compensatory damages through contract claims, cross-claims, or counter claims from contractors, subcontractors, or their agents on projects on which there was Federal-aid participation, the Federal share of such recovery shall be equivalent to the Federal share of the project or projects involved. Such recovery shall be credited to the project or projects from which the claim or claims arose.

[56 FR 37004, Aug. 2, 1991, as amended at 62 FR 6873, Feb. 14, 1997]



§635.125   Termination of contract.

(a) All contracts exceeding $10,000 shall contain suitable provisions for termination by the State, including the manner by which the termination will be effected and the basis for settlement. In addition, such contracts shall describe conditions under which the contract may be terminated for default as well as conditions where the contract may be terminated because of circumstances beyond the control of the contractor.

(b) The SHA prior to termination of a Federal-aid contract shall consult with and receive the concurrence of the Division Administrator. The extent of Federal-aid participation in contract termination costs, including final settlement, will depend upon the merits of the individual case. However, under no circumstances shall Federal funds participate in anticipated profit on work not performed.

(c) Except as provided for in paragraph (e) of this section, normal Federal-aid plans, specifications, and estimates, advertising, and award procedures are to be followed when a SHA awards the contract for completion of a terminated Federal-aid contract.

(d) When a SHA awards the contract for completion of a Federal-aid contract previously terminated for default, the construction amount eligible for Federal participation on the project should not exceed whichever amount is the lesser, either:

(1) The amount representing the payments made under the original contract plus payments made under the new contract; or

(2) The amount representing what the cost would have been if the construction had been completed as contemplated by the plans and specifications under the original contract.

(e) If the surety awards a contract for completion of a defaulted Federal-aid contract or completes it by some other acceptable means, the FHWA will consider the terms of the original contract to be in effect and that the work will be completed in accordance with the approved plans and specifications included therein. No further FHWA approval or concurrence action will therefore be needed in connection with any defaulted Federal-aid contract awarded by a surety. Under this procedure, the construction amount eligible for Federal participation on the project should not exceed the amount representing what the cost would have been if the construction had been completed as contemplated by the plans and specifications under the original contract.


§635.126   Record of materials, supplies, and labor.

(a) The provisions in this section are required to facilitate FHWA's efforts to compile data on Federal-aid contracts for the establishment of highway construction usage factors.

(b) On all Federal-aid construction contracts of $1 million or more for projects on the National Highway System, the SHA shall require the contractor:

(1) To become familiar with the list of specific materials and supplies including labor-hour and gross earning items contained in Form FHWA-47, "Statement of Materials and Labor Used by Contractors on Highway Construction Involving Federal Funds," prior to the commencement of work under this contract;

(2) To maintain a record of the total cost of all materials and supplies purchased for and incorporated in the work, and also of the quantities of those specific materials and supplies listed on Form FHWA-47, and in the units shown; and

(3) To furnish, upon the completion of the contract, to the SHA on Form FHWA-47 both the data required in paragraph (b)(2) of this section relative to materials and supplies and a final labor summary for all contract work indicating the total hours worked and the gross earnings.

(c) Upon receipt from the contractor, the SHA shall review the Form FHWA-47 for reasonableness and promptly transmit the form to the Division Administrator in accordance with the instructions printed in the form.

[56 FR 37004, Aug. 2, 1991, as amended at 62 FR 6873, Feb. 14, 1997]



§635.127   Agreement provisions regarding overruns in contract time.

(a) Each State highway agency (SHA) shall establish specific liquidated damages rates applicable to projects in that State. The rates may be project-specific or may be in the form of a table or schedule developed for a range of project costs and/or project types. These rates shall, as a minimum, be established to cover the estimated average daily construction engineering (CE) costs associated with the type of work encountered on the project. The amounts shall be assessed by means of deductions, for each calendar day or workday overrun in contract time, from payments otherwise due to the contractor for performance in accordance with the contract terms.

(b) The rates established shall be subject to FHWA approval either on a project-by-project basis, in the case of project-specific rates, or on a periodic basis after initial approval where a rate table or schedule is used. In the latter case, the SHA shall periodically review its cost data to ascertain if the rate table/schedule closely approximates, at a minimum, the actual average daily CE costs associated with the type and size of the projects in the State. Where rate schedules or other means are already included in the SHA specifications or standard special provisions, verification by the SHA that the amounts are adequate shall be submitted to the FHWA for review and approval. After initial approval by the FHWA of the rates, the SHA shall review the rates at least every 2 years and provide updated rates, when necessary, for FHWA approval. If updated rates are not warranted, justification of this fact is to be sent to the FHWA for review and acceptance.

(c) The SHA may, with FHWA concurrence, include additional amounts as liquidated damages in each contract to cover other anticipated costs of project related delays or inconveniences to the SHA or the public. Costs resulting from winter shutdowns, retaining detours for an extended time, additional demurrage, or similar costs as well as road user delay costs may be included.

(d) In addition to the liquidated damages provisions, the SHA may also include incentive/disincentive for early completion provisions in the contract. The incentive/disincentive amounts shall be shown separately from the liquidated damages amounts.

(e) Where there has been an overrun in contract time, the following principles shall apply in determining the cost of a project that is eligible for Federal-aid reimbursement:

(1) A proportional share, as used in this section, is the ratio of the final contract construction costs eligible for Federal participation to the final total contract construction costs of the project.

(2) Where CE costs are claimed as a participating item based upon actual expenses incurred or where CE costs are not claimed as a participating item, and where the liquidated damages rates cover only CE expenses, the total CE costs for the project shall be reduced by the assessed liquidated damages amounts prior to figuring any Federal pro rata share payable. If the amount of liquidated damages assessed is more than the actual CE totals for the project, a proportional share of the excess shall be deducted from the federally participating contract construction cost before determining the final Federal share.

(3) Where the SHA is being reimbursed for CE costs on the basis of an approved percentage of the participating construction cost, the total contract construction amount that would be eligible for Federal participation shall be reduced by a proportional share of the total liquidated damages amounts assessed on the project.

(4) Where liquidated damages include extra anticipated non-CE costs due to contractor caused delays, the amount assessed shall be used to pay for the actual non-CE expenses incurred by the SHA, and, if a Federal participating item(s) is involved, to reduce the Federal share payable for that item(s). If the amount assessed is more than the actual expenses incurred by the SHA, a proportional share of the excess shall be deducted from the federally participating contract construction cost of the project before the Federal share is figured.

(f) When provisions for incentive/disincentive for early completion are used in the contract, a proportion of the increased project costs due to any incentive payments to the contractor shall be added to the federally participating contract construction cost before calculating the Federal share. When the disincentive provision is applicable, a proportion of the amount assessed the contractor shall be deducted from the federally participating contract construction cost before the Federal share calculation. Proportions are to be calculated in the same manner as set forth in paragraph (e)(1) of this section.

[52 FR 31390, Aug. 20, 1987. Redesignated at 62 FR 6872, Feb. 14, 1997]


Subpart B -- Force Account Construction



§635.201   Purpose.

The purpose of this subpart is to prescribe procedures in accordance with 23 U.S.C. 112(b) for a State highway agency to request approval that highway construction work be performed by some method other than contract awarded by competitive bidding.

[48 FR 22912, May 23, 1983]



§635.202   Application.

This subpart applies to all Federal-aid and other highway construction projects financed in whole or in part with Federal funds and to be constructed by a State highway agency or a subdivision thereof in pursuant of agreements between any other State highway agency and the Federal Highway Administration (FHWA). This subpart does not apply to projects constructed under a Certification Acceptance Plan in those States where the Secretary has discharged his/her responsibility pursuant to 23 U.S.C. 117, except where employees of a political subdivision of a State are working on a project outside such political subdivision.

[48 FR 22912, May 23, 1983]



§635.203   Definitions.

The following definitions shall apply for the purpose of this subpart:

(a) A State highway agency is that department, commission, board, or official of any State charged by its laws with the responsibility for highway construction. The term State should be considered equivalent to State highway agency if the context so implies.

(b) Except as provided for as emergency repair work in §668.105(i) and in §635.204(b), the term some other method of construction as used in 23 U.S.C. 112(b) shall mean the force account method of construction as defined herein. In the unlikely event that circumstances are considered to justify a negotiated contract or another unusual method of construction, the policies and procedures prescribed herein for force account work will apply.

(c) The term force account shall mean the direct performance of highway construction work by a State highway agency, a county, a railroad, or a public utility company by use of labor, equipment, materials, and supplies furnished by them and used under their direct control.

(d) The term county shall mean any county, township, municipality or other political subdivision that may be empowered to cooperate with the State highway agency in highway matters.

(e) The term cost effective shall mean the efficient use of labor, equipment, materials and supplies to assure the lowest overall cost.

(f) For the purpose of this part, an emergency shall be deemed to exist when emergency repair work as provided for in §668.105(i) is necessary or when a major element or segment of the highway system has failed and the situation is such that competitive bidding is not possible or is impractical because immediate action is necessary to:

(1) Minimize the extent of the damage,

(2) Protect remaining facilities, or

(3) Restore essential travel.

This definition of emergency has no applicability to the Emergency Relief Program of 23 CFR part 668.

[39 FR 35158, Sept. 30, 1974, as amended at 48 FR 22912, May 23, 1983; 52 FR 45172, Nov. 25, 1987]



§635.204   Determination of more cost effective method or an emergency.

(a) Congress has expressly provided that the contract method based on competitive bidding shall be used by a State highway agency or county for performance of highway work financed with the aid of Federal funds unless the State highway agency demonstrates, to the satisfaction of the Secretary, that some other method is more cost effective or that an emergency exists.

(b) When a State highway agency determines it necessary due to an emergency to undertake a federally financed highway construction project by force account or negotiated contract method, it shall submit a request to the Division Administrator identifying and describing the project, the kinds of work to be performed, the method to be used, the estimated costs, the estimated Federal Funds to be provided, and the reason or reasons that an emergency exists.

(c) Except as provided in paragraph (b) of this section, when a State highway agency desires that highway construction work financed with the aid of Federal funds, other than the kinds of work designated under §635.205(b), be undertaken by force account, it shall submit a request to the Division Administrator identifying and describing the project and the kind of work to be performed, the estimated costs, the estimated Federal funds to be provided, and the reason or reasons that force account for such project is considered cost effective.

(d) The Division Administrator shall notify the State highway agency in writing of his/her determination.

[52 FR 45172, Nov. 25, 1987]



§635.205   Finding of cost effectiveness.

(a) It may be found cost effective for a State highway agency or county to undertake a federally financed highway construction project by force account when a situation exists in which the rights or resposibilities of the community at large are so affected as to require some special course of action, including situations where there is a lack of bids or the bids received are unreasonable.

(b) Pursuant to authority in 23 U.S.C. 112(b), it is hereby determined that by reason of the inherent nature of the operations involved, it is cost effective to perform by force account the adjustment of railroad or utility facilities and similar types of facilities owned or operated by a public agency, a railroad, or a utility company provided that the organization is qualified to perform the work in a satisfactory manner. The installation of new facilities shall be undertaken by competitive bidding except as provided in §635.204(c). Adjustment of railroad facilities shall include minor work on the railroad's operating facilities routinely performed by the railroad with its own forces such as the installation of grade crossing warning devices, crossing surfaces, and minor track and signal work. Adjustment of utility facilities shall include minor work on the utility's existing facilities routinely performed by the utility with its own forces and includes minor installations of new facilities to provide power, minor lighting, telephone, water and similar utility service to a rest area, weigh-station, movable bridge, or other highway appurtenance, provided such installation cannot feasibly be done as incidental to a major installation project such as an extensive highway lighting system.

[52 FR 45173, Nov. 25, 1987]


Subpart C -- Physical Construction Authorization


Source: 40 FR 17251, Apr. 18, 1975, unless otherwise noted.


§635.301   Purpose.

To prescribe the policies and procedures under which a State highway agency may be authorized to advance a Federal-aid highway project to the physical construction stage.


§635.303   Applicability.

The provisions of this subpart are applicable to all Federal-aid highway construction projects except projects constructed under an approved Certification Acceptance Plan.


§635.305   Physical construction.

For purposes of this subpart the physical construction of a project is considered to consist of the actual construction of the highway itself with its appurtenant facilities. It includes any removal, adjustment or demolition of buildings or major obstructions, and utility or railroad work that is a part of the contract for the physical construction.


§635.307   Coordination.

(a) The right-of-way clearance, utility, and railroad work are to be so coordinated with the physical construction that no unnecessary delay or cost for the physical construction will occur.

(b) All right-of-way clearance, utility, and railroad work performed separately from the contract for the physical construction of the project are to be accomplished in accordance with provisions of the following:

(1) 23 CFR part 140, subpart I;

(2) 23 CFR part 646, subpart B;

(3) 23 CFR 710.403; and

(4) 23 CFR part 645, subpart A.

[40 FR 17251, Apr. 18, 1975, as amended at 40 FR 25585, June 17, 1975; 64 FR 71289, Dec. 21, 1999]



§635.309   Authorization.

Authorization to advertise the physical construction for bids or to proceed with force account construction thereof shall normally be issued as soon as, but not until, all of the following conditions have been met:

(a) The plans, specifications, and estimates (PS&E) therefor have been approved.

(b) A statement is received from the State, either separately or combined with the information required by §635.309(c), that either all right-of-way clearance, utility, and railroad work has been completed or that all necessary arrangements have been made for it to be undertaken and completed as required for proper coordination with the physical construction schedules. Where it is determined that the completion of such work in advance of the highway construction is not feasible or practical due to economy, special operational problems and the like, there shall be appropriate notification provided in the bid proposals identifying the right-of-way clearance, utility, and railroad work which is to be underway concurrently with the highway construction.

(c) A statement is received from the State certifying that all individuals and families have been relocated to decent, safe and sanitary housing or the State has made available to relocatees adequate replacement housing in accordance with the provisions of the current Federal Highway Administration (FHWA) directive(s) covering the administration of the Highway Relocation Assistance Program and that one of the following has application:

(1) All necessary rights-of-way, including control of access rights when pertinent, have been acquired including legal and physical possession. Trial or appeal of cases may be pending in court but legal possession has been obtained. There may be some improvements remaining on the right-of-way but all occupants have vacated the lands and improvements and the State has physical possession and the right to remove, salvage, or demolish these improvements and enter on all land.

(2) Although all necessary rights-of-way have not been fully acquired, the right to occupy and to use all rights-of-way required for the proper execution of the project has been acquired. Trial or appeal of some parcels may be pending in court and on other parcels full legal possession has not been obtained but right of entry has been obtained, the occupants of all lands and improvements have vacated and the State has physical possession and right to remove, salvage, or demolish these improvements.

(3) The acquisition or right of occupancy and use of a few remaining parcels is not complete, but all occupants of the residences on such parcels have had replacement housing made available to them in accordance with 49 CFR 24.204. The State may request authorization on this basis only in very unusual circumstances. This exception must never become the rule. Under these circumstances, advertisement for bids or force-account work may be authorized if FHWA finds that it will be in the public interest. The physical construction may then also proceed, but the State shall ensure that occupants of residences, businesses, farms, or non-profit organizations who have not yet moved from the right-of-way are protected against unnecessary inconvenience and disproportionate injury or any action coercive in nature. When the State requests authorization to advertise for bids and to proceed with physical construction where acquisition or right of occupancy and use of a few parcels has not been obtained, full explanation and reasons therefor including identification of each such parcel will be set forth in the State's request along with a realistic date when physical occupancy and use is anticipated as well as substantiation that such date is realistic. Appropriate notification shall be provided in the bid proposals identifying all locations where right of occupancy and use has not been obtained.

(d) The State highway agency in accord with 23 CFR 771.111(h), has submitted public hearing transcripts, certifications and reports pursuant to 23 U.S.C. 128.

(e) An affirmative finding of cost effectiveness or that an emergency exists has been made as required by 23 U.S.C. 112, when construction by some method other than contract based on competitive bidding is contemplated.

(f) Minimum wage rates determined by the Department of Labor in accordance with the provisions of 23 U.S.C. 113, are in effect and will not expire before the end of the period within which it can reasonably be expected that the contract will be awarded.

(g) A statement has been received that right-of-way has been acquired or will be acquired in accordance with the current FHWA directive(s) covering the acquisition of real property or that acquisition of right-of-way is not required.

(h) A statement has been received that the steps relative to relocation advisory assistance and payments as required by the current FHWA directive(s) covering the administration of the Highway Relocation Assistance Program have been taken, or that they are not required.

(i) The FHWA Division Administrator has determined that appropriate measures have been included in the PS&E in keeping with approved guidelines, for minimizing possible soil erosion and water pollution as a result of highway construction operations.

(j) The FHWA Division Administrator has determined that requirements of 23 CFR part 771 have been fulfilled and appropriate measures have been included in the PS&E to ensure that conditions and commitments made in the development of the project to mitigate environmental harm will be met.

(k) Where utility facilities are to use and occupy the right-of-way, the State has demonstrated to the satisfaction of the FHWA Division Administrator that the provisions of 23 CFR 645.119(b) have been fulfilled.

(l) The FHWA Division Administrator has verified the fact that adequate replacement housing is in place and has been made available to all affected persons.

(m) Where applicable, areawide agency review has been accomplished as required by 42 U.S.C. 3334 and 4231 through 4233.

(n) The FHWA Division Administrator has determined that the PS&E provide for the erection of only those information signs and traffic control devices that conform to the standards developed by the Secretary of Transportation or mandates of Federal law and do not include promotional or other informational signs regarding such matters as identification of public officials, contractors, organizational affiliations, and related logos and symbols.

(o) The FHWA Division Administrator has determined that, where applicable, provisions are included in the PS&E that require the erection of funding source signs, for the life of the construction project, in accordance with section 154 of the Surface Transportation and Uniform Relocation Assistance Act of 1987.

[40 FR 17251, Apr. 18, 1975; 40 FR 36319, Aug. 20, 1975, as amended at 47 FR 47239, Oct. 25, 1982; 49 FR 28550, July 13, 1984; 50 FR 34093, Aug. 23, 1985; 52 FR 32669, Aug. 28, 1987; 52 FR 45173, Nov. 25, 1987; 53 FR 1921, Jan. 25, 1988; 54 FR 47075, Nov. 9, 1989]


Subpart D -- General Material Requirements


Source: 41 FR 36204, Aug. 27, 1976, unless otherwise noted.


§635.401   Purpose.

The purpose of this subpart is to prescribe requirements and procedures relating to product and material selection and use on Federal-aid highway projects.


§635.403   Definitions.

As used in this subpart, the following terms have the meanings indicated:

(a) FHWA Division Administrator means the chief Federal Highway Administration (FHWA) official assigned to conduct business in a particular State;

(b) Material means any tangible substance incorporated into a Federal-aid highway project;

(c) PS&E means plans, specifications, and estimates;

(d) Special provisions means additions and revisions to the standard and supplemental specifications applicable to an individual project;

(e) Standard specifications means a compilation in book form of specifications approved for general application and repetitive use;

(f) State has the meaning set forth in 23 U.S.C. 101;

(g) State highway agency means that department, commission, board, or official of any State charged by its laws with the responsibility for highway construction;

(h) Supplemental specifications means approved additions and revisions to the standard specifications.


§635.405   Applicability.

The requirements and procedures prescribed in this subpart apply to all contracts relating to Federal-aid highway projects, except those constructed under a Certification Acceptance Plan.


§635.407   Use of materials made available by a public agency.

(a) Contracts for highway projects shall require the contractor to furnish all materials to be incorporated in the work and shall permit the contractor to select the sources from which the materials are to be obtained. Exception to this requirement may be made when there is a definite finding by the State highway agency and concurred in by the FHWA Division Administrator, that it is in the public interest to require the contractor to use material furnished by the State highway agency or from sources designated by the State highway agency. In cases such as this, the FHWA does not expect mutual sharing of costs unless the State highway agency receives a related credit from another agency or political subdivision of the State. Where such a credit does accrue to the State highway agency, it shall be applied to the Federal-aid project involved. The designation of a mandatory material source may be permitted based on environmental considerations, provided the environment would be substantially enhanced without excessive cost. Otherwise, if a State highway agency proposal to designate a material source for mandatory use would result in higher project costs, Federal-aid funds shall not participate in the increase even if the designation would conserve other public funds.

(b) The provisions of paragraph (a) of this section will not preclude the designation in the plans and specifications of sources of local natural materials, such as borrow aggregates, that have been investigated by the State highway agency and found to contain materials meeting specification requirements. The use of materials from such designated sources shall not be mandatory unless there is a finding of public interest as stated in paragraph (a) of this section.

(c) Federal funds may participate in the cost of specifications materials made available by a public agency when they have been actually incorporated in accepted items of work, or in the cost of such materials meeting the criteria and stockpiled at the locations specified in §635.114 of this chapter.

(d) To be eligible for Federal participation in its cost, any material, other than local natural materials, to be purchased by the State highway agency and furnished to the contractor for mandatory use in the project, must have been acquired on the basis of competitive bidding, except when there is a finding of public interest justifying the use of another method of acquisition. The location and unit price at which such material will be available to the contractor must be stated in the special provisions for the benefit of all prospective bidders. The unit cost eligible for Federation participation will be limited to the unit cost of such material to the State highway agency.

(e) When the State highway agency or another public agency owns or has control over the source of a local natural material the unit price at which such material will be made available to the contractor must be stated in the plans or special provisions. Federal participation will be limited to (1) the cost of the material to the State highway agency or other public agency; or (2) the fair and reasonable value of the material, whichever is less. Special cases may arise that will justify Federal participation on a basis other than that set forth above. Such cases should be fully documented and receive advance approval by the FHWA Division Administrator.

(f) Costs incurred by the State highway agency or other public agency for acquiring a designated source or the right to take materials from it will not be eligible for Federal participation if the source is not used by the contractor.

(g) The contract provisions for one or a combination of Federal-aid projects shall not specify a mandatory site for the disposal of surplus excavated materials unless there is a finding by the State highway agency with the concurrence of the FHWA Division Administrator that such placement is the most economical except that the designation of a mandatory site may be permitted based on environmental considerations, provided the environment would be substantially enhanced without excessive cost.


§635.409   Restrictions upon materials.

No requirement shall be imposed and no procedure shall be enforced by any State highway agency in connection with a project which may operate:

(a) To require the use of or provide a price differential in favor of articles or materials produced within the State, or otherwise to prohibit, restrict or discriminate against the use of articles or materials shipped from or prepared, made or produced in any State, territory or possession of the United States; or

(b) To prohibit, restrict or otherwise discriminate against the use of articles or materials of foreign origin to any greater extent than is permissible under policies of the Department of Transportation as evidenced by requirements and procedures prescribed by the FHWA Administrator to carry out such policies.


§635.410   Buy America requirements.

(a) The provisions of this section shall prevail and be given precedence over any requirements of this subpart which are contrary to this section. However, nothing in this section shall be construed to be contrary to the requirements of §635.409(a) of this subpart.

(b) No Federal-aid highway construction project is to be authorized for advertisement or otherwise authorized to proceed unless at least one of the following requirements is met:

(1) The project either: (i) Includes no permanently incorporated steel or iron materials, or (ii) if steel or iron materials are to be used, all manufacturing processes, including application of a coating, for these materials must occur in the United States. Coating includes all processes which protect or enhance the value of the material to which the coating is applied.

(2) The State has standard contract provisions that require the use of domestic materials and products, including steel and iron materials, to the same or greater extent as the provisions set forth in this section.

(3) The State elects to include alternate bid provisions for foreign and domestic steel and iron materials which comply with the following requirements. Any procedure for obtaining alternate bids based on furnishing foreign steel and iron materials which is acceptable to the Division Administrator may be used. The contract provisions must (i) require all bidders to submit a bid based on furnishing domestic steel and iron materials, and (ii) clearly state that the contract will be awarded to the bidder who submits the lowest total bid based on furnishing domestic steel and iron materials unless such total bid exceeds the lowest total bid based on furnishing foreign steel and iron materials by more than 25 percent.

(4) When steel and iron materials are used in a project, the requirements of this section do not prevent a minimal use of foreign steel and iron materials, if the cost of such materials used does not exceed one-tenth of one percent (0.1 percent) of the total contract cost or $2,500, whichever is greater. For purposes of this paragraph, the cost is that shown to be the value of the steel and iron products as they are delivered to the project.

(c)(1) A State may request a waiver of the provisions of this section if;

(i) The application of those provisions would be inconsistent with the public interest; or

(ii) Steel and iron materials/products are not produced in the United States in sufficient and reasonably available quantities which are of a satisfactory quality.

(2) A request for waiver, accompanied by supporting information, must be submitted in writing to the Regional Federal Highway Administrator (RFHWA) through the FHWA Division Administrator. A request must be submitted sufficiently in advance of the need for the waiver in order to allow time for proper review and action on the request. The RFHWA will have approval authority on the request.

(3) Requests for waivers may be made for specific projects, or for certain materials or products in specific geographic areas, or for combinations of both, depending on the circumstances.

(4) The denial of the request by the RFHWA may be appealed by the State to the Federal Highway Administrator (Administrator), whose action on the request shall be considered administratively final.

(5) A request for a waiver which involves nationwide public interest or availability issues or more than one FHWA region may be submitted by the RFHWA to the Administrator for action.

(6) A request for waiver and an appeal from a denial of a request must include facts and justification to support the granting of the waiver. The FHWA response to a request or appeal will be in writing and made available to the public upon request. Any request for a nationwide waiver and FHWA's action on such a request may be published in the FEDERAL REGISTER for public comment.

(7) In determining whether the waivers described in paragraph (c)(1) of this section will be granted, the FHWA will consider all appropriate factors including, but not limited to, cost, administrative burden, and delay that would be imposed if the provision were not waived.

(d) Standard State and Federal-aid contract procedures may be used to assure compliance with the requirements of this section.

[48 FR 53104, Nov. 25, 1983, as amended at 49 FR 18821, May 3, 1984; 58 FR 38975, July 21, 1993]


Editorial Note: For a waiver document affecting §635.410, see 60 FR 15478, Mar. 24, 1995.


§635.411   Material or product selection.

(a) Federal funds shall not participate, directly or indirectly, in payment for any premium or royalty on any patented or proprietary material, specification, or process specifically set forth in the plans and specifications for a project, unless:

(1) Such patented or proprietary item is purchased or obtained through competitive bidding with equally suitable unpatented items; or

(2) The State highway agency certifies either that such patented or proprietary item is essential for synchronization with existing highway facilities, or that no equally suitable alternate exists; or

(3) Such patented or proprietary item is used for research or for a distinctive type of construction on relatively short sections of road for experimental purposes.

(b) When there is available for purchase more than one nonpatented, nonproprietary material, semifinished or finished article or product that will fulfill the requirements for an item of work of a project and these available materials or products are judged to be of satisfactory quality and equally acceptable on the basis of engineering analysis and the anticipated prices for the related item(s) of work are estimated to be approximately the same, the PS&E for the project shall either contain or include by reference the specifications for each such material or product that is considered acceptable for incorporation in the work. If the State highway agency wishes to substitute some other acceptable material or product for the material or product designated by the successful bidder or bid as the lowest alternate, and such substitution results in an increase in costs, there will not be Federal-aid participation in any increase in costs.

(c) A State highway agency may require a specific material or product when there are other acceptable materials and products, when such specific choice is approved by the Division Administrator as being in the public interest. When the Division Administrator's approval is not obtained, the item will be nonparticipating unless bidding procedures are used that establish the unit price of each acceptable alternative. In this case Federal-aid participation will be based on the lowest price so established.

(d) Appendix A sets forth the FHWA requirements regarding (1) the specification of alternative types of culvert pipes, and (2) the number and types of such alternatives which must be set forth in the specifications for various types of drainage installations.

(e) Reference in specifications and on plans to single trade name materials will not be approved on Federal-aid contracts.


§635.413   Warranty clauses.

The SHA may include warranty provisions in National Highway System (NHS) construction contracts in accordance with the following:

(a) Warranty provisions shall be for a specific construction product or feature. Items of maintenance not eligible for Federal participation shall not be covered.

(b) All warranty requirements and subsequent revisions shall be submitted to the Division Administrator for advance approval.

(c) No warranty requirement shall be approved which, in the judgment of the Division Administrator, may place an undue obligation on the contractor for items over which the contractor has no control.

(d) A SHA may follow its own procedures regarding the inclusion of warranty provisions in non-NHS Federal-aid contracts.

[60 FR 44274, Aug. 25, 1995]



§635.417   Convict produced materials.

(a) Materials produced after July 1, 1991, by convict labor may only be incorporated in a Federal-aid highway construction project if such materials have been:

(1) Produced by convicts who are on parole, supervised release, or probation from a prison or

(2) Produced in a qualified prison facility and the cumulative annual production amount of such materials for use in Federal-aid highway construction does not exceed the amount of such materials produced in such facility for use in Federal-aid highway construction during the 12-month period ending July 1, 1987.

(b) Qualified prison facility means any prison facility in which convicts, during the 12-month period ending July 1, 1987, produced materials for use in Federal-aid highway construction projects.

[53 FR 1923, Jan. 25, 1988, as amended at 58 FR 38975, July 21, 1993]




Appendix A to Subpart D of Part 635 -- Summary of Acceptable Criteria for Specifying Types of Culvert Pipes

--------------------------------------------------------------------------------------------------------------------------------------------------------
          Alternatives required         AASHTO designations
Type of drainage installation  ---------------------------------------------------- to be included with    Application       Remarks
     Yes       No       Number       alternatives
--------------------------------------------------------------------------------------------------------------------------------------------------------
Cross drains under high-type    ............. X............ .................... .................... Statewide........... Any AASHTO-approved
pavement.\1\                                                            material.\2\
Other cross-drain installations... X............ ............. 3 minimum........... M-170 and M-190..... ......do............   Do.\2\
Side-drain installations.......... X............ ............. ......do............ M-36................ ......do............   Do.\2\
Special installation conditions... ............. X............ .................... .................... Individual      Specified to meet
                                        installation.     special condi-
                                                   tions.
Special drainage systems (storm   ............. X............ .................... .................... ......do............ Specified to meet
sewers, inverted siphons, etc.).                                                  site require-ments.
--------------------------------------------------------------------------------------------------------------------------------------------------------
\1\High-type pavement is generally described as FHWA construction type codes I, J, K, L, and plant mix and penetration macadam segments, respectively
shown in the right-hand columns of type codes G and H having a combined thickness of surface and base of 7 in or more (or equivalent) or that are
constructed on rigid bases.
\2\Types not included in currently approved AASHTO specifications may be specified if recommended by the State with adequate justification and approved
by FHWA.

Subpart E -- Interstate Maintenance Guidelines


Source: 45 FR 20793, Mar. 31, 1980, unless otherwise noted.


§635.501   Purpose.

To prescribe Interstate maintenance guidelines and establish the policy and procedures to insure that the condition of Interstate routes is maintained at the level required by the purposes for which they were designed.


§635.503   Policy.

The policy of the FHWA is to insure that each State highway agency develops and implements an Interstate maintenance program conforming to the guidelines in this subpart. The maintenance program shall be consistent with practices deemed necessary to adequately provide for motorist safety, preservation of the highways, rideability, and aesthetics.


§635.505   Maintenance guidelines.

(a) The following critical elements should serve to direct the development and implementation of an Interstate maintenance program in each State.

(1) Roadway surfaces. Preservation of the structural integrity of the roadway and the safety and comfort of the user. This includes a safe, smooth, skid-resistant surface, as close as practical to the original, or subsequently improved, grade and cross section.

(2) Shoulders. Preservation of a safe, smooth surface which is free of obstruction, contiguous with the adjacent roadway surface, and as close as practical to the original, or subsequently improved, grade and cross section.

(3) Roadside. Preservation of the roadside in a safe, pleasant, and forgiving manner through vegetation management, erosion control, and litter pick-up.

(4) Drainage. Preservation of hydraulic capacity for which originally designed.

(5) Bridges and tunnels. Preservation of the structural and operational characteristics for which originally designed. These include safe, smooth, skid-resistant surfaces; proper surface drainage; and adequate functioning bearing devices and substructural elements. Replacement or repair of structural railing and approach guardrail should be done without unreasonable delay. Tunnels should be cleaned, properly lighted, and adequately ventilated.

(6) Snow and ice control. Preservation of the roadway safety, efficiency, and environment during winter driving conditions.

(7) Traffic control devices. Preservation of clean, legible, visible, and properly functioning traffic control devices. This includes pavement markings, signing, delineators, signals, etc.

(8) Safety appurtenances. Replacement of damaged, defective, and/or inoperable devices without unreasonable delay. This includes guardrails, impact attenuators, breakaway supports, barriers, etc.

(9) Safety rest areas. Preservation and operation of facilities reasonably necessary for the convenience, relaxation, and informational needs of the user.

(10) Access control. Preservation of the originally designed access control, elimination of unauthorized traffic movement, and prevention of improper or unauthorized use of the highway rights-of-way.

(11) Traffic safety in maintenance and utility work zones. Procedures that will aid the safety of motorists and maintenance workers. The procedures shall be consistent with the provisions of 23 CFR part 630, subpart J, and part VI of the Manual on Uniform Traffic Control Devices. 1

1Available for purchase from the Superintendent of Documents, U.S. Government Printing Office, Washington, DC 20402 (GPO Stock Number 050-001-81001-8), and for inspection and copying as prescribed in 49 CFR 7, app. D.

(b) All replacements and repairs should conform to the currently approved design standards (23 CFR part 625) for all critical elements listed in paragraph (a) of this section. Exceptions for minor repairs must be clearly defined in a State's maintenance program.

(c) These guidelines shall be interpreted to expect that repairs and maintenance will be performed without unreasonable delay, that variations from the State's approved program will be allowed in situations involving emergency or unforeseeability, and that the State will seek to attain a high level of maintenance.


§635.507   Implementation.

(a) Each State highway agency shall prepare an initial program submission which shall include a description of the State's Interstate maintenance program; a discussion of the method by which the State manages its program, including copies of operating documents; and a general description of the level of resources and activity the State intends to devote to attain the objectives stated under each of the critical elements in §635.505(a). This initial submission shall be made to the FHWA no later than 120 days after the effective date of this subpart. The FHWA shall review each State's initial program submission for conformance with the provisions of this subpart and approve or disapprove the submission on the basis of that review.

(b) Within one year after the effective date of this subpart, and by January 1 of each subsequent year, each State highway agency shall certify to the FHWA that it has an Interstate maintenance program as required by this subpart and that its Interstate routes are being maintained in accordance with that program.

(c) Beginning in 1981 and each year thereafter, each State highway agency shall update its initial program submission by providing the FHWA with a discussion of:

(1) The condition of the State's Interstate routes and deficiencies,

(2) State maintenance priorities,

(3) The State maintenance budget, and

(4) Exceptions and/or revisions to the initial submission.

(d) The FHWA shall review each State's annual submission for conformance with the provisions of this subpart and monitor the implementation of each State's program in accordance with the review procedures described in the FHWA Maintenance Review Manual 2 and the Federal-Aid Highway Program Manual, volume 6, chapter 4, section 3, subsection 1. 3 If differences between the State and the FHWA cannot be resolved concerning the adequacy of the Interstate maintenance program's level of resources and activity, the FHWA shall initiate action under §635.509.

2, 3Available for inspection and copying as prescribed in 49 CFR part 7, appendix D.


§635.509   Deficient or unsatisfactory maintenance.

(a) Fund reduction. If a State fails to certify as required by this subpart, or if the Secretary determines that a State is not adequately maintaining its Interstate routes in accordance with a maintenance program as required by this subpart, the Federal-aid highway funds apportioned to the State for the next fiscal year (after the date on which the State must certify) shall be reduced by an amount equal to 10 percent of the amount which would otherwise be apportioned to the State under 23 U.S.C. 104. In addition, future project approvals may be withheld by the Secretary under 23 U.S.C. 116.

(b) Procedure for reduction of funds. (1) If it appears to the Federal Highway Administrator that a State has not submitted a certification conforming to the requirements of this subpart, or that a State is not adequately maintaining its Interstate routes in accordance with a maintenance program as required by this subpart, the Administrator shall make in writing a proposed determination of nonconformity, and shall notify the Governor of the State of the proposed determination by certified mail. The notice shall state the reasons for the proposed determination and inform the State that it may within 30 days from the date of the letter request a hearing to show cause why it should not be found in nonconformity. If the State informs the Administrator before the end of the 30-day period that it wishes to attempt to resolve the matter informally, the Administrator may extend the time for requesting a hearing by an additional 30 days. In the event of a request for informal resolution, the State and the Administrator (or designees) shall promptly schedule a meeting to resolve the matter.

(2) If a State does not request a hearing in a timely fashion as provided in paragraph (b)(1) of this section, the Administrator shall forward the proposed determination to the Secretary. Upon approval by the Secretary, the provisions of paragraph (a) of this section shall take effect immediately.

(3) If a State requests a hearing, the Secretary shall expeditiously convene a hearing on the record, which shall be conducted according to the provisions of the Administrative Procedure Act, 5 U.S.C. 551 et seq. Based on the record of the proceeding, the Secretary shall determine whether the State is in nonconformity with this subpart. If the Secretary determines that the State is in nonconformity, the provisions of paragraph (a) of this section shall take effect immediately.

(4) The Secretary may reduce 10 percent of a State's apportionment of funds under 23 U.S.C. 104 prior to the administrative determination under this section in order to prevent the apportionment to the State of funds which would be affected by a determination of nonconformity.

(5) Funds withheld pursuant to a final administrative determination under this section shall be reapportioned to all other eligible States one year from the date of this determination, unless before this time the Secretary determines, on the basis of information submitted by the State and the FHWA, that the State has come into conformity with this section. If the Secretary determines that the State has come into conformity, the withheld funds shall be released to the State.

(6) The reapportionment of funds under paragraph (b)(5) of this section shall be stayed during the pendency of any proceeding for judicial review of a final administrative determination of nonconformity made by the Secretary.




PART 637 -- CONSTRUCTION INSPECTION AND APPROVAL



Subpart A [Reserved]


Subpart B -- Quality Assurance Procedures for Construction


   Sec.
637.201   Purpose.
637.203   Definitions.
637.205   Policy.
637.207   Quality assurance program.
637.209   Laboratory and sampling and testing personnel qualifications.
Appendix A to Subpart B -- Guide Letter of Certification by State Engineer

Authority: 23 U.S.C. 109, 114, and 315; 49 CFR 1.48(b).

Source: 60 FR 33717, June 29, 1995, unless otherwise noted.



Subpart A [Reserved]

Subpart B -- Quality Assurance Procedures for Construction



§637.201   Purpose.

To prescribe policies, procedures, and guidelines to assure the quality of materials and construction in all Federal-aid highway projects on the National Highway System.


§637.203   Definitions.

Acceptance program. All factors that comprise the State highway agency's (SHA) determination of the quality of the product as specified in the contract requirements. These factors include verification sampling, testing, and inspection and may include results of quality control sampling and testing.

Independent assurance program. Activities that are an unbiased and independent evaluation of all the sampling and testing procedures used in the acceptance program. Test procedures used in the acceptance program which are performed in the SHA's central laboratory would not be covered by an independent assurance program.

Proficiency samples. Homogeneous samples that are distributed and tested by two or more laboratories. The test results are compared to assure that the laboratories are obtaining the same results.

Qualified laboratories. Laboratories that are capable as defined by appropriate programs established by each SHA. As a minimum, the qualification program shall include provisions for checking test equipment and the laboratory shall keep records of calibration checks.

Qualified sampling and testing personnel. Personnel who are capable as defined by appropriate programs established by each SHA.

Quality assurance. All those planned and systematic actions necessary to provide confidence that a product or service will satisfy given requirements for quality.

Quality control. All contractor/vendor operational techniques and activities that are performed or conducted to fulfill the contract requirements.

Random sample. A sample drawn from a lot in which each increment in the lot has an equal probability of being chosen.

Vendor. A supplier of project-produced material that is not the contractor.

Verification sampling and testing. Sampling and testing performed to validate the quality of the product.


§637.205   Policy.

(a) Quality assurance program. Each SHA shall develop a quality assurance program which will assure that the materials and workmanship incorporated into each Federal-aid highway construction project on the NHS are in conformity with the requirements of the approved plans and specifications, including approved changes. The program must meet the criteria in §637.207 and be approved by the FHWA.

(b) SHA capabilities. The SHA shall maintain an adequate, qualified staff to administer its quality assurance program. The State shall also maintain a central laboratory. The State's central laboratory shall meet the requirements in §637.209(a)(2).

(c) Independent assurance program. Independent assurance samples and tests or other procedures shall be performed by qualified sampling and testing personnel employed by the SHA or its designated agent.

(d) Verification sampling and testing. The verification sampling and testing are to be performed by qualified testing personnel employed by the SHA or its designated agent, excluding the contractor and vendor.

(e) Random samples. All samples used for quality control and verification sampling and testing shall be random samples.


§637.207   Quality assurance program.

(a) Each SHA's quality assurance program shall provide for an acceptance program and an independent assurance (IA) program consisting of the following:

(1) Acceptance program.

(i) Each SHA's acceptance program shall consist of the following:

(A) Frequency guide schedules for verification sampling and testing which will give general guidance to personnel responsible for the program and allow adaptation to specific project conditions and needs.

(B) Identification of the specific location in the construction or production operation at which verification sampling and testing is to be accomplished.

(C) Identification of the specific attributes to be inspected which reflect the quality of the finished product.

(ii) Quality control sampling and testing results may be used as part of the acceptance decision provided that:

(A) The sampling and testing has been performed by qualified laboratories and qualified sampling and testing personnel.

(B) The quality of the material has been validated by the verification sampling and testing. The verification testing shall be performed on samples that are taken independently of the quality control samples.

(C) The quality control sampling and testing is evaluated by an IA program.

(iii) If the results from the quality control sampling and testing are used in the acceptance program, the SHA shall establish a dispute resolution system. The dispute resolution system shall address the resolution of discrepancies occurring between the verification sampling and testing and the quality control sampling and testing. The dispute resolution system may be administered entirely within the SHA.

(2) The IA program shall evaluate the qualified sampling and testing personnel and the testing equipment. The program shall cover sampling procedures, testing procedures, and testing equipment. Each IA program shall include a schedule of frequency for IA evaluation. The schedule may be established based on either a project basis or a system basis. The frequency can be based on either a unit of production or on a unit of time.

(i) The testing equipment shall be evaluated by using one or more of the following: Calibration checks, split samples, or proficiency samples.

(ii) Testing personnel shall be evaluated by observations and split samples or proficiency samples.

(iii) A prompt comparison and documentation shall be made of test results obtained by the tester being evaluated and the IA tester. The SHA shall develop guidelines including tolerance limits for the comparison of test results.

(iv) If the SHA uses the system approach to the IA program, the SHA shall provide an annual report to the FHWA summarizing the results of the IA program.

(3) The preparation of a materials certification, conforming in substance to Appendix A of this subpart, shall be submitted to the FHWA Division Administrator for each construction project which is subject to FHWA construction oversight activities.

(b) [Reserved]


§637.209   Laboratory and sampling and testing personnel qualifications.

(a) Laboratories.

(1) After June 29, 2000, all contractor, vendor, and SHA testing used in the acceptance decision shall be performed by qualified laboratories.

(2) After June 30, 1997, each SHA shall have its central laboratory accredited by the AASHTO Accreditation Program or a comparable laboratory accreditation program approved by the FHWA.

(3) After June 29, 2000, any non-SHA designated laboratory which performs IA sampling and testing shall be accredited in the testing to be performed by the AASHTO Accreditation Program or a comparable laboratory accreditation program approved by the FHWA.

(4) After June 29, 2000, any non-SHA laboratory that is used in dispute resolution sampling and testing shall be accredited in the testing to be performed by the AASHTO Accreditation Program or a comparable laboratory accreditation program approved by the FHWA.

(b) Sampling and testing personnel. After June 29, 2000, all sampling and testing data to be used in the acceptance decision or the IA program shall be executed by qualified sampling and testing personnel.

(c) Conflict of interest. In order to avoid an appearance of a conflict of interest, any qualified non-SHA laboratory shall perform only one of the following types of testing on the same project: Verification testing, quality control testing, IA testing, or dispute resolution testing.

Appendix A to Subpart B -- Guide Letter of Certification by State Engineer Date_____ Project No._____

This is to certify that:

The results of the tests used in the acceptance program indicate that the materials incorporated in the construction work, and the construction operations controlled by sampling and testing, were in conformity with the approved plans and specifications. (The following sentence should be added if the IA testing frequencies are based on project quantities. All independent assurance samples and tests are within tolerance limits of the samples and tests that are used in the acceptance program.)

Exceptions to the plans and specifications are explained on the back hereof (or on attached sheet). _____

Director of SHA Laboratory or other appropriate SHA Official.




PART 640 -- CERTIFICATION ACCEPTANCE


Sec.
640.101   Purpose.
640.103   Definitions.
640.105   Effect of certification acceptance.
640.107   Coverage.
640.109   Requirements for certification acceptance.
640.111   Content of State certification.
640.113   Procedures.
640.115   Evaluations.
640.117   Rescission of State certification.

Authority: 23 U.S.C. 101(e), 117, and 315; 49 CFR 1.48(b).

Source: 60 FR 47483, Sept. 13, 1995, unless otherwise noted.


§640.101   Purpose.

The purpose of this part is to provide instructions for preparation and acceptance of State certification proposals to accomplish the policies and objectives of title 23, U.S.C., using State laws, regulations, directives, and standards. Also covered are procedures for administering projects under certification acceptance and evaluating State performance.


§640.103   Definitions.

Unless otherwise specified in this part, the definitions in 23 U.S.C. 101(a) are applicable to this part. As used in this part:

Certification acceptance (CA) means the alternative procedure authorized by 23 U.S.C. 117(a) for administering Federal-aid highway projects not on the Interstate System.

State certification means a written statement prepared by a State highway/transportation agency setting forth the laws, regulations, directives, and standards it will use, or cause to be used, in the administration of certain highway projects.

State highway/transportation agency has the same meaning as that given for State highway department in 23 U.S.C. 101.


§640.105   Effect of certification acceptance.

(a) Acceptance of a State certification permits a State to discharge certain responsibilities otherwise assigned to the Secretary under title 23, U.S.C., for Federal-aid highway projects. A State may permit performance and project certification by capable local governments.

(b) Acceptance of a State certification does not constitute a commitment or obligation of Federal funds.

(c) Acceptance of a State certification does not preclude FHWA access to and review of a Federal-aid project at any time.

(d) Certification acceptance as an alternative procedure does not replace the fundamental provisions of law in title 23, U.S.C., with respect to the basic structure of the Federal-aid highway program. Acceptance of a CA proposal does not preclude application of any provision of title 23, U.S.C., that may be advantageous to the State.

(e) Nothing in this part shall affect or discharge any responsibility or obligation of the FHWA under any Federal law other than title 23, U.S.C.


§640.107   Coverage.

(a) Certification acceptance may apply to Federal-aid highway projects except projects on the Interstate System. If other FHWA regulations and title 23, U.S.C., allow, projects not on a Federal-aid highway may be administered under the provisions of an accepted State certification.

(b) The CA procedure shall not apply to transportation planning and research (23 U.S.C. 134, 135, and 307), highway safety (chapter 4, title 23, U.S.C.), or those public transportation projects not administered by FHWA under title 23, U.S.C.

(c) A State certification may provide for either full or partial coverage of the Federal-aid highway projects, programs, phases of work, and classes of projects.


§640.109   Requirements for certification acceptance.

(a) Acceptance of either a full or partial coverage State certification as described in §640.107(c) will be based upon:

(1) A State request and identification of the State laws, regulations, directives, and standards that either separately or collectively will accomplish the policies and objectives contained in or issued pursuant to title 23, U.S.C., and

(2) An FHWA finding that the State highway/transportation agency has the capability to carry out project responsibilities in accordance with such State requirements. The FHWA finding will be based on previous process reviews and evaluations conducted as part of FHWA's oversight of Federal-aid programs and an FHWA evaluation of the State's performance and resources. If information from process reviews and that available from previous evaluations are considered to be insufficient to form a reasonable judgment, they may be supplemented by additional reviews and inquiries of the State agency.

(b) A State certification may be accepted in whole or in part, depending on FHWA findings. Where minor deficiencies are found, acceptance may be conditioned or may exclude the affected State operations until the deficiencies are corrected. Where deficiencies are found which are of such magnitude as to create doubt that the policies and objectives of title 23, U.S.C., would be accomplished, the State certification will not be accepted until the deficiencies are corrected.


§640.111   Content of State certification.

(a) The State certification will include the following:

(1) The name of the State highway/transportation agency and the legal authority which permits such agency to accomplish the policies and objectives contained in or issued pursuant to title 23, U.S.C.;

(2) A statement of the programs, phases of work, and classes of projects or combinations thereof that the State is including in the certification being submitted for acceptance;

(3) For submissions providing full or partial coverage of projects as provided in §640.107(c), a listing of the title 23, U.S.C., policies and objectives and citation of State laws, regulations, directives, and standards that will be applied. Any policies and objectives that are not applicable due to partial coverage may be omitted; and

(4) A description of the State's methods for assuring local government knowledge of and compliance with State and Federal requirements where they will perform services on projects administered under CA.

(b) Existing assurances and formal agreements between the State and the FHWA with respect to equal employment opportunity, current billing, and control of outdoor advertising will continue in full force and effect and may be incorporated by reference. Likewise, the State's procedures accepted under 23 U.S.C. 109(h) may be incorporated by reference.

(c) State certifications are to be signed by the chief official of the State highway/transportation agency and submitted to the FHWA Division Administrator.


§640.113   Procedures.

(a) Authorization by the FHWA to proceed with work on a CA project will be in response to a written request from the State highway/transportation agency.

(b) If the State finds that exceptions to CA procedures or standards are appropriate on a project, the State will justify and document such decisions.

(c) A project agreement, or modification to a project agreement, will be executed as required by 23 CFR Part 630, subpart C, Project Agreements.

(d) The FHWA may accept projects based on inspections of a type and frequency necessary to ensure the projects are completed in accordance with appropriate standards. The State is to notify the FHWA when a project is complete and/or ready for such inspection and will certify that the plans, design, and construction for the project were in accord with the laws, regulations, directives, and standards contained in the State certification or such project exceptions as were approved by the State.

(e) Revisions or amendments to State certifications will be made when necessary and processed as provided in §640.111(c). The existing State certification is to be reviewed periodically to determine its adequacy in light of this part, the statutes in effect at the time of the review, and the operational reviews made by FHWA.

[60 FR 47483, Sept. 13, 1995, as amended at 61 FR 57331, Nov. 6, 1996]



§640.115   Evaluations.

(a) The FHWA may conduct periodic evaluations, as deemed appropriate, of the State's operations under CA. These evaluations may include coverage of any or all areas of the State's administration of CA projects.

(b) If a failure to comply with Federal or State laws occurs and the State is unable or unwilling to effect corrective action of the deficiency, an evaluation report, including recommendations, will be prepared by the FHWA as a basis for considering whether acceptance of the State certification should be rescinded under §640.117.


§640.117   Rescission of State certification.

The acceptance of a State certification may be rescinded at any time upon request of the State or if considered necessary by the FHWA to protect the Federal interest. The rescission may be applied to all or part of the programs or projects covered in the State certification.




PART 645 -- UTILITIES



Subpart A -- Utility Relocations, Adjustments, and Reimbursement


   Sec.
645.101   Purpose.
645.103   Applicability.
645.105   Definitions.
645.107   Eligibility.
645.109   Preliminary engineering.
645.111   Right-of-way.
645.113   Agreements and authorizations.
645.115   Construction.
645.117   Cost development and reimbursement.
645.119   Alternate procedure.

Subpart B -- Accommodation of Utilities

645.201   Purpose.
645.203   Applicability.
645.205   Policy.
645.207   Definitions.
645.209   General requirements.
645.211   State transportation department accommodation policies.
645.213   Use and occupancy agreements (permits).
645.215   Approvals.

Authority: 23 U.S.C. 101, 109, 111, 116, 123, and 315; 23 CFR 1.23 and 1.27; 49 CFR 1.48(b); and E.O. 11990, 42 26961 (May 24, 1977).

Editorial Note: Nomenclature changes to part 645 appear at 65 FR 70311, Nov. 22, 2000.

Subpart A -- Utility Relocations, Adjustments, and Reimbursement


Source: 50 FR 20345, May 15, 1985, unless otherwise noted.


§645.101   Purpose.

To prescribe the policies, procedures, and reimbursement provisions for the adjustment and relocation of utility facilities on Federal-aid and direct Federal projects.


§645.103   Applicability.

(a) The provisions of this regulation apply to reimbursement claimed by a State transportation department (STD) for costs incurred under an approved and properly executed transportation department (TD)/utility agreement and for payment of costs incurred under all Federal Highway Administration (FHWA)/utility agreements.

(b) Procedures on the accommodation of utilities are set forth in 23 CFR part 645, subpart B, Accommodation of Utilities.

(c) When the lines or facilities to be relocated or adjusted due to highway construction are privately owned, located on the owner's land, devoted exclusively to private use and not directly or indirectly serving the public, the provisions of the FHWA's right-of-way procedures in 23 CFR 710.203, apply. When applicable, under the foregoing conditions, the provisions of this regulation may be used as a guide to establish a cost-to-cure.

(d) The FHWA's reimbursement to the STD will be governed by State law (or State regulation) or the provisions of this regulation, whichever is more restrictive. When State law or regulation differs from this regulation, a determination shall be made by the STD subject to the concurrence of the FHWA as to which standards will govern, and the record documented accordingly, for each relocation encountered.

(e) For direct Federal projects, all references herein to the STD or TD are inapplicable, and it is intended that the FHWA be considered in the relative position of the STD or TD.

[50 FR 20345, May 15, 1985, as amended at 64 FR 71289, Dec. 21, 1999]



§645.105   Definitions.

For the purposes of this regulation, the following definitions shall apply:

Authorization -- for Federal-aid projects authorization to the STD by the FHWA, or for direct Federal projects authorization to the utility by the FHWA, to proceed with any phase of a project. The date of authorization establishes the date of eligibility for Federal funds to participate in the costs incurred on that phase of work.

Betterment -- any upgrading of the facility being relocated that is not attributable to the highway construction and is made solely for the benefit of and at the election of the utility.

Cost of relocation -- the entire amount paid by or on behalf of the utility properly attributable to the relocation after deducting from that amount any increase in value of the new facility, and any salvage derived from the old facility.

Cost of Removal -- the amount expended to remove utility property including the cost of demolishing, dismantling, removing, transporting, or otherwise disposing of utility property and of cleaning up to leave the site in a neat and presentable condition.

Cost of salvage -- the amount expended to restore salvaged utility property to usable condition after its removal.

Direct Federal projects -- highway projects such as projects under the Federal Lands Highways Program which are under the direct administration of the FHWA.

Indirect or overhead costs -- those costs which are not readily identifiable with one specific task, job, or work order. Such costs may include indirect labor, social security taxes, insurance, stores expense, and general office expenses. Costs of this nature generally are distributed or allocated to the applicable job or work orders, other accounts and other functions to which they relate. Distribution and allocation is made on a uniform basis which is reasonable, equitable, and in accordance with generally accepted cost accounting practices.

Relocation -- the adjustment of utility facilities required by the highway project. It includes removing and reinstalling the facility, including necessary temporary facilities, acquiring necessary right-of-way on the new location, moving, rearranging or changing the type of existing facilities and taking any necessary safety and protective measures. It shall also mean constructing a replacement facility that is both functionally equivalent to the existing facility and necessary for continuous operation of the utility service, the project economy, or sequence of highway construction.

Salvage value -- the amount received from the sale of utility property that has been removed or the amount at which the recovered material is charged to the utility's accounts, if retained for reuse.

State transportation department -- the transportation department of one of the 50 States, the District of Columbia, or Puerto Rico.

Transportation department(TD) -- that department, commission, board, or official of any State or political subdivison thereof, charged by its law with the responsibility for highway administration.

Use and occupancy agreement -- the document (written agreement or permit) by which the TD approves the use and occupancy of highway right-of-way by utility facilities or private lines.

Utility -- a privately, publicly, or cooperatively owned line, facility or system for producing, transmitting, or distributing communications, cable television, power, electricity, light, heat, gas, oil, crude products, water, steam, waste, storm water not connected with highway drainage, or any other similar commodity, including any fire or police signal system or street lighting system, which directly or indirectly serves the public. The term utility shall also mean the utility company inclusive of any wholly owned or controlled subsidiary.

Work order system -- a procedure for accumulating and recording into separate accounts of a utility all costs to the utility in connection with any change in its system or plant.

[50 FR 20345, May 15, 1985, as amended at 65 FR 70311, Nov. 22, 2000]



§645.107   Eligibility.

(a) When requested by the STD, Federal funds may participate, subject to the provisions of §645.103(d) of this part and at the pro rata share applicable, in an amount actually paid by an TD for the costs of utility relocations. Federal funds may participate in safety corrective measures made under the provisions of §645.107(k) of this part. Federal funds may also participate for relocations necessitated by the actual construction of highway project made under one or more of the following conditions when:

(1) The STD certifies that the utility has the right of occupancy in its existing location because it holds the fee, an easement, or other real property interest, the damaging or taking of which is compensable in eminent domain,

(2) The utility occupies privately or publicly owned land, including public road or street right-of-way, and the STD certifies that the payment by the TD is made pursuant to a law authorizing such payment in conformance with the provisions of 23 U.S.C. 123, and/or

(3) The utility occupies publicy owned land, including public road and street right-of-way, and is owned by a public agency or political subdivision of the State, and is not required by law or agreement to move at its own expense, and the STD certifies that the TD has the legal authority or obligation to make such payments.

(b) On projects which the STD has the authority to participate in project costs, Federal funds may not participate in payments made by a political subdivision for relocation of utility facilities, other than those proposed under the provisions of §645.107(k) of this part, when State law prohibits the STD from making payment for relocation of utility facilities.

(c) On projects which the STD does not have the authority to participate in project costs, Federal funds may participate in payments made by a political subdivision for relocation of utility facilities necessitated by the actual construction of a highway project when the STD certifies that such payment is based upon the provisions of §645.107(a) of this part and does not violate the terms of a use and occupancy agreement, or legal contract, between the utility and the TD or for utility safety corrective measures under the provisions of §645.107(k) of this part.

(d) Federal funds are not eligible to participate in any costs for which the utility contributes or repays the TD, except for utilities owned by the political subdivision on projects which qualify under the provisions of §645.107(c) of this part in which case the costs of the utility are considered to be costs of the TD.

(e) The FHWA may deny Federal fund participation in any payments made by a TD for the relocation of utility facilities when such payments do not constitute a suitable basis for Federal fund participation under the provisions of title 23 U.S.C.

(f) The rights of any public agency or political subdivision of a State under contract, franchise, or other instrument or agreement with the utility, pertaining to the utility's use and occupancy of publicly owned land, including public road and street right-of-way, shall be considered the rights of the STD in the absence of State law to the contrary.

(g) In lieu of the individual certifications required by §645.107(a) and (c), the STD may file a statement with the FHWA setting forth the conditions under which the STD will make payments for the relocation of utility facilities. The FHWA may approve Federal fund participation in utility relocations proposed by the STD under the conditions of the statement when the FHWA has made an affirmative finding that such statement and conditions form a suitable basis for Federal fund participation under the provisions of 23 U.S.C. 123.

(h) Federal funds may not participate in the cost of relocations of utility facilities made solely for the benefit or convenience of a utility, its contractor, or a highway contractor.

(i) When the advance installation of new utility facilities crossing or otherwise occupying the proposed right-of-way of a planned highway project is underway, or scheduled to be underway, prior to the time such right-of-way is purchased by or under control of the TD, arrangements should be made for such facilities to be installed in a manner that will meet the requirements of the planned highway project. Federal funds are eligible to participate in the additional cost incurred by the utility that are attributable to, and in accommodation of, the highway project provided such costs are incurred subsequent to authorization of the work by the FHWA. Subject to the other provisions of this regulation, Federal participation may be approved under the foregoing circumstances when it is demonstrated that the action taken is necessary to protect the public interest and the adjustment of the facility is necessary by reason of the actual construction of the highway project.

(j) Federal funds are eligible to participate in the costs of preliminary engineering and allied services for utilities, the acquisition of replacement right-of-way for utilities, and the physical construction work associated with utility relocations. Such costs must be incurred by or on behalf of a utility after the date the work is included in an approved program and after the FHWA has authorized the STD to proceed in accordance with 23 CFR part 630, subpart A, Federal-Aid Programs Approval and Project Authorization.

(k) Federal funds may participate in projects solely for the purpose of implementing safety corrective measures to reduce the roadside hazards of utility facilities to the highway user. Safety corrective measures should be developed in accordance with the provisions of 23 CFR 645.209(k). (Information collection requirements in paragraph (g) were approved by the Office of Management and Budget under control number 2125-0515)

[50 FR 20345, May 15, 1985, as amended at 53 FR 24932, July 1, 1988]



§645.109   Preliminary engineering.

(a) As mutually agreed to by the TD and utility, and subject to the provisions of paragraph (b) of this section, preliminary engineering activities associated with utility relocation work may be done by:

(1) The TD's or utility's engineering forces;

(2) An engineering consultant selected by the TD, after consultation with the utility, the contract to be administered by the TD; or,

(3) An engineering consultant selected by the utility, with the approval of the TD, the contract to be administered by the utility.

(b) When a utility is not adequately staffed to pursue the necessary preliminary engineering and related work for the utility relocation, Federal funds may participate in the amount paid to engineers, architects, and others for required engineering and allied services provided such amounts are not based on a percentage of the cost of relocation. When Federal participation is requested by the STD in the cost of such services, the utility and its consultant shall agree in writing as to the services to be provided and the fees and arrangements for the services. Federal funds may participate in the cost of such services performed under existing written continuing contracts when it is demonstrated that such work is performed regularly for the utility in its own work and that the costs are reasonable.

(c) The procedures in 23 CFR part 172, Administration of Engineering and Design Related Service Contracts, may be used as a guide for reviewing proposed consultant contracts.

[50 FR 20345, May 15, 1985, as amended at 60 FR 34850, July 5, 1995; 65 FR 70311, Nov. 22, 2000]



§645.111   Right-of-way.

(a) Federal participation may be approved for the cost of replacement right-of-way provided:

(1) The utility has the right of occupancy in its existing location beause it holds the fee, an easement, or another real property interest, the damaging or taking of which is compensable in eminent domain, or the acquisition is made in the interest of project economy or is necessary to meet the requirements of the highway project, and

(2) There will be no charge to the project for that portion of the utility's existing right-of-way being transferred to the TD for highway purposes.

(b) The utility shall determine and make a written valuation of the replacement right-of-way that it acquires in order to justify amounts paid for such right-of-way. This written valuation shall be accomplished prior to negotiation for acquisition.

(c) Acquisition of replacement right-of-way by the TD on behalf of a utility or acquisition of nonoperating real property from a utility shall be in accordance with the Uniform Relocation Assistance and Real Property Acquisition Policies Act of 1970 (42 U.S.C. 4601 et seq.) and applicable right-of-way procedures in 23 CFR 710.203.

(d) When the utility has the right-of-occupancy in its existing location because it holds the fee, an easement, or another real property interest, and it is not necessary by reason of the highway construction to adjust or replace the facilities located thereon, the taking of and damage to the utility's real property, including the disposal or removal of such facilities, may be considered a right-of-way transaction in accordance with provisions of the applicable right-of-way procedures in 23 CFR 710.203.

[50 FR 20345, May 15, 1985, as amended at 64 FR 71289, Dec. 21, 1999]



§645.113   Agreements and authorizations.

(a) On Federal-aid and direct Federal projects involving utility relocations, the utility and the TD shall agree in writing on their separate responsibilities for financing and accomplishing the relocation work. When Federal participation is requested, the agreement shall incorporate this regulation by reference and designate the method to be used for performing the work (by contract or force account) and for developing relocation costs. The method proposed by the utility for developing relocation costs must be acceptable to both the TD and the FHWA. The preferred method for the development of relocation costs by a utility is on the basis of actual direct and related indirect costs accumulated in accordance with a work order accounting procedure prescribed by the applicable Federal or State regulatory body.

(b) When applicable, the written agreement shall specify the terms and amounts of any contribution or repayments made or to be made by the utility to the TD in connection with payments by the TD to the utility under the provisions of §645.107 of this regulation.

(c) The agreement shall be supported by plans, specifications when required, and itemized cost estimates of the work agreed upon, including appropriate credits to the project, and shall be sufficiently informative and complete to provide the TD and the FHWA with a clear description of the work required.

(d) When the relocation involves both work to be done at the TD's expense and work to be done at the expense of the utility, the written agreement shall state the share to be borne by each party.

(e) In the event there are changes in the scope of work, extra work or major changes in the planned work covered by the approved agreement, plans, and estimates, Federal participation shall be limited to costs covered by a modification of the agreement, a written change, or extra work order approved by the TD and the FHWA.

(f) When proposed utility relocation and adjustment work on a project for a specific utility company can be clearly defined and the cost can be accurately estimated, the FHWA may approve an agreement between the TD and the utility company for a lump-sum payment without later confirmation by audit of actual costs.

(g) Except as otherwise provided by §645.113(h), authorization by the FHWA to the STD to proceed with the physical relocation of a utility's facilities may be given after:

(1) The utility relocation work, or the right-of-way, or physical construction phase of the highway construction work is included in an approved Statewide transportation improvement program,

(2) The appropriate environmental evaluation and public hearing procedures required by 23 CFR part 771, Environmental Impact and Related Procedures, have been satisfied.

(3) The FHWA has reviewed and approved the plans, estimates, and proposed or executed agreements for the utility work and is furnished a schedule for accomplishing the work.

(h) The FHWA may authorize the physical relocation of utility facilities before the requirements of §645.113(g)(2) are satisfied when the relocation or adjustment of utility facilities meets the requirements of §645.107(i) of this regulation.

(i) Whenever the FHWA has authorized right-of-way acquisition under the hardship and protective buying provisions of 23 CFR 710.503, the FHWA may authorize the physical relocation of utility facilities located in whole or in part on such right-of-way.

(j) When all efforts by the TD and utility fail to bring about written agreement of their separate responsibilities under the provisions of this regulation, the STD shall submit its proposal and a full report of the circumstances to the FHWA. Conditional authorizations for the relocation work to proceed may be given by the FHWA to the STD with the understanding that Federal funds will not be paid for work done by the utility until the STD proposal has been approved by the FHWA.

(k) The FHWA will consider for approval any special procedure under State law, or appropriate administrative or judicial order, or under blanket master agreements with the utilities, that will fully accomplish all of the foregoing objectives and accelerate the advancement of the construction and completion of projects.

[50 FR 20345, May 15, 1985, as amended at 60 FR 34850, July 5, 1995; 64 FR 71289, Dec. 21, 1999; 65 FR 70311, Nov. 22, 2000]



§645.115   Construction.

(a) Part 635, subpart B, of this title, Force Account Construction (justification required for force account work), states that it is cost-effective for certain utility adjustments to be performed by a utility with its own forces and equipment, provided the utility is qualified to perform the work in a satisfactory manner. This cost-effectiveness finding covers minor work on the utility's existing facilities routinely performed by the utility with its own forces. When the utility is not adequately staffed and equipped to perform such work with its own forces and equipment at a time convenient to and in coordination with the associated highway construction, such work may be done by:

(1) A contract awarded by the TD or utility to the lowest qualified bidder based on appropriate solicitation,

(2) Inclusion as part of the TD's highway construction contract let by the TD as agreed to by the utility,

(3) An existing continuing contract, provided the costs are reasonable, or

(4) A contract for low-cost incidental work, such as tree trimming and the like, awarded by the TD or utility without competitive bidding, provided the costs are reasonable.

(b) When it has been determined under part 635, subpart B, that the force account method is not the most cost-effective means for accomplishing the utility adjustment, such work is to be done under competitive bid contracts as described in §645.115(a) (1) and (2) or under an existing continuing contract provided it can be demonstrated this is the most cost-effective method.

(c) Costs for labor, materials, equipment, and other services furnished by the utility shall be billed by the utility directly to the TD. The special provisions of contracts let by the utility or the TD shall be explicit in this respect. The costs of force account work performed for the utility by the TD and of contract work performed for the utility under a contract let by the TD shall be reported separately from the costs of other force account and contract items on the highway project.


§645.117   Cost development and reimbursement.

(a) Developing and recording costs. (1) All utility relocation costs shall be recorded by means of work orders in accordance with an approved work order system except when another method of developing and recording costs, such as lump-sum agreement, has been approved by the TD and the FHWA. Except for work done under contracts, the individual and total costs properly reported and recorded in the utility's accounts in accordance with the approved method for developing such costs, or the lump-sum agreement, shall constitute the maximum amount on which Federal participation may be based.

(2) Each utility shall keep its work order system or other approved accounting procedure in such a manner as to show the nature of each addition to or retirement from a facility, the total costs thereof, and the source or sources of cost. Separate work orders may be issued for additions and retirements. Retirements, however, may be included with the construction work order provided that all items relating to retirements shall be kept separately from those relating to construction.

(3) The STD may develop, or work in concert with utility companies to develop, other acceptable costing methods, such as unit costs, to estimate and reimburse utility relocation expenditures. Such other methods shall be founded in generally accepted industry practices and be reasonably supported by recent actual expenditures. Unit costs should be developed periodically and supported annually by a maintained data base of relocation expenses. Development of any alternate costing method should consider the factors listed in paragraphs (b) through (g) of this section. Streamlining of the cost development and reimbursement procedures is encouraged so long as adequate accountability for Federal expenditures is maintained. Concurrence by the FHWA is required for any costing method used other than actual cost.

(b) Direct labor costs. (1) Salaries and wages, at actual or average rates, and related expenses paid by the utility to individuals for the time worked on the project are reimbursable when supported by adequate records. This includes labor associated with preliminary engineering, construction engineering, right-of-way, and force account construction.

(2) Salaries and expenses paid to individuals who are normally part of the overhead organization of the utility may be reimbursed for the time worked directly on the project when supported by adequate records and when the work performed by such individuals is essential to the project and could not have been accomplished as economically by employees outside the overhead organization.

(3) Amounts paid to engineers, architects and others for services directly related to projects may be reimbursed.

(c) Labor surcharges. (1) Labor surcharges include worker compensation insurance, public liability and property damage insurance, and such fringe benefits as the utility has established for the benefit of its employees. The cost of labor surcharges will be reimbursed at actual cost to the utility, or, at the option of the utility, average rates which are representative of actual costs may be used in lieu of actual costs if approved by the STD and the FHWA. These average rates should be adjusted at least once annually to take into account known anticipated changes and correction for any over or under applied costs for the preceding period.

(2) When the utility is a self-insurer, there may be reimbursement at experience rates properly developed from actual costs. The rates cannot exceed the rates of a regular insurance company for the class of employment covered.

(d) Overhead and indirect construction costs. (1) Overhead and indirect construction costs not charged directly to work order or construction accounts may be allocated to the relocation provided the allocation is made on an equitable basis. All costs included in the allocation shall be eligible for Federal reimbursement, reasonable, actually incurred by the utility, and consistent with the provisions of 48 CFR part 31.

(2) Costs not eligible for Federal reimbursement include, but are not limited to, the costs associated with advertising, sales promotion, interest on borrowings, the issuance of stock, bad debts, uncollectible accounts receivable, contributions, donations, entertainment, fines, penalties, lobbying, and research programs.

(3) The records supporting the entries for overhead and indirect construction costs shall show the total amount, rate, and allocation basis for each additive, and are subject to audit by representatives of the State and Federal Government.

(e) Material and supply costs. (1) Materials and supplies, if available, are to be furnished from company stock except that they may be obtained from other sources near the project site when available at a lower cost. When not available from company stock, they may be purchased either under competitive bids or existing continuing contracts under which the lowest available prices are developed. Minor quantities of materials and supplies and proprietary products routinely used in the utility's operation and essential for the maintenance of system compatibility may be excluded from these requirements. The utility shall not be required to change its existing standards for materials used in permanent changes to its facilities. Costs shall be determined as follows:

(i) Materials and supplies furnished from company stock shall be billed at the current stock prices for such new or used materials at time of issue.

(ii) Materials and supplies not furnished from company stock shall be billed at actual costs to the utility delivered to the project site.

(iii) A reasonable cost for plant inspection and testing may be included in the costs of materials and supplies when such expense has been incurred. The computation of actual costs of materials and supplies shall include the deduction of all offered discounts, rebates, and allowances.

(iv) The cost of rehabilitating rather than replacing existing utility facilities to meet the requirements of a project is reimbursable, provided this cost does not exceed replacement costs.

(2) Materials recovered from temporary use and accepted for reuse by the utility shall be credited to the project at prices charged to the job, less a considertion for loss in service life at 10 percent. Materials recovered from the permanent facility of the utility that are accepted by the utility for return to stock shall be credited to the project at the current stock prices of such used materials. Materials recovered and not accepted for reuse by the utility, if determined to have a net sale value, shall be sold to the highest bidder by the TD or utility following an opportunity for TD inspection and appropriate solicitation for bids. If the utility practices a system of periodic disposal by sale, credit to the project shall be at the going prices supported by records of the utility.

(3) Federal participation may be approved for the total cost of removal when either such removal is required by the highway construction or the existing facilities cannot be abandoned in place for aesthetic or safety reasons. When the utility facilities can be abandoned in place but the utility or highway constructor elects to remove and recover the materials, Federal funds shall not participate in removal costs which exceed the value of the materials recovered.

(4) The actual and direct costs of handling and loading materials and supplies at company stores or material yards, and of unloading and handling recovered materials accepted by the utility at its stores or material yards are reimbursable. In lieu of actual costs, average rates which are representative of actual costs may be used if approved by the STD and the FHWA. These average rates should be adjusted at least once annually to take into account known anticipated changes and correction for any over or under applied costs for the preceding period. At the option of the utility, 5 percent of the amounts billed for the materials and supplies issued from company stores and material yards or the value of recovered materials will be reimbursed in lieu of actual or average costs for handling.

(f) Equipment costs. The average or actual costs of operation, minor maintenance, and depreciation of utility-owned equipment may be reimbursed. Reimbursement for utility-owned vehicles may be made at average or actual costs. When utility-owned equipment is not available, reimbursement will be limited to the amount of rental paid (1) to the lowest qualified bidder, (2) under existing continuing contracts at reasonable costs, or (3) as an exception by negotiation when paragraph (f) (1) and (2) of this section are impractical due to project location or schedule.

(g) Transportation costs. (1) The utility's cost, consistent with its overall policy, of necessary employee transportation and subsistence directly attributable to the project is reimbursable.

(2) Reasonable cost for the movement of materials, supplies, and equipment to the project and necessary return to storage including the associated cost of loading and unloading equipment is reimbursable.

(h) Credits. (1) Credit to the highway project will be required for the cost of any betterments to the facility being replaced or adjusted, and for the salvage value of the materials removed.

(2) Credit to the highway project will be required for the accrued depreciation of a utility facility being replaced, such as a building, pumping station, filtration plant, power plant, substation, or any other similar operational unit. Such accrued depreciation is that amount based on the ratio between the period of actual length of service and total life expectancy applied to the original cost. Credit for accrued depreciation shall not be required for a segment of the utility's service, distribution, or transmission lines.

(3) No betterment credit is required for additions or improvements which are:

(i) Required by the highway project,

(ii) Replacement devices or materials that are of equivalent standards although not identical,

(iii) Replacement of devices or materials no longer regularly manufactured with next highest grade or size,

(iv) Required by law under governmental and appropriate regulatory commission code, or

(v) Required by current design practices regularly followed by the company in its own work, and there is a direct benefit to the highway project.

(4) When the facilities, including equipment and operating facilities, described in §645.117(h)(2) are not being replaced, but are being rehabilitated and/or moved, as necessitated by the highway project, no credit for accrued depreciation is needed.

(5) In no event will the total of all credits required under the provisions of this regulation exceed the total costs of adjustment exclusive of the cost of additions or improvements necessitated by the highway construction.

(i) Billings. (1) After the executed TD/utility agreement has been approved by the FHWA, the utility may be reimbursed through the STD by progress billings for costs incurred. Cost for materials stockpiled at the project site or specifically purchased and delivered to the utility for use on the project may also be reimbursed on progress billings following approval of the executed TD/utility agreement.

(2) The utility shall provide one final and complete billing of all costs incurred, or of the agreed-to lump-sum, within one year following completion of the utility relocation work, otherwise previous payments to the utility may be considered final, except as agreed to between the STD and the utility. Billings received from utilities more than one year following completion of the utility relocation work may be paid if the STD so desires, and Federal-aid highway funds may participate in these payments.

(3) All utility cost records and accounts relating to the project are subject to audit by representatives of the State and Federal Government for a period of 3 years from the date final payment has been received by the utility. (Information collection requirements in paragraph (i) were approved by the Office of Management and Budget under control number 2125-0159)

[50 FR 20345, May 15, 1985, as amended at 60 FR 34850, July 5, 1995; 65 FR 70311, Nov. 22, 2000]



§645.119   Alternate procedure.

(a) This alternate procedure is provided to simplify the processing of utility relocations or adjustments under the provisions of this regulation. Under this procedure, except as otherwise provided in paragraph (b) of this section, the STD is to act in the relative position of the FHWA for reviewing and approving the arrangements, fees, estimates, plans, agreements, and other related matters required by this regulation as prerequisites for authorizing the utility to proceed with and complete the work.

(b) The scope of the STD's approval authority under the alternate procedure includes all actions necessary to advance and complete all types of utility work under the provisions of this regulation except in the following instances:

(1) Utility relocations and adjustments involving major transfer, production, and storage facilities such as generating plants, power feed stations, pumping stations and reservoirs.

(2) Utility relocations falling within the scope of §645.113 (h), (i), and (j), and §645.107(i) of this regulation.

(c) To adopt the alternate procedure, the STD must file a formal application for approval by the FHWA. The application must include the following:

(1) The STD's written policies and procedures for administering and processing Federal-aid utility adjustments. Those policies and procedures must make adequate provisions with respect to the following:

(i) Compliance with the requirements of this regulation, except as otherwise provided by §645.119(b), and the provisions of 23 CFR part 645, subpart B, Accommodation of Utilities.

(ii) Advance utility liaison, planning, and coordination measures for providing adequate lead time and early scheduling of utility relocation to minimize interference with the planned highway construction.

(iii) Appropriate administrative, legal, and engineering review and coordination procedures as needed to establish the legal basis of the TD's payment; the extent of eligibility of the work under State and Federal laws and regulations; the more restrictive payment standards under §645.103(d) of this regulation; the necessity of the proposed utility work and its compatibility with proposed highway improvements; and the uniform treatment of all utility matters and actions, consistent with sound management practices.

(iv) Documentation of actions taken in compliance with STD policies and the provisions of this regulation, shall be retained by the STD.

(2) A statement signed by the chief administrative officer of the STD certifying that:

(i) Federal-aid utility relocations will be processed in accordance with the applicable provisions of this regulation, and the STD's utility policies and procedures submitted under §645.119(c)(1).

(ii) Reimbursement will be requested only for those costs properly attributable to the proposed highway construction and eligible for participation under the provisions of this regulation.

(d) The STD's application and any changes to it will be submitted to the FHWA for review and approval.

(e) After the alternate procedure has been approved, the FHWA may authorize the STD to proceed with utility relocation on a project in accordance with the certification, subject to the following conditions:

(1) The utility work must be included in an approved program.

(2) The STD must submit a request in writing for such authorization. The request shall include a list of the utility relocations to be processed under the alternate procedure, along with the best available estimate of the total costs involved.

(f) The FHWA may suspend approval of the alternate procedure when any FHWA review discloses noncompliance with the certification. Federal funds will not participate in relocation costs incurred that do not comply with the requirements under §645.119(c)(1). (Information collection requirements in paragraph (c) were approved by the Office of Management and Budget under control number 2125-0533)

[50 FR 20345, May 15, 1985, as amended at 65 FR 70311, Nov. 22, 2000]


Subpart B -- Accommodation of Utilities


Source: 50 FR 20354, May 15, 1985, unless otherwise noted.


§645.201   Purpose.

To prescribe policies and procedures for accommodating utility facilities and private lines on the right-of-way of Federal-aid or direct Federal highway projects.


§645.203   Applicability.

This subpart applies to:

(a) New utility installations within the right-of-way of Federal-aid or direct Federal highway projects,

(b) Existing utility facilities which are to be retained, relocated, or adjusted within the right-of-way of active projects under development or construction when Federal-aid or direct Federal highway funds are either being or have been used on the involved highway facility. When existing utility installations are to remain in place without adjustments on such projects the transportation department and utility are to enter into an appropriate agreement as discussed in §645.213 of this part,

(c) Existing utility facilities which are to be adjusted or relocated under the provisions of §645.209(k), and

(d) Private lines which may be permitted to cross the right-of-way of a Federal-aid or direct Federal highway project pursuant to State law and regulations and the provisions of this subpart. Longitudinal use of such right-of-way by private lines is to be handled under the provisions of 23 CFR 1.23(c).


§645.205   Policy.

(a) Pursuant to the provisions of 23 CFR 1.23, it is in the public interest for utility facilities to be accommodated on the right-of-way of a Federal-aid or direct Federal highway project when such use and occupancy of the highway right-of-way do not adversely affect highway or traffic safety, or otherwise impair the highway or its aesthetic quality, and do not conflict with the provisions of Federal, State or local laws or regulations.

(b) Since by tradition and practice highway and utility facilities frequently coexist within common right-of-way or along the same transportation corridors, it is essential in such situations that these public service facilities be compatibly designed and operated. In the design of new highway facilities consideration should be given to utility service needs of the area traversed if such service is to be provided from utility facilities on or near the highway. Similarly the potential impact on the highway and its users should be considered in the design and location of utility facilities on or along highway right-of-way. Efficient, effective and safe joint highway and utility development of transportation corridors is important along high speed and high volume roads, such as major arterials and freeways, particularly those approaching metropolitan areas where space is increasingly limited. Joint highway and utility planning and development efforts are encouraged on Federal-aid highway projects.

(c) The manner is which utilities cross or otherwise occupy the right-of-way of a direct Federal or Federal-aid highway project can materially affect the highway, its safe operation, aesthetic quality, and maintenance. Therefore, it is necessary that such use and occupancy, where authorized, be regulated by transportation departments in a manner which preserves the operational safety and the functional and aesthetic quality of the highway facility. This subpart shall not be construed to alter the basic legal authority of utilities to install their facilities on public highways pursuant to law or franchise and reasonable regulation by transportation departments with respect to location and manner of installation.

(d) When utilities cross or otherwise occupy the right-of-way of a direct Federal or Federal-aid highway project on Federal lands, and when the right-of-way grant is for highway purposes only, the utility must also obtain and comply with the terms of a right-of-way or other occupancy permit for the Federal agency having jurisdiction over the underlying land.

[50 FR 20354, May 15, 1985, as amended at 53 FR 2833, Feb. 2, 1988]



§645.207   Definitions.

For the purpose of this regulation, the following definitions shall apply:

Aesthetic quality -- those desirable characteristics in the appearance of the highway and its environment, such as harmony between or blending of natural and manufactured objects in the environment, continuity of visual form without distracting interruptions, and simplicity of designs which are desirably functional in shape but without clutter.

Border area -- the area between the traveled way and the right-of-way line.

Clear roadside policy -- that policy employed by a transportation department to provide a clear zone in order to increase safety, improve traffic operations, and enhance the aesthetic quality of highways by designing, constructing and maintaining highway roadsides as wide, flat, and rounded as practical and as free as practical from natural or manufactured hazards such as trees, drainage structures, nonyielding sign supports, highway lighting supports, and utility poles and other ground-mounted structures. The policy should address the removal of roadside obstacles which are likely to be associated with accident or injury to the highway user, or when such obstacles are essential, the policy should provide for appropriate countermeasures to reduce hazards. Countermeasures include placing utility facilities at locations which protect out-of-control vehicles, using breakaway features, using impact attenuation devices, or shielding. In all cases full consideration shall be given to sound engineering principles and economic factors.

Clear zone -- the total roadside border area starting at the edge of the traveled way, available for safe use by errant vehicles. This area may consist of a shoulder, a recoverable slope, a non-recoverable slope, and/or the area at the toe of a non-recoverable slope available for safe use by an errant vehicle. The desired width is dependent upon the traffic volumes and speeds, and on the roadside geometry. The current edition of the AASHTO "Roadside Design Guide" should be used as a guide for establishing clear zones for various types of highways and operating conditions. This publication is available for inspection and copying from the FHWA Washington Headquarters and all FHWA Division Offices as prescribed in 49 CFR part 7. Copies of current AASHTO publications are available for purchase from the American Association of State Highway and Transportation Officials, Suite 225, 444 North Capitol Street, NW., Washington, D.C. 20001, or electronically at http://www.aashto.org.

Direct Federal highway projects -- those active or completed highway projects such as projects under the Federal Lands Highways Program which are under the direct administration of the Federal Highway Administration (FHWA)

Federal-aid highway projects -- those active or completed highway projects administered by or through a State transportation department which involve or have involved the use of Federal-aid highway funds for the development, acquisition of right-of-way, construction or improvement of the highway or related facilities, including highway beautification projects under 23 U.S.C. 319, Landscaping and Scenic Enhancement.

Freeway -- a divided arterial highway with full control of access.

Highway -- any public way for vehicular travel, including the entire area within the right-of-way and related facilities constructed or improved in whole or in part with Federal-aid or direct Federal highway funds.

Transportation department -- that department, agency, commission, board, or official of any State or political subdivision thereof, charged by its law with the responsibility for highway administration.

Private lines -- privately owned facilities which convey or transmit the commodities outlined in the definition of utility facility of this section, but devoted exclusively to private use.

Right-of-way -- real property, or interests therein, acquired, dedicated or reserved for the construction, operation, and maintenance of a highway in which Federal-aid or direct Federal highway funds are or have been involved in any stage of development. Lands acquired under 23 U.S.C. 319 shall be considered to be highway right-of-way.

State transportation department -- the transportation department of one of the 50 States, the District of Columbia, or Puerto Rico.

Use and occupancy agreement -- the document (written agreement or permit) by which the transportation department approves the use and occupancy of highway right-of-way by utility facilities or private lines.

Utility facility -- privately, publicly or cooperatively owned line, facility, or system for producing, transmitting, or distributing communications, cable television, power, electricity, light, heat, gas, oil, crude products, water, steam, waste, storm water not connected with highway drainage, or any other similar commodity, including any fire or police signal system or street lighting system, which directly or indirectly serves the public. The term utility shall also mean the utility company inclusive of any substantially owned or controlled subsidiary. For the purposes of this part, the term includes those utility-type facilities which are owned or leased by a government agency for its own use, or otherwise dedicated solely to governmental use. The term utility includes those facilities used solely by the utility which are a part of its operating plant.

[50 FR 20345, May 15, 1985, as amended at 51 FR 16834, May 7, 1986; 53 FR 2833, Feb. 2, 1988; 55 FR 25828, June 25, 1990; 60 FR 34850, July 5, 1995; 61 FR 12022, Mar. 25, 1996; 65 FR 70311, Nov. 22, 2000]



§645.209   General requirements.

(a) Safety. Highway safety and traffic safety are of paramount, but not of sole, importance when accommodating utility facilities within highway right-of-way. Utilities provide an essential public service to the general public. Traditionally, as a matter of sound economic public policy and law, utilities have used public road right-of-way for transmitting and distributing their services. The lack of sufficient right-of-way width to accommodate utilities outside the desirable clear zone, in and of itself, is not a valid reason to preclude utilities from occupying the highway right-of-way. However, due to the nature and volume of highway traffic, the effect of such joint use on the traveling public must be carefully considered by transportation departments before approval of utility use of the right-of-way of Federal-aid or direct Federal highway projects is given. Adjustments in the operating characteristics of the utility or the highway or other special efforts may be necessary to increase the compatibility of utility-highway joint use. The possibility of this joint use should be a consideration in establishing right-of-way requirements for highway projects. In any event, the design, location, and manner in which utilities use and occupy the right-of-way of Federal-aid or direct Federal highway projects must conform to the clear roadside policies for the highway involved and otherwise provide for a safe traveling environment as required by 23 U.S.C. 109(l)(1).

(b) New above ground installations. On Federal-aid or direct Federal highway projects, new above ground utility installations, where permitted, shall be located as far from the traveled way as possible, preferably along the right-of-way line. No new above ground utility installations are to be allowed within the established clear zone of the highway unless a determination has been made by the transportation department that placement underground is not technically feasible or is unreasonably costly and there are no feasible alternate locations. In exceptional situations when it is essential to locate such above ground utility facilities within the established clear zone of the highway, appropriate countermeasures to reduce hazards shall be used. Countermeasures include placing utility facilities at locations which protect or minimize exposure to out-of-control vehicles, using breakaway features, using impact attenuation devices, using delineation, or shielding.

(c) Installations within freeways. (1) Each State transportation department shall submit an accommodation plan in accordance with §§645.211 and 645.215 which addresses how the State transportation department will consider applications for longitudinal utility installations within the access control lines of a freeway. This includes utility installations within interchange areas which must be constructed or serviced by direct access from the main lanes or ramps. If a State transportation department elects to permit such use, the plan must address how the State transportation department will oversee such use consistent with this subpart, Title 23 U.S.C., and the safe and efficient use of the highways.

(2) Any accommodation plan shall assure that installations satisfy the following criteria:

(i) The effects utility installations will have on highway and traffic safety will be ascertained, since in no case shall any use be permitted which would adversely affect safety.

(ii) The direct and indirect environmental and economic effects of any loss of productive agricultural land or any productivity of any agricultural land which would result from the disapproval of the use of such right-of-way for accommodation of such utility facility will be evaluated.

(iii) These environmental and economic effects together with any interference with or impairment of the use of the highway in such right-of-way which would result from the use of such right-of-way for the accommodation of such utility facility will be considered.

(iv) [Reserved]

(v) A utility strip will be established along the outer edge of the right-of-way by locating a utility access control line between the proposed utility installation and the through roadway and ramps. Existing fences should be retained and, except along sections of freeways having frontage roads, planned fences should be located at the freeway right-of-way line. The State or political subdivision is to retain control of the utility strip right-of-way including its use by utility facilities. Service connections to adjacent properties shall not be permitted from within the utility strip.

(3) Nothing in this part shall be construed as prohibiting a transportation department from adopting a more restrictive policy than that contained herein with regard to longitudinal utility installations along freeway right-of-way and access for constructing and/or for servicing such installations.

(d) Uniform policies and procedures. For a transportation department to fulfill its responsibilities to control utility use of Federal-aid highway right-of-way within the State and its political subdivisions, it must exercise or cause to be exercised, adequate regulation over such use and occupancy through the establishment and enforcement of reasonably uniform policies and procedures for utility accommodation.

(e) Private lines. Because there are circumstances when private lines may be allowed to cross or otherwise occupy the right-of-way of Federal-aid projects, transportation departments shall establish uniform policies for properly controlling such permitted use. When permitted, private lines must conform to the provisions of this part and the provisions of 23 CFR 1.23(c) for longitudinal installations.

(f) Direct Federal highway projects. On direct Federal highway projects, the FHWA will apply, or cause to be applied, utility and private line accommodation policies similar to those required on Federal-aid highway projects. When appropriate, agreements will be entered into between the FHWA and the transportation department or other government agencies to ensure adequate control and regulation of use by utilities and private lines of the right-of-way on direct Federal highway projects.

(g) Projects where state lacks authority. On Federal-aid highway projects where the State transportation department does not have legal authority to regulate highway use by utilities and private lines, the State transportation department must enter into formal agreements with those local officials who have such authority. The agreements must provide for a degree of protection to the highway at least equal to the protection provided by the State transportation department's utility accommodation policy approved under the provisions of §645.215(b) of this part. The project agreement between the State transportation department and the FHWA on all such Federal-aid highway projects shall contain a special provision incorporating the formal agreements with the responsible local officials.

(h) Scenic areas. New utility installations, including those needed for highway purposes, such as for highway lighting or to serve a weigh station, rest area or recreation area, are not permitted on highway right-of-way or other lands which are acquired or improved with Federal-aid or direct Federal highway funds and are located within or adjacent to areas of scenic enhancement and natural beauty. Such areas include public park and recreational lands, wildlife and waterfowl refuges, historic sites as described in 23 U.S.C. 138, scenic strips, overlooks, rest areas and landscaped areas. The State transportation department may permit exceptions provided the following conditions are met:

(1) New underground or aerial installations may be permitted only when they do not require extensive removal or alteration of trees or terrain features visible to the highway user or impair the aesthetic quality of the lands being traversed.

(2) Aerial installations may be permitted only when:

(i) Other locations are not available or are unusually difficult and costly, or are less desirable from the standpoint of aesthetic quality,

(ii) Placement underground is not technically feasible or is unreasonably costly, and

(iii) The proposed installation will be made at a location, and will employ suitable designs and materials, which give the greatest weight to the aesthetic qualities of the area being traversed. Suitable designs include, but are not limited to, self-supporting armless, single-pole construction with vertical configuration of conductors and cable.

(3) For new utility installations within freeways, the provisions of paragraph (c) of this section must also be satisfied.

(i) Joint use agreements. When the utility has a compensable interest in the land occupied by its facilities and such land is to be jointly occupied and used for highway and utility purposes, the transportation department and utility shall agree in writing as to the obligations and responsibilities of each party. Such joint-use agreements shall incorporate the conditions of occupancy for each party, including the rights vested in the transportation department and the rights and privileges retained by the utility. In any event, the interest to be acquired by or vested in the transportation department in any portion of the right-of-way of a Federal-aid or direct Federal highway project to be vacated, used or occupied by utilities or private lines, shall be adequate for the construction, safe operation, and maintenance of the highway project.

(j) Traffic control plan. Whenever a utility installation, adjustment or maintenance activity will affect the movement of traffic or traffic safety, the utility shall implement a traffic control plan and utilize traffic control devices as necessary to ensure the safe and expeditious movement of traffic around the work site and the safety of the utility work force in accordance with procedures established by the transportation department. The traffic control plan and the application of traffic control devices shall conform to the standards set forth in the current edition of the "Manual on Uniform Traffic Control Devices" (MUTCD) and 23 CFR part 630, subpart J. This publication is available for inspection and copying from the FHWA Washington Headquarters and all FHWA Division Offices as prescribed in 49 CFR part 7.

(k) Corrective measures. When the transportation department determines that existing utility facilities are likely to be associated with injury or accident to the highway user, as indicated by accident history or safety studies, the transportation department shall initiate or cause to be initiated in consultation with the affected utilities, corrective measures to provide for a safer traffic environment. The corrective measures may include changes to utility or highway facilities and should be prioritized to maximum safety benefits in the most cost-effective manner. The scheduling of utility safety improvements should take into consideration planned utility replacement or upgrading schedules, accident potential, and the availability of resources. It is expected that the requirements of this paragraph will result in an orderly and positive process to address the identified utility hazard problems in a timely and reasonable manner with due regard to the effect of the corrective measures on both the utility consumer and the road user. The type of corrective measures are not prescribed. Any requests received involving Federal participation in the cost of adjusting or relocating utility facilities pursuant to this paragrpah shall be subject to the provisions of 23 CFR part 645, subpart A, Utility Relocations, Adjustments and Reimbursement, and 23 CFR part 924, Highway Safety Improvement Program.

(l) Wetlands. The installation of privately owned lines or conduits on the right-of-way of Federal-aid or direct Federal highway projects for the purpose of draining adjacent wetlands onto the highway right-of-way is considered to be inconsistent with Executive Order 11990, Protection of Wetlands, dated May 24, 1977, and shall be prohibited.

(m) Utility determination. In determining whether a proposed installation is a utility or not, the most important consideration is how the STD views it under its own State laws and/or regulations.

[50 FR 20354, May 15, 1985, as amended at 53 FR 2833, Feb. 2, 1988; 60 FR 34851, July 5, 1995; 65 FR 70311, Nov. 22, 2000]



§645.211   State transportation department accommodation policies.

The FHWA should use the current editions of the AASHTO publications, "A Guide for Accommodating Utilities Within Highway Right-of-Way" and "Roadside Design Guide" to assist in the evaluation of adequacy of STD utility accommodation policies. These publications are available for inspection from the FHWA Washington Headquarters and all FHWA Division Offices as prescribed in 49 CFR part 7. Copies of current AASHTO publications are available for purchase from the American Association of State Highway and Transportation Officials, Suite 225, 444 North Capitol Street NW., Washington, DC 20001, or electronically at http://www.aashto.org. At a minimum, such policies shall make adequate provisions with respect to the following:

(a) Utilities must be accommodated and maintained in a manner which will not impair the highway or adversely affect highway or traffic safety. Uniform procedures controlling the manner, nature and extent of such utility use shall be established.

(b) Consideration shall be given to the effect of utility installations in regard to safety, aesthetic quality, and the costs or difficulty of highway and utility construction and maintenance.

(c) The State transportation department's standards for regulating the use and occupancy of highway right-of-way by utilities must include, but are not limited to, the following:

(1) The horizontal and vertical location requirements and clearances for the various types of utilities must be clearly stated. These must be adequate to ensure compliance with the clear roadside policies for the particular highway involved.

(2) The applicable provisions of government or industry codes required by law or regulation must be set forth or appropriately referenced, including highway design standards or other measures which the State transportation department deems necessary to provide adequate protection to the highway, its safe operation, aesthetic quality, and maintenance.

(3) Specifications for and methods of installation; requirements for preservation and restoration of highway facilities, appurtenances, and natural features and vegetation on the right-of-way; and limitations on the utility's activities within the right-of-way including installation within areas set forth by §645.209(h) of this part should be prescribed as necessary to protect highway interests.

(4) Measures necessary to protect traffic and its safe operation during and after installation of facilities, including control-of-access restrictions, provisions for rerouting or detouring traffic, traffic control measures to be employed, procedures for utility traffic control plans, limitations on vehicle parking and materials storage, protection of open excavations, and the like must be provided.

(5) A State transportation department may deny a utility's request to occupy highway right-of-way based on State law, regulation, or ordinances or the State transportation department's policy. However, in any case where the provisions of this part are to be cited as the basis for disapproving a utility's request to use and occupy highway right-of-way, measures must be provided to evaluate the direct and indirect environmental and economic effects of any loss of productive agricultural land or any impairment of the productivity of any agricultural land that would result from the disapproval. The environmental and economic effects on productive agricultural land together with the possible interference with or impairment of the use of the highway and the effect on highway safety must be considered in the decision to disapprove any proposal by a utility to use such highway right-of-way.

(d) Compliance with applicable State laws and approved State transportation department utility accommodation policies must be assured. The responsible State transportation department's file must contain evidence of the written arrangements which set forth the terms under which utility facilities are to cross or otherwise occupy highway right-of-way. All utility installations made on highway right-of-way shall be subject to written approval by the State transportation department. However, such approval will not be required where so provided in the use and occupancy agreement for such matters as utility facility maintenance, installation of service connections on highways other than freeways, or emergency operations.

(e) The State transportation department shall set forth in its utility accommodation plan detailed procedures, criteria, and standards it will use to evaluate and approve individual applications of utilities on freeways under the provisions of §645.209(c) of this part. The State transportation department also may develop such procedures, criteria and standards by class of utility. In defining utility classes, consideration may be given to distinguishing utility services by type, nature or function and their potential impact on the highway and its user.

(f) The means and authority for enforcing the control of access restrictions applicable to utility use of controlled access highway facilities should be clearly set forth in the State transportation department plan. (Information collection requirements in paragraphs (a), (b) and (c) were approved under control number 2125-0522, and paragraph (d) under control number 2125-0514)

[50 FR 20354, May 15, 1985, as amended at 53 FR 2834, Feb. 2, 1988; 55 FR 25828, June 25, 1990; 65 FR 70312, Nov. 22, 2000]



§645.213   Use and occupancy agreements (permits).

The written arrangements, generally in the form of use and occupancy agreements setting forth the terms under which the utility is to cross or otherwise occupy the highway right-of-way, must include or incorporate by reference:

(a) The transportation department standards for accommodating utilities. Since all of the standards will not be applicable to each individual utility installation, the use and occupancy agreement must, as a minimum, describe the requirements for location, construction, protection of traffic, maintenance, access restriction, and any special conditions applicable to each installation.

(b) A general description of the size, type, nature, and extent of the utility facilities being located within the highway right-of-way.

(c) Adequate drawings or sketches showing the existing and/or proposed location of the utility facilities within the highway right-of-way with respect to the existing and/or planned highway improvements, the traveled way, the right-of-way lines and, where applicable, the control of access lines and approved access points.

(d) The extent of liability and responsibilities associated with future adjustment of the utilities to accommodate highway improvements.

(e) The action to be taken in case of noncompliance with the transportation department's requirements.

(f) Other provisions as deemed necessary to comply with laws and regulations. (Approved by the Office of Management and Budget under control number 2125-0522)


§645.215   Approvals.

(a) Each State transportation department shall submit a statement to the FHWA on the authority of utilities to use and occupy the right-of-way of State highways, the State transportation department's power to regulate such use, and the policies the State transportation department employs or proposes to employ for accommodating utilities within the right-of-way Federal-aid highways under its jurisdiction. Statements previously submitted and approved by the FHWA need not be resubmitted provided the statement adequately addresses the requirements of this part. When revisions are deemed necessary the changes to the previously approved statement may be submitted separately to the FHWA for approval. The State transportation department shall include similar information on the use and occupancy of such highways by private lines where permitted. The State shall identify those areas, if any, of Federal-aid highways within its borders where the State transportation department is without legal authority to regulate use by utilities. The statement shall address the nature of the formal agreements with local officials required by §645.209(g) of this part. It is expected that the statements required by this part or necessary revisions to previously submitted and approved statements will be submitted to FHWA within 1 year of the effective date of this regulation.

(b) Upon determination by the FHWA that a State transportation department's policies satisfy the provisions of 23 U.S.C. 109, 111, and 116, and 23 CFR 1.23 and 1.27, and meet the requirements of this regulation, the FHWA will approve their use on Federal-aid highway projects in that State

(c) Any changes, additions or deletions the State transportation department proposes to the approved policies are subject to FHWA approval.

(d) When a utility files a notice or makes an individual application or request to a STD to use or occupy the right-of-way of a Federal-aid highway project, the STD is not required to submit the matter to the FHWA for prior concurrence, except when the proposed installation is not in accordance with this regulation or with the STD's utility accommodation policy approved by the FHWA for use on Federal-aid highway projects.

(e) The State transportation department's practices under the policies or agreements approved under §645.215(b) of this part shall be periodically reviewed by the FHWA. (Information collection requirements in paragraph (a) were approved by the Office of Management and Budget under control number 2125-0514)

[50 FR 20354, May 15, 1985, as amended at 53 FR 2834, Feb. 2, 1988; 60 FR 34851, July 5, 1995; 65 FR 70312, Nov. 22, 2000]






PART 646 -- RAILROADS



Subpart A -- Railroad-Highway Insurance Protection


   Sec.
646.101   Purpose.
646.103   Application.
646.105   Contractor's public liability and property damage insurance.
646.107   Railroad protective insurance.
646.109   Types of coverage.
646.111   Amount of coverage.

Subpart B -- Railroad-Highway Projects

646.200   Purpose and applicability.
646.202   [Reserved]
646.204   Definitions.
646.206   Types of projects.
646.208   Funding.
646.210   Classification of projects and railroad share of the cost.
646.212   Federal share.
646.214   Design.
646.216   General procedures.
646.218   Simplified procedure for accelerating grade crossing improvements.
646.220   Alternate Federal-State procedure.
Appendix to Subpart B -- Horizontal and Vertical Clearance Provisions for Overpass and Underpass Structures

Authority: 23 U.S.C. 109(e), 120(c), 130, 133(d)(1), and 315; 49 CFR 1.48(b).

Subpart A -- Railroad-Highway Insurance Protection


Source: 39 FR 36474, Oct. 10, 1974, unless otherwise noted.


§646.101   Purpose.

The purpose of this part is to prescribe provisions under which Federal funds may be applied to the costs of public liability and property damage insurance obtained by contractors (a) for their own operations, and (b) on behalf of railroads on or about whose right-of-way the contractors are required to work in the construction of highway projects financed in whole or in part with Federal funds.


§646.103   Application.

(a) This part applies:

(1) To a contractors' legal liability for bodily injury to, or death of, persons and for injury to, or destruction of, property.

(2) To the liability which may attach to railroads for bodily injury to, or death of, persons and for injury to, or destruction of, property.

(3) To damage to property owned by or in the care, custody or control of the railroads, both as such liability or damage may arise out of the contractor's operations, or may result from work performed by railroads at or about railroad rights-of-way in connection with projects financed in whole or in part with Federal funds.

(b) Where the highway construction is under the direct supervision of the Federal Highway Administration (FHWA), all references herein to the State shall be considered as references to the FHWA.


§646.105   Contractor's public liability and property damage insurance.

(a) Contractors may be subject to liability with respect to bodily injury to or death of persons, and injury to, or destruction of property, which may be suffered by persons other than their own employees as a result of their operations in connection with construction of highway projects located in whole or in part within railroad right-of-way and financed in whole or in part with Federal funds. Protection to cover such liability of contractors shall be furnished under regular contractors' public liability and property damage insurance policies issued in the names of the contractors. Such policies shall be so written as to furnish protection to contractors respecting their operations in performing work covered by their contract.

(b) Where a contractor sublets a part of the work on any project to a subcontractor, the contractor shall be required to secure insurance protection in his own behalf under contractor's public liability and property damage insurance policies to cover any liability imposed on him by law for damages because of bodily injury to, or death of, persons and injury to, or destruction of, property as a result of work undertaken by such subcontractors. In addition, the contractor shall provide for and on behalf of any such subcontractors protection to cover like liability imposed upon the latter as a result of their operations by means of separate and individual contractor's public liability and property damage policies; or, in the alternative, each subcontractor shall provide satisfactory insurance on his own behalf to cover his individual operations.

(c) The contractor shall furnish to the State highway department evidence satisfactory to such department and to the FHWA that the insurance coverages required herein have been provided. The contractor shall also furnish a copy of such evidence to the railroad or railroads involved. The insurance specified shall be kept in force until all work required to be performed shall have been satisfactorily completed and accepted in accordance with the contract under which the construction work is undertaken.


§646.107   Railroad protective insurance.

In connection with highway projects for the elimination of hazards of railroad-highway crossings and other highway construction projects located in whole or in part within railroad right-of-way, railroad protective liability insurance shall be purchased on behalf of the railroad by the contractor. The standards for railroad protective insurance established by §§646.109 through 646.111 shall be adhered to insofar as the insurance laws of the State will permit.

[39 FR 36474, Oct. 10, 1974, as amended at 47 FR 33955, Aug. 5, 1982]



§646.109   Types of coverage.

(a) Coverage shall be limited to damage suffered by the railroad on account of occurrences arising out of the work of the contractor on or about the railroad right-of-way, independent of the railroad's general supervision or control, except as noted in §646.109(b)(4).

(b) Coverage shall include:

(1) Death of or bodily injury to passengers of the railroad and employees of the railroad not covered by State workmen's compensation laws;

(2) Personal property owned by or in the care, custody or control of the railroads;

(3) The contractor, or any of his agents or employees who suffer bodily injury or death as the result of acts of the railroad or its agents, regardless of the negligence of the railroad;

(4) Negligence of only the following classes of railroad employees:

(i) Any supervisory employee of the railroad at the job site;

(ii) Any employee of the railroad while operating, attached to, or engaged on, work trains or other railroad equipment at the job site which are assigned exclusively to the contractor; or

(iii) Any employee of the railroad not within (b)(4) (i) or (ii) who is specifically loaned or assigned to the work of the contractor for prevention of accidents or protection of property, the cost of whose services is borne specifically by the contractor or governmental authority.


§646.111   Amount of coverage.

(a) The maximum dollar amounts of coverage to be reimbursed from Federal funds with respect to bodily injury, death and property damage is limited to a combined amount of $2 million per occurrence with an aggregate of $6 million applying separately to each annual period except as provided in paragraph (b) of this section.

(b) In cases involving real and demonstrable danger of appreciably higher risks, higher dollar amounts of coverage for which premiums will be reimbursable from Federal funds shall be allowed. These larger amounts will depend on circumstances and shall be written for the individual project in accordance with standard underwriting practices upon approval of the FHWA.

[39 FR 36474, Oct. 10, 1974, as amended at 47 FR 33955, Aug. 5, 1982]


Subpart B -- Railroad-Highway Projects


Source: 40 FR 16059, Apr. 9, 1975, unless otherwise noted.


§646.200   Purpose and applicability.

(a) The purpose of this subpart is to prescribe policies and procedures for advancing Federal-aid projects involving railroad facilities.

(b) This subpart, and all references hereinafter made to projects, applies to Federal-aid projects involving railroad facilities, including projects for the elimination of hazards of railroad-highway crossings, and other projects which use railroad properties or which involve adjustments required by highway construction to either railroad facilities or facilities that are jointly owned or used by railroad and utility companies.

(c) Additional instructions for projects involving the elimination of hazards of railroad/highway grade crossings pursuant to 23 U.S.C. 130 are set forth in 23 CFR part 924.

(d) Procedures on reimbursement for projects undertaken pursuant to this subpart are set forth in 23 CFR part 140, subpart I.

(e) Procedures on insurance required of contractors working on or about railroad right-of-way are set forth in 23 CFR part 646, subpart A.

[40 FR 16059, Apr. 9, 1975, as amended at 45 FR 20795, Mar. 31, 1980; 62 FR 45328, Aug. 27, 1997]



§646.202   [Reserved]


§646.204   Definitions.

For the purposes of this subpart, the following definitions apply:

Active warning devices means those traffic control devices activated by the approach or presence of a train, such as flashing light signals, automatic gates and similar devices, as well as manually operated devices and crossing watchmen, all of which display to motorists positive warning of the approach or presence of a train.

Company shall mean any railroad or utility company including any wholly owned or controlled subsidiary thereof.

Construction shall mean the actual physical construction to improve or eliminate a railroad-highway grade crossing or accomplish other railroad involved work.

A diagnostic team means a group of knowledgeable representatives of the parties of interest in a railroad-highway crossing or a group of crossings.

Main line railroad track means a track of a principal line of a railroad, including extensions through yards, upon which trains are operated by timetable or train order or both, or the use of which is governed by block signals or by centralized traffic control.

Passive warning devices means those types of traffic control devices, including signs, markings and other devices, located at or in advance of grade crossings to indicate the presence of a crossing but which do not change aspect upon the approach or presence of a train.

Preliminary engineering shall mean the work necessary to produce construction plans, specifications, and estimates to the degree of completeness required for undertaking construction thereunder, including locating, surveying, designing, and related work.

Railroad shall mean all rail carriers, publicly-owned, private, and common carriers, including line haul freight and passenger railroads, switching and terminal railroads and passenger carrying railroads such as rapid transit, commuter and street railroads.

Utility shall mean the lines and facilities for producing, transmitting or distributing communications, power, electricity, light, heat, gas, oil, water, steam, sewer and similar commodities.

[40 FR 16059, Apr. 9, 1975, as amended at 62 FR 45328, Aug. 27, 1997]



§646.206   Types of projects.

(a) Projects for the elimination of hazards, to both vehicles and pedestrians, of railroad-highway crossings may include but are not limited to:

(1) Grade crossing elimination;

(2) Reconstruction of existing grade separations; and

(3) Grade crossing improvements.

(b) Other railroad-highway projects are those which use railroad properties or involve adjustments to railroad facilities required by highway construction but do not involve the elimination of hazards of railroad-highway crossings. Also included are adjustments to facilities that are jointly owned or used by railroad and utility companies.


§646.208   Funding.

(a) Railroad/highway crossing projects may be funded through the Federal-aid funding source appropriate for the involved project.

(b) Projects for the elimination of hazards at railroad/highway crossings may, at the option of the State, be funded with the funds provided by 23 U.S.C. 133(d)(1).

[62 FR 45328, Aug. 27, 1997]



§646.210   Classification of projects and railroad share of the cost.

(a) State laws requiring railroads to share in the cost of work for the elimination of hazards at railroad-highway crossings shall not apply to Federal-aid projects.

(b) Pursuant to 23 U.S.C. 130(b), and 49 CFR 1.48:

(1) Projects for grade crossing improvements are deemed to be of no ascertainable net benefit to the railroads and there shall be no required railroad share of the costs.

(2) Projects for the reconstruction of existing grade separations are deemed to generally be of no ascertainable net benefit to the railroad and there shall be no required railroad share of the costs, unless the railroad has a specific contractual obligation with the State or its political subdivision to share in the costs.

(3) On projects for the elimination of existing grade crossings at which active warning devices are in place or ordered to be installed by a State regulatory agency, the railroad share of the project costs shall be 5 percent.

(4) On projects for the elimination of existing grade crossings at which active warning devices are not in place and have not been ordered installed by a State regulatory agency, or on projects which do not eliminate an existing crossing, there shall be no required railroad share of the project cost.

(c) The required railroad share of the cost under §646.210(b)(3) shall be based on the costs for preliminary engineering, right-of-way and construction within the limits described below:

(1) Where a grade crossing is eliminated by grade separation, the structure and approaches required to transition to a theoretical highway profile which would have been constructed if there were no railroad present, for the number of lanes on the existing highway and in accordance with the current design standards of the State highway agency.

(2) Where another facility, such as a highway or waterway, requiring a bridge structure is located within the limits of a grade separation project, the estimated cost of a theoretical structure and approaches as described in §646.210(c)(1) to eliminate the railroad-highway grade crossing without considering the presence of the waterway or other highway.

(3) Where a grade crossing is eliminated by railroad or highway relocation, the actual cost of the relocation project, the estimated cost of the relocation project, or the estimated cost of a structure and approaches as described in §646.210(c)(1), whichever is less.

(d) Railroads may voluntarily contribute a greater share of project costs than is required. Also, other parties may voluntarily assume the railroad's share.


§646.212   Federal share.

(a) General. (1) Federal funds are not eligible to participate in costs incurred solely for the benefit of the railroad.

(2) At grade separations Federal funds are eligible to participate in costs to provide space for more tracks than are in place when the railroad establishes to the satisfaction of the State highway agency and FHWA that it has a definite demand and plans for installation of the additional tracks within a reasonable time.

(3) The Federal share of the cost of a grade separation project shall be based on the cost to provide horizontal and/or vertical clearances used by the railroad in its normal practice subject to limitations as shown in the appendix or as required by a State regulatory agency.

(b) The Federal share of railroad/highway crossing projects may be:

(1) Regular pro rata sharing as provided by 23 U.S.C. 120(a) and 120(b).

(2) One hundred percent Federal share, as provided by 23 U.S.C. 120(c).

(3) Ninety percent Federal share for funds made available through 23 U.S.C. 133(d)(1).

[40 FR 16059, Apr. 9, 1975, as amended at 47 FR 33955, Aug. 5, 1982; 53 FR 32218, Aug. 24, 1988; 62 FR 45328, Aug. 27, 1997]



§646.214   Design.

(a) General. (1) Facilities that are the responsibility of the railroad for maintenance and operation shall conform to the specifications and design standards used by the railroad in its normal practice, subject to approval by the State highway agency and FHWA.

(2) Facilities that are the responsibility of the highway agency for maintenance and operation shall conform to the specifications and design standards and guides used by the highway agency in its normal practice for Federal-aid projects.

(b) Grade crossing improvements. (1) All traffic control devices proposed shall comply with the latest edition of the Manual on Uniform Traffic Control Devices for Streets and Highways supplemented to the extent applicable by State standards.

(2) Pursuant to 23 U.S.C. 109(e), where a railroad-highway grade crossing is located within the limits of or near the terminus of a Federal-aid highway project for construction of a new highway or improvement of the existing roadway, the crossing shall not be opened for unrestricted use by traffic or the project accepted by FHWA until adequate warning devices for the crossing are installed and functioning properly.

(3)(i) Adequate warning devices, under §646.214(b)(2) or on any project where Federal-aid funds participate in the installation of the devices are to include automatic gates with flashing light signals when one or more of the following conditions exist:

(A) Multiple main line railroad tracks.

(B) Multiple tracks at or in the vicinity of the crossing which may be occupied by a train or locomotive so as to obscure the movement of another train approaching the crossing.

(C) High Speed train operation combined with limited sight distance at either single or multiple track crossings.

(D) A combination of high speeds and moderately high volumes of highway and railroad traffic.

(E) Either a high volume of vehicular traffic, high number of train movements, substantial numbers of schoolbuses or trucks carrying hazardous materials, unusually restricted sight distance, continuing accident occurrences, or any combination of these conditions.

(F) A diagnostic team recommends them.

(ii) In individual cases where a diagnostic team justifies that gates are not appropriate, FHWA may find that the above requirements are not applicable.

(4) For crossings where the requirements of §646.214(b)(3) are not applicable, the type of warning device to be installed, whether the determination is made by a State regulatory agency, State highway agency, and/or the railroad, is subject to the approval of FHWA.

(c) Grade crossing elimination. All crossings of railroads and highways at grade shall be eliminated where there is full control of access on the highway (a freeway) regardless of the volume of railroad or highway traffic.

[40 FR 16059, Apr. 9, 1975, as amended at 47 FR 33955, Aug. 5, 1982; 62 FR 45328, Aug. 27, 1997]



§646.216   General procedures.

(a) General. Unless specifically modified herein, applicable Federal-aid procedures govern projects undertaken pursuant to this subpart.

(b) Preliminary engineering and engineering services. (1) As mutually agreed to by the State highway agency and railroad, and subject to the provisions of §646.216(b)(2), preliminary engineering work on railroad-highway projects may be accomplished by one of the following methods:

(i) The State or railroad's engineering forces;

(ii) An engineering consultant selected by the State after consultation with the railroad, and with the State administering the contract; or

(iii) An engineering consultant selected by the railroad, with the approval of the State and with the railroad administering the contract.

(2) Where a railroad is not adequately staffed, Federal-aid funds may participate in the amounts paid to engineering consultants and others for required services, provided such amounts are not based on a percentage of the cost of construction, either under contracts for individual projects or under existing written continuing contracts where such work is regularly performed for the railroad in its own work under such contracts at reasonable costs.

(c) Rights-of-way. (1) Acquisition of right-of-way by a State highway agency on behalf of a railroad or acquisition of nonoperating real property from a railroad shall be in accordance with the Uniform Relocation Assistance and Real Property Acquisition Policies Act of 1970 (42 U.S.C. 4601 et seq.) and applicable FHWA right-of-way procedures in 23 CFR, chapter I, subchapter H. On projects for the elimination of hazards of railroad-highway crossings by the relocation of railroads, acquisition or replacement right-of-way by a railroad shall be in accordance with 42 U.S.C. 4601 et seq.

(2) Where buildings and other depreciable structures of the railroad (such as signal towers, passenger stations, depots, and other buildings, and equipment housings) which are integral to operation of railroad traffic are wholly or partly affected by a highway project, the costs of work necessary to functionally restore such facilities are eligible for participation. However, when replacement of such facilities is necessary, credits shall be made to the cost of the project for:

(i) Accrued depreciation, which is that amount based on the ratio between the period of actual length of service and total life expectancy applied to the original cost.

(ii) Additions or improvements which provide higher quality or increased service capability of the facility and which are provided solely for the benefit of the railroad.

(iii) Actual salvage value of the material recovered from the facility being replaced. Total credits to a project shall not be required in excess of the replacement cost of the facility.

(3) Where Federal funds participate in the cost of replacement right-of-way, there will be no charge to the project for the railroad's existing right-of-way being transferred to the State highway agency except when the value of the right-of-way being taken exceeds the value of the replacement right-of-way.

(d) State-railroad agreements. (1) Where construction of a Federal-aid project requires use of railroad properties or adjustments to railroad facilities, there shall be an agreement in writing between the State highway agency and the railroad company.

(2) The written agreement between the State and the railroad shall, as a minimum include the following, where applicable:

(i) The provisions of this subpart and of 23 CFR part 140, subpart I, incorporated by reference.

(ii) A detailed statement of the work to be performed by each party.

(iii) Method of payment (either actual cost or lump sum),

(iv) For projects which are not for the elimination of hazards of railroad-highway crossings, the extent to which the railroad is obligated to move or adjust its facilities at its own expense,

(v) The railroad's share of the project cost,

(vi) An itemized estimate of the cost of the work to be performed by the railroad,

(vii) Method to be used for performing the work, either by railroad forces or by contract,

(viii) Maintenance responsibility,

(ix) Form, duration, and amounts of any needed insurance,

(x) Appropriate reference to or identification of plans and specifications,

(xi) Statements defining the conditions under which the railroad will provide or require protective services during performance of the work, the type of protective services and the method of reimbursement to the railroad, and

(xii) Provisions regarding inspection of any recovered materials.

(3) On work to be performed by the railroad with its own forces and where the State highway agency and railroad agree, subject to approval by FHWA, an agreement providing for a lump sum payment in lieu of later determination of actual costs may be used for any of the following:

(i) Installation or improvement of grade crossing warning devices and/or grade crossing surfaces, regardless of cost, or

(ii) Any other eligible work where the estimated cost to the State of the proposed railroad work does not exceed $100,000 or

(iii) Where FHWA finds that the circumstances are such that this method of developing costs would be in the best interest of the public.

(4) Where the lump sum method of payment is used, periodic reviews and analyses of the railroad's methods and cost data used to develop lump sum estimates will be made.

(5) Master agreements between a State and a railroad on an areawide or statewide basis may be used. These agreements would contain the specifications, regulations, and provisions required in conjunction with work performed on all projects. Supporting data for each project or group of projects must, when combined with the master agreement by reference, satisfy the provisions of §646.216(d)(2).

(6) Official orders issued by regulatory agencies will be accepted in lieu of State-railroad agreements only where, together with supplementary written understandings between the State and the railroad, they include the items required by §646.216(d)(2).

(7) In extraordinary cases where FHWA finds that the circumstances are such that requiring such agreement or order would not be in the best interest of the public, projects may be approved for construction with the aid of Federal funds, provided satisfactory commitments have been made with respect to construction, maintenance and the railroad share of project costs.

(e) Authorizations. (1) The costs of preliminary engineering, right-of-way acquisition, and construction incurred after the date each phase of the work is included in an approved statewide transportation improvement program and authorized by the FHWA are eligible for Federal-aid participation. Preliminary engineering and right-of-way acquisition costs which are otherwise eligible, but incurred by a railroad prior to authorization by the FHWA, although not reimbursable, may be included as part of the railroad share of project cost where such a share is required.

(2) Prior to issuance of authorization by FHWA either to advertise the physical construction for bids or to proceed with force account construction for railroad work or for other construction affected by railroad work, the following must be accomplished:

(i) The plans, specifications and estimates must be approved by FHWA.

(ii) A proposed agreement between the State and railroad must be found satisfactory by FHWA. Before Federal funds may be used to reimburse the State for railroad costs the executed agreement must be approved by FHWA. However, cost for materials stockpiled at the project site or specifically purchased and delivered to the company for use on the project may be reimbursed on progress billings prior to the approval of the executed State-Railroad Agreement in accordance with 23 CFR 140.922(a) and §646.218 of this part.

(iii) Adequate provisions must be made for any needed easements, right-of-way, temporary crossings for construction purposes or other property interests.

(iv) The pertinent portions of the State-railroad agreement applicable to any protective services required during performance of the work must be included in the project specifications and special provisions for any construction contract.

(3) In unusual cases, pending compliance with §646.216(e)(2)(ii), (iii) and (iv), authorization may be given by FHWA to advertise for bids for highway construction under conditions where a railroad grants a right-of-entry to its property as necessary to prosecute the physical construction.

(f) Construction. (1) Construction may be accomplished by:

(i) Railroad force account,

(ii) Contracting with the lowest qualified bidder based on appropriate solicitation,

(iii) Existing continuing contracts at reasonable costs, or

(iv) Contract without competitive bidding, for minor work, at reasonable costs.

(2) Reimbursement will not be made for any increased costs due to changes in plans:

(i) For the convenience of the contractor, or

(ii) Not approved by the State and FHWA.

(3) The State and FHWA shall be afforded a reasonable opportunity to inspect materials recovered by the railroad prior to disposal by sale or scrap. This requirement will be satisfied by the railroad giving written notice, or oral notice with prompt written confirmation, to the State of the time and place where the materials will be available for inspection. The giving of notice is the responsibility of the railroad, and it may be held accountable for full value of materials disposed of without notice.

(4) In addition to normal construction costs, the following construction costs are eligible for participation with Federal-aid funds when approved by the State and FHWA:

(i) The cost of maintaining temporary facilities of a railroad company required by and during the highway construction to the extent that such costs exceed the documented normal cost of maintaining the permanent facilities.

(ii) The cost of stage or extended construction involving grade corrections and/or slope stabilization for permanent tracks of a railroad which are required to be relocated on new grade by the highway construction. Stage or extended construction will be approved by FHWA only when documentation submitted by the State establishes the proposed method of construction to be the only practical method and that the cost of the extended construction within the period specified is estimated to be less than the cost of any practicable alternate procedure.

(iii) The cost of restoring the company's service by adustments of existing facilities away from the project site, in lieu of and not to exceed the cost of replacing, adjusting or relocating facilities at the project site.

(iv) The cost of an addition or improvement to an existing railroad facility which is required by the highway construction.

[40 FR 16059, Apr. 9, 1975, as amended at 40 FR 29712, July 15, 1975; 47 FR 33956, Aug. 5, 1982; 62 FR 45328, Aug. 27, 1997]



§646.218   Simplified procedure for accelerating grade crossing improvements.

(a) The procedure set forth in this section is encouraged for use in simplifying and accelerating the processing of single or multiple grade crossing improvements.

(b) Eligible preliminary engineering costs may include those incurred in selecting crossings to be improved, determining the type of improvement for each crossing, estimating the cost and preparing the required agreement.

(c) The written agreement between a State and a railroad shall contain as a minimum:

(1) Identification of each crossing location.

(2) Description of improvement and estimate of cost for each crossing location.

(3) Estimated schedule for completion of work at each location.

(d) Following programming, authorization and approval of the agreement under §646.218(c), FHWA may authorize construction, including acquisition of warning device materials, with the condition that work at any particular location will not be undertaken until the proposed or executed State-railroad agreement under §646.216(d)(2) is found satisfactory by FHWA and the final plans, specifications, and estimates are approved and with the condition that only material actually incorporated into the project will be eligible for Federal participation.

(e) Work programmed and authorized under this simplified procedure should include only that which can reasonably be expected to reach the construction stage within one year and be completed within two years after the initial authorization date.


§646.220   Alternate Federal-State procedure.

(a) On other than Interstate projects, an alternate procedure may be used, at the election of the State, for processing certain types of railroad-highway work. Under this procedure, the State highway agency will act in the relative position of FHWA for reviewing and approving projects.

(b) The scope of the State's approval authority under the alternate procedure includes all actions necessary to advance and complete the following types of railroad-highway work:

(1) All types of grade crossing improvements under §646.206(a)(3).

(2) Minor adjustments to railroad facilities under §646.206(b).

(c) The following types of work are to be reviewed and approved in the normal manner, as prescribed elsewhere in this subpart.

(1) All projects under §646.206(a) (1) and (2).

(2) Major adjustments to railroad facilities under §646.206(b).

(d) Any State wishing to adopt the alternate procedure may file a formal application for approval by FHWA. The application must include the following:

(1) The State's written policies and procedures for administering and processing Federal-aid railroad-highway work, which make adequate provisions with respect to all of the following:

(i) Compliance with the provisions of title 23 U.S.C., title 23 CFR, and other applicable Federal laws and Executive Orders.

(ii) Compliance with this subpart and 23 CFR part 140, subpart I and 23 CFR part 172.

(iii) For grade crossing safety improvements, compliance with the requirements of 23 CFR part 924.

(2) A statement signed by the Chief Administrative Officer of the State highway agency certifying that:

(i) The work will be done in accordance with the applicable provisions of the State's policies and procedures submitted under §646.220(d)(1), and

(ii) Reimbursement will be requested in only those costs properly attributable to the highway construction and eligible for Federal fund participation.

(e) When FHWA has approved the alternate procedure, it may authorize the State to proceed in accordance with the State's certification, subject to the following conditions:

(1) The work has been programmed.

(2) The State submits in writing a request for such authorization which shall include a list of the improvements or adjustments to be processed under the alternate procedure, along with the best available estimate of cost.

(f) The FHWA Regional Administrator may suspend approval of the certified procedure, where FHWA reviews disclose noncompliance with the certification. Federal-aid funds will not be eligible to participate in costs that do not qualify under §646.220(d)(1).

[40 FR 16059, Apr. 9, 1975; 40 FR 29712, July 15, 1975; 40 FR 31211, July 25, 1975; 42 FR 30835, June 17, 1977, as amended at 45 FR 20795, Mar. 31, 1980]




Appendix to Subpart B of Part 646 -- Horizontal and Vertical Clearance Provisions for Overpass and Underpass Structures

The following implements provisions of 23 CFR 646.212(a)(3).

a. Lateral Geometrics

A cross section with a horizontal distance of 6.1 meters, measured at right angles from the centerline of track at the top of rails, to the face of the embankment slope, may be approved. The 6.1-meters distance may be increased at individual structure locations as appropriate to provide for drainage if justified by a hydraulic analysis or to allow adequate room to accommodate special conditions, such as where heavy and drifting snow is a problem. The railroad must demonstrate that this is its normal practice to address these special conditions in the manner proposed. Additionally, this distance may also be increased up to 2.5 meters as may be necessary for off-track maintenance equipment, provided adequate horizontal clearance is not available in adjacent spans and where justified by the presence of an existing maintenance road or by evidence of future need for such equipment. All piers should be placed at least 2.8 meters horizontally from the centerline of the track and preferably beyond the drainage ditch. For multiple track facilities, all dimensions apply to the centerline of the outside track.

Any increase above the 6.1-meters horizontal clearance distance must be required by specific site conditions and be justified by the railroad to the satisfaction of the State highway agency (SHA) and the FHWA.

b. Vertical Clearance

A vertical clearance of 7.1 meters above the top of rails, which includes an allowance for future ballasting of the railroad tracks, may be approved. Vertical clearance greater than 7.1 meters may be approved when the State regulatory agency having jurisdiction over such matters requires a vertical clearance in excess of 7.1 meters or on a site by site basis where justified by the railroad to the satisfaction of the SHA and the FHWA. A railroad's justification for increased vertical clearance should be based on an analysis of engineering, operational and/or economic conditions at a specific structure location.

Federal-aid highway funds are also eligible to participate in the cost of providing vertical clearance greater than 7.1 meters where a railroad establishes to the satisfaction of a SHA and the FHWA that it has a definite formal plan for electrification of its rail system where the proposed grade separation project is located. The plan must cover a logical independent segment of the rail system and be approved by the railroad's corporate headquarters. For 25 kv line, a vertical clearance of 7.4 meters may be approved. For 50 kv line, a vertical clearance of 8.0 meters may be approved.

A railroad's justification to support its plan for electrification shall include maps and plans or drawings showing those lines to be electrified; actions taken by its corporate headquarters committing it to electrification including a proposed schedule; and actions initiated or completed to date implementing its electrification plan such as a showing of the amounts of funds and identification of structures, if any, where the railroad has expended its own funds to provide added clearance for the proposed electrification. If available, the railroad's justification should include information on its contemplated treatment of existing grade separations along the section of its rail system proposed for electrification.

The cost of reconstructing or modifying any existing railroad-highway grade separation structures solely to accommodate electrification will not be eligible for Federal-aid highway fund participation.

c. Railroad Structure Width

Two and eight tenths meters of structure width outside of the centerline of the outside tracks may be approved for a structure carrying railroad tracks. Greater structure width may be approved when in accordance with standards established and used by the affected railroad in its normal practice.

In order to maintain continuity of off-track equipment roadways at structures carrying tracks over limited access highways, consideration should be given at the preliminary design stage to the feasibility of using public road crossings for this purpose. Where not feasible, an additional structure width of 2.5 meters may be approved if designed for off-track equipment only.

[53 FR 32218, Aug. 24, 1988, as amended at 62 FR 45328, Aug. 27, 1997]






PART 650 -- BRIDGES, STRUCTURES, AND HYDRAULICS



Subpart A -- Location and Hydraulic Design of Encroachments on Flood Plains


   Sec.
650.101   Purpose.
650.103   Policy.
650.105   Definitions.
650.107   Applicability.
650.109   Public involvement.
650.111   Location hydraulic studies.
650.113   Only practicable alternative finding.
650.115   Design standards.
650.117   Content of design studies.

Subpart B -- Erosion and Sediment Control on Highway Construction Projects

650.201   Purpose.
650.203   Policy.
650.205   Definitions.
650.207   Plans, specifications, and estimates.
650.209   Construction.
650.211   Guidelines.

Subpart C -- National Bridge Inspection Standards

650.301   Application of standards.
650.303   Inspection procedures.
650.305   Frequency of inspections.
650.307   Qualifications of personnel.
650.309   Inspection report.
650.311   Inventory.

Subpart D -- Highway Bridge Replacement and Rehabilitation Program

650.401   Purpose.
650.403   Definition of terms.
650.405   Eligible projects.
650.407   Application for bridge replacement or rehabilitation.
650.409   Evaluation of bridge inventory.
650.411   Procedures for bridge replacement and rehabilitation projects.
650.413   Funding.
650.415   Reports.

Subparts E-F [Reserved]


Subpart G -- Discretionary Bridge Candidate Rating Factor

650.701   Purpose.
650.703   Eligible projects.
650.705   Application for discretionary bridge funds.
650.707   Rating factor.
650.709   Special considerations.

Subpart H -- Navigational Clearances for Bridges

650.801   Purpose.
650.803   Policy.
650.805   Bridges not requiring a USCG permit.
650.807   Bridges requiring a USCG permit.
650.809   Movable span bridges.

Authority: 23 U.S.C. 109 (a) and (h), 144, 151, 315, and 319; 23 CFR 1.32; 49 CFR 1.48(b), E.O. 11988 (3 CFR, 1977 Comp., p. 117); Department of Transportation Order 5650.2 dated April 23, 1979 (44 FR 24678); §161 of Public Law 97-424, 96 Stat. 2097, 3135; §4(b) of Public Law 97-134, 95 Stat. 1699; 33 U.S.C. 401, 491 et seq., 511 et seq.; and §1057 of Public Law 102-240, 105 Stat. 2002.

Subpart A -- Location and Hydraulic Design of Encroachments on Flood Plains


Source: 44 FR 67580, Nov. 26, 1979, unless otherwise noted.


§650.101   Purpose.

To prescribe Federal Highway Administration (FHWA) policies and procedures for the location and hydraulic design of highway encroachments on flood plains, including direct Federal highway projects administered by the FHWA.


§650.103   Policy.

It is the policy of the FHWA:

(a) To encourage a broad and unified effort to prevent uneconomic, hazardous or incompatible use and development of the Nation's flood plains,

(b) To avoid longitudinal encroachments, where practicable,

(c) To avoid significant encroachments, where practicable,

(d) To minimize impacts of highway agency actions which adversely affect base flood plains,

(e) To restore and preserve the natural and beneficial flood-plain values that are adversely impacted by highway agency actions,

(f) To avoid support of incompatible flood-plain development,

(g) To be consistent with the intent of the Standards and Criteria of the National Flood Insurance Program, where appropriate, and

(h) To incorporate "A Unified National Program for Floodplain Management" of the Water Resources Council into FHWA procedures.


§650.105   Definitions.

(a) Action shall mean any highway construction, reconstruction, rehabilitation, repair, or improvement undertaken with Federal or Federal-aid highway funds or FHWA approval.

(b) Base flood shall mean the flood or tide having a 1-percent chance of being exceeded in any given year.

(c) Base flood plain shall mean the area subject to flooding by the base flood.

(d) Design Flood shall mean the peak discharge, volume if appropriate, stage or wave crest elevation of the flood associated with the probability of exceedance selected for the design of a highway encroachment. By definition, the highway will not be inundated from the stage of the design flood.

(e) Encroachment shall mean an action within the limits of the base flood plain.

(f) Floodproof shall mean to design and construct individual buildings, facilities, and their sites to protect against structural failure, to keep water out or to reduce the effects of water entry.

(g) Freeboard shall mean the vertical clearance of the lowest structural member of the bridge superstructure above the water surface elevation of the overtopping flood.

(h) Minimize shall mean to reduce to the smallest practicable amount or degree.

(i) Natural and beneficial flood-plain values shall include but are not limited to fish, wildlife, plants, open space, natural beauty, scientific study, outdoor recreation, agriculture, aquaculture, forestry, natural moderation of floods, water quality maintenance, and groundwater recharge.

(j) Overtopping flood shall mean the flood described by the probability of exceedance and water surface elevation at which flow occurs over the highway, over the watershed divide, or through structure(s) provided for emergency relief.

(k) Practicable shall mean capable of being done within reasonable natural, social, or economic constraints.

(l) Preserve shall mean to avoid modification to the functions of the natural flood-plain environment or to maintain it as closely as practicable in its natural state.

(m) Regulatory floodway shall mean the flood-plain area that is reserved in an open manner by Federal, State or local requirements, i.e., unconfined or unobstructed either horizontally or vertically, to provide for the discharge of the base flood so that the cumulative increase in water surface elevation is no more than a designated amount (not to exceed 1 foot as established by the Federal Emergency Management Agency (FEMA) for administering the National Flood Insurance Program).

(n) Restore shall mean to reestablish a setting or environment in which the functions of the natural and beneficial flood-plain values adversely impacted by the highway agency action can again operate.

(o) Risk shall mean the consequences associated with the probability of flooding attributable to an encroachment. It shall include the potential for property loss and hazard to life during the service life of the highway.

(p) Risk analysis shall mean an economic comparison of design alternatives using expected total costs (construction costs plus risk costs) to determine the alternative with the least total expected cost to the public. It shall include probable flood-related costs during the service life of the facility for highway operation, maintenance, and repair, for highway-aggravated flood damage to other property, and for additional or interrupted highway travel.

(q) Significant encroachment shall mean a highway encroachment and any direct support of likely base flood-plain development that would involve one or more of the following construction-or flood-related impacts:

(1) A significant potential for interruption or termination of a transportation facility which is needed for emergency vehicles or provides a community's only evacuation route.

(2) A significant risk, or

(3) A significant adverse impact on natural and beneficial flood-plain values.

(r) Support base flood-plain development shall mean to encourage, allow, serve, or otherwise facilitate additional base flood-plain development. Direct support results from an encroachment, while indirect support results from an action out of the base flood plain.


§650.107   Applicability.

(a) The provisions of this regulation shall apply to all encroachments and to all actions which affect base flood plains, except for repairs made with emergency funds (23 CFR part 668) during or immediately following a disaster.

(b) The provisions of this regulation shall not apply to or alter approvals or authorizations which were given by FHWA pursuant to regulations or directives in effect before the effective date of this regulation.


§650.109   Public involvement.

Procedures which have been established to meet the public involvement requirements of 23 CFR part 771 shall be used to provide opportunity for early public review and comment on alternatives which contain encroachments.

[53 FR 11065, Apr. 5, 1988]



§650.111   Location hydraulic studies.

(a) National Flood Insurance Program (NFIP) maps or information developed by the highway agency, if NFIP maps are not available, shall be used to determine whether a highway location alternative will include an encroachment.

(b) Location studies shall include evaluation and discussion of the practicability of alternatives to any longitudinal encroachments.

(c) Location studies shall include discussion of the following items, commensurate with the significance of the risk or environmental impact, for all alternatives containing encroachments and for those actions which would support base flood-plain development:

(1) The risks associated with implementation of the action,

(2) The impacts on natural and beneficial flood-plain values,

(3) The support of probable incompatible flood-plain development,

(4) The measures to minimize flood-plain impacts associated with the action, and

(5) The measures to restore and preserve the natural and beneficial flood-plain values impacted by the action.

(d) Location studies shall include evaluation and discussion of the practicability of alternatives to any significant encroachments or any support of incompatible flood-plain development.

(e) The studies required by §650.111 (c) and (d) shall be summarized in environmental review documents prepared pursuant to 23 CFR part 771.

(f) Local, State, and Federal water resources and flood-plain management agencies should be consulted to determine if the proposed highway action is consistent with existing watershed and flood-plain management programs and to obtain current information on development and proposed actions in the affected watersheds.


§650.113   Only practicable alternative finding.

(a) A proposed action which includes a significant encroachment shall not be approved unless the FHWA finds that the proposed significant encroachment is the only practicable alternative. This finding shall be included in the final environmental document (final environmental impact statement or finding of no significant impact) and shall be supported by the following information:

(1) The reasons why the proposed action must be located in the flood plain,

(2) The alternatives considered and why they were not practicable, and

(3) A statement indicating whether the action conforms to applicable State or local flood-plain protection standards.

(b) [Reserved]

[44 FR 67580, Nov. 26, 1979, as amended at 48 FR 29274, June 24, 1983]



§650.115   Design standards.

(a) The design selected for an encroachment shall be supported by analyses of design alternatives with consideration given to capital costs and risks, and to other economic, engineering, social and environmental concerns.

(1) Consideration of capital costs and risks shall include, as appropriate, a risk analysis or assessment which includes:

(i) The overtopping flood or the base flood, whichever is greater, or

(ii) The greatest flood which must flow through the highway drainage structure(s), where overtopping is not practicable. The greatest flood used in the analysis is subject to state-of-the-art capability to estimate the exceedance probability.

(2) The design flood for encroachments by through lanes of Interstate highways shall not be less than the flood with a 2-percent chance of being exceeded in any given year. No minimum design flood is specified for Interstate highway ramps and frontage roads or for other highways.

(3) Freeboard shall be provided, where practicable, to protect bridge structures from debris- and scour-related failure.

(4) The effect of existing flood control channels, levees, and reservoirs shall be considered in estimating the peak discharge and stage for all floods considered in the design.

(5) The design of encroachments shall be consistent with standards established by the FEMA, State, and local governmental agencies for the administration of the National Flood Insurance Program for:

(i) All direct Federal highway actions, unless the standards are demonstrably inappropriate, and

(ii) Federal-aid highway actions where a regulatory floodway has been designated or where studies are underway to establish a regulatory floodway.

(b) Rest area buildings and related water supply and waste treatment facilities shall be located outside the base flood plain, where practicable. Rest area buildings which are located on the base flood plain shall be floodproofed against damage from the base flood.

(c) Where highway fills are to be used as dams to permanently impound water more than 50 acre-feet (6.17×10 4 cubic metres) in volume or 25 feet (7.6 metres) deep, the hydrologic, hydraulic, and structural design of the fill and appurtenant spillways shall have the approval of the State or Federal agency responsible for the safety of dams or like structures within the State, prior to authorization by the Division Administrator to advertise for bids for construction.


§650.117   Content of design studies.

(a) The detail of studies shall be commensurate with the risk associated with the encroachment and with other economic, engineering, social or environmental concerns.

(b) Studies by highway agencies shall contain:

(1) The hydrologic and hydraulic data and design computations,

(2) The analysis required by §650.115(a), and

(3) For proposed direct Federal highway actions, the reasons, when applicable, why FEMA criteria (44 CFR 60.3, formerly 24 CFR 1910.3) are demonstrably inappropriate.

(c) For encroachment locations, project plans shall show:

(1) The magnitude, approximate probability of exceedance and, at appropriate locations, the water surface elevations associated with the overtopping flood or the flood of §650.115(a)(1)(ii), and

(2) The magnitude and water surface elevation of the base flood, if larger than the overtopping flood.

Subpart B -- Erosion and Sediment Control on Highway Construction Projects


Source: 59 FR 37939, July 26, 1994, unless otherwise noted.


§650.201   Purpose.

The purpose of this subpart is to prescribe policies and procedures for the control of erosion, abatement of water pollution, and prevention of damage by sediment deposition from all construction projects funded under title 23, United States Code.


§650.203   Policy.

It is the policy of the Federal Highway Administration (FHWA) that all highways funded in whole or in part under title 23, United States Code, shall be located, designed, constructed and operated according to standards that will minimize erosion and sediment damage to the highway and adjacent properties and abate pollution of surface and ground water resources. Guidance for the development of standards used to minimize erosion and sediment damage is referenced in §650.211 of this part.


§650.205   Definitions.

Erosion control measures and practices are actions that are taken to inhibit the dislodging and transporting of soil particles by water or wind, including actions that limit the area of exposed soil and minimize the time the soil is exposed.

Permanent erosion and sediment control measures and practices are installations and design features of a construction project which remain in place and in service after completion of the project.

Pollutants are substances, including sediment, which cause deterioration of water quality when added to surface or ground waters in sufficient quantity.

Sediment control measures and practices are actions taken to control the deposition of sediments resulting from surface runoff.

Temporary erosion and sediment control measures and practices are actions taken on an interim basis during construction to minimize the disturbance, transportation, and unwanted deposition of sediment.


§650.207   Plans, specifications and estimates.

(a) Emphasis shall be placed on erosion control in the preparation of plans, specifications and estimates.

(b) All reasonable steps shall be taken to insure that highway project designs for the control of erosion and sedimentation and the protection of water quality comply with applicable standards and regulations of other agencies.

[39 FR 36332, Oct. 9, 1974]



§650.209   Construction.

(a) Permanent erosion and sediment control measures and practices shall be established and implemented at the earliest practicable time consistent with good construction and management practices.

(b) Implementation of temporary erosion and sediment control measures and practices shall be coordinated with permanent measures to assure economical, effective, and continuous control throughout construction.

(c) Erosion and sediment control measures and practices shall be monitored and maintained or revised to insure that they are fulfilling their intended function during the construction of the project.

(d) Federal-aid funds shall not be used in erosion and sediment control actions made necessary because of contractor oversight, carelessness, or failure to implement sufficient control measures.

(e) Pollutants used during highway construction or operation and material from sediment traps shall not be stockpiled or disposed of in a manner which makes them susceptible to being washed into any watercourse by runoff or high water. No pollutants shall be deposited or disposed of in watercourses.


§650.211   Guidelines.

(a) The FHWA adopts the AASHTO Highway Drainage Guidelines, Volume III, "Erosion and Sediment Control in Highway Construction," 1992, 1 as guidelines to be followed on all construction projects funded under title 23, United States Code. These guidelines are not intended to preempt any requirements made by or under State law if such requirements are more stringent.

1This document is available for inspection from the FHWA headquarters and field offices as prescribed by 49 CFR part 7, appendix D. It may be purchased from the American Association of State Highway and Transportation Officials offices at Suite 225, 444 North Capitol Street, NW., Washington, DC 20001.

(b) Each State highway agency should apply the guidelines referenced in paragraph (a) of this section or apply its own guidelines, if these guidelines are more stringent, to develop standards and practices for the control of erosion and sediment on Federal-aid construction projects. These specific standards and practices may reference available resources, such as the procedures presented in the AASHTO "Model Drainage Manual," 1991. 2

2This document is available for inspection from the FHWA headquarters and field offices as prescribed by 49 CFR part 7, appendix D. It may be purchased from the American Association of State Highway and Transportation Officials offices at Suite 225, 444 North Capitol Street, NW., Washington, DC 20001.

(c) Consistent with the requirements of section 6217(g) of the Coastal Zone Act Reauthorization Amendments of 1990 (Pub. L. 101-508, 104 Stat. 1388-299), highway construction projects funded under title 23, United States Code, and located in the coastal zone management areas of States with coastal zone management programs approved by the United States Department of Commerce, National Oceanic and Atmospheric Administration, should utilize "Guidance Specifying Management Measures for Sources of Nonpoint Source Pollution in Coastal Waters," 84-B-92-002, U.S. EPA, January 1993. 3 State highway agencies should refer to this Environmental Protection Agency guidance document for the design of projects within coastal zone management areas.

3This document is available for inspection and copying as prescribed by 49 CFR part 7, appendix D.

Subpart C -- National Bridge Inspection Standards



§650.301   Application of standards.

The National Bridge Inspection Standards in this part apply to all structures defined as bridges located on all public roads. In acordance with the AASHTO (American Association of State Highway and Transportation Officials) Transportation Glossary, a bridge is defined as a structure including supports erected over a depression or an obstruction, such as water, highway, or railway, and having a track or passageway for carrying traffic or other moving loads, and having an opening measured along the center of the roadway of more than 20 feet between undercopings of abutments or spring lines of arches, or extreme ends of openings for multiple boxes; it may also include multiple pipes, where the clear distance between openings is less than half of the smaller contiguous opening.

[44 FR 25435, May 1, 1979, as amended at 51 FR 16834, May 7, 1986]



§650.303   Inspection procedures.

(a) Each highway department shall include a bridge inspection organization capable of performing inspections, preparing reports, and determining ratings in acordance with the provisions of the AASHTO Manual 1 and the Standards contained herein.

1The AASHTO Manual referred to in this part is the Manual for Maintenance Inspection of Bridges 1983 together with subsequent interim changes or the most recent version of the AASHTO Manual published by the American Association of State Highway and Transportation Officials. A copy of the Manual may be examined during normal business hours at the office of each Division Administrator of the Federal Highway Administration, at the office of each Regional Federal Highway Administrator, and at the Washington Headquarters of the Federal Highway Administration. The addresses of those document insepction facilities are set forth in appendix D to part 7 of the regulations of the Office of the Secretary (49 CFR part 7). In addition, a copy of the Manual may be secured upon payment in advance by writing to the American Association of State Highway and Transportation Officials, 444 N. Capitol Street, NW., Suite 225, Washington, DC 20001.

(b) Bridge inspectors shall meet the minimum qualifications stated in §650.307.

(c) Each structure required to be inspected under the Standards shall be rated as to its safe load carrying capacity in accordance with section 4 of the AASHTO Manual. If it is determined under this rating procedure that the maximum legal load under State law exceeds the load permitted under the Operating Rating, the bridge must be posted in conformity with the AASHTO Manual or in accordance with State law.

(d) Inspection records and bridge inventories shall be prepared and maintained in accordance with the Standards.

(e) The individual in charge of the organizational unit that has been delegated the responsibilities for bridge inspection, reporting and inventory shall determine and designate on the individual inspection and inventory records and maintain a master list of the following:

(1) Those bridges which contain fracture critical members, the location and description of such members on the bridge and the inspection frequency and procedures for inspection of such members. (Fracture critical members are tension members of a bridge whose failure will probably cause a portion of or the entire bridge to collapse.)

(2) Those bridges with underwater members which cannot be visually evaluated during periods of low flow or examined by feel for condition, integrity and safe load capacity due to excessive water depth or turbidity. These members shall be described, the inspection frequency stated, not to exceed five years, and the inspection procedure specified.

(3) Those bridges which contain unique or special features requiring additional attention during inspection to ensure the safety of such bridges and the inspection frequency and procedure for inspection of each such feature.

(4) The date of last inspection of the features designated in paragraphs (e)(1) through (3) of this section and a description of the findings and follow-up actions, if necessary, resulting from the most recent inspection of fracture critical details, underwater members or special features of each so designated bridge.

[36 FR 7851, Apr. 27, 1971. Redesignated at 39 FR 10430, Mar. 20, 1974, as amended at 44 FR 25435, May 1, 1979; 53 FR 32616, Aug. 26, 1988]



§650.305   Frequency of inspections.

(a) Each bridge is to be inspected at regular intervals not to exceed 2 years in accordance with section 2.3 of the AASHTO Manual.

(b) Certain types or groups of bridges will require inspection at less than 2-year intervals. The depth and frequency to which bridges are to be inspected will depend on such factors as age, traffic characteristics, state of maintenance, and known deficiencies. The evaluation of these factors will be the responsibility of the individual in charge of the inspection program.

(c) The maximum inspection interval may be increased for certain types or groups of bridges where past inspection reports and favorable experience and analysis justify the increased interval of inspection. If a State proposes to inspect some bridges at greater than the specified two-year interval, the State shall submit a detailed proposal and supporting data to the Federal Highway Administrator for approval. The maximum time period between inspections shall not exceed four years.

[36 FR 7851, Apr. 27, 1971. Redesignated at 39 FR 10430, Mar. 20, 1974, as amended at 39 FR 29590, Aug. 16, 1974; 53 FR 32616, Aug. 26, 1988; 57 FR 53281, Nov. 9, 1992]



§650.307   Qualifications of personnel.

(a) The individual in charge of the organizational unit that has been delegated the responsibilities for bridge inspection, reporting, and inventory shall possess the following minimum qualifications:

(1) Be a registered professional engineer; or

(2) Be qualified for registration as a professional engineer under the laws of the State; or

(3) Have a minimum of 10 years experience in bridge inspection assignments in a responsible capacity and have completed a comprehensive training course based on the "Bridge Inspector's Training Manual," 2 which has been developed by a joint Federal-State task force, and subsequent additions to the manual. 3

2The "Bridge Inspector's Training Manual" may be purchased from the Superintendent of Documents, U.S. Government Printing Office, Washington, DC 20402.

3The following publications are supplements to the "Bridge Inspector's Training Manual": "Bridge Inspector's Manual for Movable Bridges." 1977, GPO Stock No. 050-002-00103-5; "Culvert Inspector's Training Manual," July 1986, GPO Stock No. 050-001-0030-7; and "Inspection of Fracture Critical Bridge Members," 1986, GPO Stock No. 050-001-00302-3.

(b) An individual in charge of a bridge inspection team shall possess the following minimum qualifications:

(1) Have the qualifications specified in paragraph (a) of this section; or

(2) Have a minimum of 5 years experience in bridge inspection assignments in a responsible capacity and have completed a comprehensive training course based on the "Bridge Inspector's Training Manual," which has been developed by a joint Federal-State task force.

(3) Current certification as a Level III or IV Bridge Safety Inspector under the National Society of Professional Engineer's program for National Certification in Engineering Technologies (NICET) 4 is an alternate acceptable means for establishing that a bridge inspection team leader is qualified.

4For information on NICET program certification contact: National Institute for Certification in Engineering Technologies, 1420 King Street, Alexandria, Virginia 22314, Attention: John D. Antrim, P.E., Phone (703) 684-2835.

[36 FR 7851, Apr. 27, 1971. Redesignated at 39 FR 10430, Mar. 20, 1974, as amended at 44 FR 25435, May 1, 1979; 53 FR 32616, Aug. 26, 1988]



§650.309   Inspection report.

The findings and results of bridge inspections shall be recorded on standard forms. The data required to complete the forms and the functions which must be performed to compile the data are contained in section 3 of the AASHTO Manual.

[39 FR 29590, Aug. 16, 1974]



§650.311   Inventory.

(a) Each State shall prepare and maintain an inventory of all bridge structures subject to the Standards. Under these Standards, certain structure inventory and appraisal data must be collected and retained within the various departments of the State organization for collection by the Federal Highway Administration as needed. A tabulation of this data is contained in the structure inventory and appraisal sheet distributed by the Federal Highway Administration as part of the Recording and Coding Guide for the Structure Inventory and Appraisal of the Nation's Bridges (Coding Guide) in January of 1979. Reporting procedures have been developed by the Federal Highway Administration.

(b) Newly completed structures, modification of existing structures which would alter previously recorded data on the inventory forms or placement of load restriction signs on the approaches to or at the structure itself shall be entered in the State's inspection reports and the computer inventory file as promptly as practical, but no later than 90 days after the change in the status of the structure for bridges directly under the State's jurisdiction and no later than 180 days after the change in status of the structure for all other bridges on public roads within the State.

[44 FR 25435, May 1, 1979, as amended at 53 FR 32617, Aug. 26, 1988]


Subpart D -- Highway Bridge Replacement and Rehabilitation Program


Source: 44 FR 15665, Mar. 15, 1979, unless otherwise noted.


§650.401   Purpose.

The purpose of this regulation is to prescribe policies and outline procedures for administering the Highway Bridge Replacement and Rehabilitation Program in accordance with 23 U.S.C. 144.


§650.403   Definition of terms.

As used in this regulation:

(a) Bridge. A structure, including supports, erected over a depression or an obstruction, such as water, a highway, or a railway, having a track or passageway for carrying traffic or other moving loads, and having an opening measured along the center of the roadway of more than 20 feet between undercopings of abutments or spring lines of arches, or extreme ends of the openings for multiple boxes; it may include multiple pipes where the clear distance between openings is less than half of the smaller contiguous opening.

(b) Sufficiency rating. The numerical rating of a bridge based on its structural adequacy and safety, essentiality for public use, and its serviceability and functional obsolescence.

(c) Rehabilitation. The major work required to restore the structural integrity of a bridge as well as work necessary to correct major safety defects.


§650.405   Eligible projects.

(a) General. Deficient highway bridges on all public roads may be eligible for replacement or rehabilitation.

(b) Types of projects which are eligible. The following types of work are eligible for participation in the Highway Bridge Replacement and Rehabilitation Program (HBRRP), hereinafter known as the bridge program.

(1) Replacement. Total replacement of a structurally deficient or functionally obsolete bridge with a new facility constructed in the same general traffic corridor. A nominal amount of approach work, sufficient to connect the new facility to the existing roadway or to return the gradeline to an attainable touchdown point in accordance with good design practice is also eligible. The replacement structure must meet the current geometric, construction and structural standards required for the types and volume of projected traffic on the facility over its design life.

(2) Rehabilitation. The project requirements necessary to perform the major work required to restore the structural integrity of a bridge as well as work necessary to correct major safety defects are eligible except as noted under ineligible work. Bridges to be rehabilitated both on or off the F-A System shall, as a minimum, conform with the provisions of 23 CFR part 625, Design Standards for Federal-aid Highways, for the class of highway on which the bridge is a part.

(c) Ineligible work. Except as otherwise prescribed by the Administrator, the costs of long approach fills, causeways, connecting roadways, interchanges, ramps, and other extensive earth structures, when constructed beyond the attainable touchdown point, are not eligible under the bridge program.


§650.407   Application for bridge replacement or rehabilitation.

(a) Agencies participate in the bridge program by conducting bridge inspections and submitting Structure Inventory and Appraisal (SI&A) sheet inspection data. Federal and local governments supply SI&A sheet data to the State agency for review and processing. The State is responsible for submitting the six computer card format or tapes containing all public road SI&A sheet bridge information through the Division Administrator of the Federal Highway Administration (FHWA) for processing. These requirements are prescribed in 23 CFR 650.309 and 650.311, the National Bridge Inspection Standards.

(b) Inventory data may be submitted as available and shall be submitted at such additional times as the FHWA may request.

(c) Inventory data on bridges that have been strengthened or repaired to eliminate deficiencies, or those that have been replaced or rehabilitated using bridge replacement and/or other funds, must be revised in the inventory through data submission.

(d) The Secretary may, at the request of a State, inventory bridges, on and off the Federal-aid system, for historic significance.

[44 FR 15665, Mar. 15, 1979, as amended at 44 FR 72112, Dec. 13, 1979]



§650.409   Evaluation of bridge inventory.

(a) Sufficiency rating of bridges. Upon receipt and evaluation of the bridge inventory, a sufficiency rating will be assigned to each bridge by the Secretary in accordance with the approved AASHTO 1 sufficiency rating formula. The sufficiency rating will be used as a basis for establishing eligibility and priority for replacement or rehabilitation of bridges; in general the lower the rating, the higher the priority.

1American Association of State Highway and Transporation Officials, Suite 225, 444 North Capitol Street, NW, Washington, DC 20001.

(b) Selection of bridges for inclusion in State program. After evaluation of the inventory and assignment of sufficiency ratings, the Secretary will provide the State with a selection list of bridges within the State that are eligible for the bridge program. From that list or from previously furnished selection lists, the State may select bridge projects.


§650.411   Procedures for bridge replacement and rehabilitation projects.

(a) Consideration shall be given to projects which will remove from service highway bridges most in danger of failure.

(b) Submission and approval of projects. (1) Bridge replacement or rehabilitation projects shall be submitted by the State to the Secretary in accordance with 23 CFR part 630, subpart A Federal-Aid Programs, Approval and Authorization.

(2) Funds apportioned to a State shall be made available throughout each State on a fair and equitable basis.

(c)(1) Each approved project will be designed, constructed, and inspected for acceptance in the same manner as other projects on the system on which the project is located. It shall be the responsibility of the State agency to properly maintain, or cause to be properly maintained, any project constructed under this bridge program. The State highway agency shall enter into a formal agreement for maintenance with appropriate local government officials in cases where an eligible project is located within and is under the legal authority of such a local government.

(2) Whenever a deficient bridge is replaced or its deficiency alleviated by a new bridge under the bridge program, the deficient bridge shall either be dismantled or demolished or its use limited to the type and volume of traffic the structure can safely service over its remaining life. For example, if the only deficiency of the existing structure is inadequate roadway width and the combination of the new and existing structure can be made to meet current standards for the volume of traffic the facility will carry over its design life, the existing bridge may remain in place and be incorporated into the system.

[44 FR 15665, Mar. 15, 1979, as amended at 44 FR 72112, Dec. 13, 1979]



§650.413   Funding.

(a) Funds authorized for carrying out the Highway Bridge Replacement and Rehabilitation Program are available for obligation at the beginning of the fiscal year for which authorized and remain available for expenditure for the same period as funds apportioned for projects on the Federal-aid primary system.

(b) The Federal share payable on account of any project carried out under 23 U.S.C. 144 shall be 80 percent of the eligible cost.

(c) Not less than 15 percent nor more than 35 percent of the apportioned funds shall be expended for projects located on public roads, other than those on a Federal-aid system. The Secretary after consultation with State and local officials may, with respect to a State, reduce the requirement for expenditure for bridges not on a Federal-aid system when he determines that such State has inadequate needs to justify such expenditure.


§650.415   Reports.

The Secretary must report annually to the Congress on projects approved and current inventories together with recommendations for further improvements.

Subparts E-F [Reserved]

Subpart G -- Discretionary Bridge Candidate Rating Factor


Source: 48 FR 52296, Nov. 17, 1983, unless otherwise noted.


§650.701   Purpose.

The purpose of this regulation is to describe a rating factor used as part of a selection process of allocation of discretionary bridge funds made available to the Secretary of Transportation under 23 U.S.C. 144.


§650.703   Eligible projects.

(a) Deficient highway bridges on Federal-aid highway system roads may be eligible for allocation of discretionary bridge funds to the same extent as they are for bridge funds apportioned under 23 U.S.C. 144, provided that the total project cost for a discretionary bridge candidate is at least $10 million or twice the amont of 23 U.S.C. 144 funds apportioned to the State during the fiscal year for which funding for the candidate bridge is requested.

(b) After the effective date of this regulation for the discretionary bridge candidate rating factor, only candidate bridges not previously selected with a computed rating factor of 100 or less will be eligible for consideration.


§650.705   Application for discretionary bridge funds.

Each year through its field offices, the FHWA will issue an annual call for discretionary bridge candidate submittals including updates of previously submitted but not selected projects. Each State is responsible for submitting such data as required for candidate bridges. Data requested will include structure number, funds needed by fiscal year, total project cost, current average daily truck traffic and a narrative describing the existing bridge, the proposed new or rehabilitated bridge and other relevant factors which the State believes may warrant special consideration.


§650.707   Rating factor.

(a) The following formula is to be used in the selection process for ranking discretionary bridge candidates:

The lower the rating factor, the higher the priority for selection and funding.

(b) The terms in the rating factor are defined as follows:

SR is Sufficiency Rating computed as illustrated in appendix A of the Recording and Coding Guide for the Structure inventory and Appraisal of the Nation's Bridges, USDOT/FHWA (latest edition); (If SR is less than 1.0, use SR=1.0);

ADT is Average Daily Traffic in thousands taking the most current value from the national bridge inventory data;

ADTT is Average Daily Truck Traffic in thousands (Pick up trucks and light delivery trucks not included);

For load posted bridges, the ADTT furnished should be that which would use the bridge if traffic were not restricted.

The ADTT should be the annual average volume, not peak or seasonal.

D is Defense Highway System Status

D=1 if not on defense highway

D=1.5 if bridge carries a designated defense highway

The last term of the rating factor expression includes the State's unobligated balance of funds received under 23 U.S.C. 144 as of June 30 preceding the date of calculation, and the total funds received under 23 U.S.C. 144 for the last four fiscal years ending with the most recent fiscal year of the FHWA's annual call for discretionary bridge candidate submittals; (if unobligated HBRRP balance is less than $10 million, use zero balance);

TPC is Total Project Cost in millions of dollars;

HBRRP is Highway Bridge Replacement and Rehabilitation Program;

ADT' is ADT plus ADTT.

(c) In order to balance the relative importance of candidate bridges with very low (less than one) sufficiency ratings and very low ADT's against candidate bridges with high ADT's, the minimum sufficiency rating used will be 1.0. If the computed sufficiency rating for a candidate bridge is less than 1.0, use 1.0 in the rating factor formula.

(d) If the unobligated balance of HBRRP funds for the State is less than $10 million, the HBRRP modifier is 1.0. This will limit the effect of the modifier on those States with small apportionments or those who may be accumulating funds to finance a major bridge.

[48 FR 52296, Nov. 17, 1983; 48 FR 53407, Nov. 28, 1983]



§650.709   Special considerations.

(a) The selection process for new discretionary bridge projects will be based upon the rating factor priority ranking. However, although not specifically included in the rating factor formula, special consideration will be given to bridges that are closed to all traffic or that have a load restriction of less than 10 tons. Consideration will also be given to bridges with other unique situations, and to bridge candidates in States which have not previously been allocated discretionary bridge funds.

(b) The need to administer the program from a balanced national perspective requires that the special cases set forth in paragraph (a) of this section and other unique situations be considered in the discretionary bridge candidate evaluation process.

(c) Priority consideration will be given to the continuation and completion of bridge projects previously begun with discretionary bridge funds.

Subpart H -- Navigational Clearances for Bridges


Source: 52 FR 28139, July 28, 1987, unless otherwise noted.


§650.801   Purpose.

The purpose of this regulation is to establish policy and to set forth coordination procedures for Federal-aid highway bridges which require navigational clearances.


§650.803   Policy.

It is the policy of FHWA:

(a) To provide clearances which meet the reasonable needs of navigation and provide for cost-effective highway operations,

(b) To provide fixed bridges wherever practicable, and

(c) To consider appropriate pier protection and vehicular protective and warning systems on bridges subject to ship collisions.


§650.805   Bridges not requiring a USCG permit.

(a) The FHWA has the responsibility under 23 U.S.C. 144(h) to determine that a USCG permit is not required for bridge construction. This determination shall be made at an early stage of project development so that any necessary coordination can be accomplished during environmental processing.

(b) A USCG permit shall not be required if the FHWA determines that the proposed construction, reconstruction, rehabilitation, or replacement of the federally aided or assisted bridge is over waters (1) which are not used or are not susceptible to use in their natural condition or by reasonable improvement as a means to transport interstate or foreign commerce and (2) which are (i) not tidal, or (ii) if tidal, used only by recreational boating, fishing, and other small vessels less than 21 feet in length.

(c) The highway agency (HA) shall assess the need for a USCG permit or navigation lights or signals for proposed bridges. The HA shall consult the appropriate District Offices of the U.S. Army Corps of Engineers if the susceptibility to improvement for navigation of the water of concern is unknown and shall consult the USCG if the types of vessels using the waterway are unknown.

(d) For bridge crossings of waterways with navigational traffic where the HA believes that a USCG permit may not be required, the HA shall provide supporting information early in the environmental analysis stage of project development to enable the FHWA to make a determination that a USCG permit is not required and that proposed navigational clearances are reasonable.

(e) Since construction in waters exempt from a USCG permit may be subject to other USCG authorizations, such as approval of navigation lights and signals and timely notice to local mariners of waterway changes, the USCG should be notified whenever the proposed action may substantially affect local navigation.


§650.807   Bridges requiring a USCG permit.

(a) The USCG has the responsibility (1) to determine whether a USCG permit is required for the improvement or construction of a bridge over navigable waters except for the exemption exercised by FHWA in §650.805 and (2) to approve the bridge location, alignment and appropriate navigational clearances in all bridge permit applications.

(b) A USCG permit shall be required when a bridge crosses waters which are: (1) tidal and used by recreational boating, fishing, and other small vessels 21 feet or greater in length or (2) used or susceptible to use in their natural condition or by reasonable improvement as a means to transport interstate or foreign commerce. If it is determined that a USCG permit is required, the project shall be processed in accordance with the following procedures.

(c) The HA shall initiate coordination with the USCG at an early stage of project development and provide opportunity for the USCG to be involved throughout the environmental review process in accordance with 23 CFR part 771. The FHWA and Coast Guard have developed internal guidelines which set forth coordination procedures that both agencies have found useful in streamlining and expediting the permit approval process. These guidelines include (1) USCG/FHWA Procedures for Handling Projects which Require a USCG Permit 1 and (2) the USCG/FHWA Memorandum of Understanding on Coordinating The Preparation and Processing of Environmental Projects. 2

1This document is an internal directive in the USCG Bridge Administration Manual, Enclosure 1a, COMDT INST M16590.5, change 2 dated Dec. 1, 1983. It is available for inspection and copying from the U.S. Coast Guard or the Federal Highway Administration as prescribed in 49 CFR part 7, appendices B and D.

2FHWA Notice 6640.22 dated July 17, 1981, is available for inspection and copying as prescribed in 49 CFR part 7, appendix D.

(d) The HA shall accomplish sufficient preliminary design and consultation during the environmental phase of project development to investigate bridge concepts, including the feasibility of any proposed movable bridges, the horizontal and vertical clearances that may be required, and other location considerations which may affect navigation. At least one fixed bridge alternative shall be included with any proposal for a movable bridge to provide a comparative analysis of engineering, social, economic and environmental benefit and impacts.

(e) The HA shall consider hydraulic, safety, environmental and navigational needs along with highway costs when designing a proposed navigable waterway crossing.

(f) For bridges where the risk of ship collision is significant, HA's shall consider, in addition to USCG requirements, the need for pier protection and warning systems as outlined in FHWA Technical Advisory 5140.19, Pier Protection and Warning Systems for Bridges Subject to Ship Collisions, dated February 11, 1983.

(g) Special navigational clearances shall normally not be provided for accommodation of floating construction equipment of any type that is not required for navigation channel maintenance. If the navigational clearances are influenced by the needs of such equipment, the USCG should be consulted to determine the appropriate clearances to be provided.

(h) For projects which require FHWA approval of plans, specifications and estimates, preliminary bridge plans shall be approved at the appropriate level by FHWA for structural concepts, hydraulics, and navigational clearances prior to submission of the permit application.

(i) If the HA bid plans contain alternative designs for the same configuration (fixed or movable), the permit application shall be prepared in sufficient detail so that all alternatives can be evaluated by the USCG. If appropriate, the USCG will issue a permit for all alternatives. Within 30 days after award of the construction contract, the USCG shall be notified by the HA of the alternate which was selected. The USCG procedure for evaluating permit applications which contain alternates is presented in its Bridge Administration Manual (COMDT INST M16590.5). 3 The FHWA policy on alternates, Alternate Design for Bridges; Policy Statement, was published at 48 FR 21409 on May 12, 1983.

3United States Coast Guard internal directives are available for inspection and copying as prescribed in 49 CFR part 7, appendix B.


§650.809   Movable span bridges.

A fixed bridge shall be selected wherever practicable. If there are social, economic, environmental or engineering reasons which favor the selection of a movable bridge, a cost benefit analysis to support the need for the movable bridge shall he prepared as a part of the preliminary plans.




PART 652 -- PEDESTRIAN AND BICYCLE ACCOMMODATIONS AND PROJECTS


Sec.
652.1   Purpose.
652.3   Definitions.
652.5   Policy.
652.7   Eligibility.
652.9   Federal participation.
652.11   Planning.
652.13   Design and construction criteria.

Authority: 23 U.S.C. 109, 217, 315, 402(b)(1)(F); 49 CFR 1.48(b).

Source: 49 FR 10662, Mar. 22, 1984, unless otherwise noted.


§652.1   Purpose.

To provide policies and procedures relating to the provision of pedestrian and bicycle accommodations on Federal-aid projects, and Federal participation in the cost of these accommodations and projects.


§652.3   Definitions.

(a) Bicycle. A vehicle having two tandem wheels, propelled solely by human power, upon which any person or persons may ride.

(b) Bikeway. Any road, path, or way which in some manner is specifically designated as being open to bicycle travel, regardless of whether such facilities are designated for the exclusive use of bicycles or are to be shared with other transportation modes.

(c) Bicycle Path (Bike Path). A bikeway physically separated from motorized vehicular traffic by an open space or barrier and either within the highway right-of-way or within an independent right-of-way.

(d) Bicycle Lane (Bike Lane). A portion of a roadway which has been designated by striping, signing and pavement markings for the preferential or exclusive use of bicyclists.

(e) Bicycle Route (Bike Route). A segment of a system of bikeways designated by the jurisdiction having authority with appropriate directional and informational markers, with or without a specific bicycle route number.

(f) Shared Roadway. Any roadway upon which a bicycle lane is not designated and which may be legally used by bicycles regardless of whether such facility is specifically designated as a bikeway.

(g) Pedestrian Walkway or Walkway. A continuous way designated for pedestrians and separated from the through lanes for motor vehicles by space or barrier.

(h) Highway Construction Project. A project financed in whole or in part with Federal-aid or Federal funds for the construction, reconstruction or improvement of a highway or portions thereof, including bridges and tunnels.

(i) Independent Bicycle Construction Project (Independent Bicycle Project). A project designation used to distinguish a bicycle facility constructed independently and primarily for use by bicyclists from an improvement included as an incidental part of a highway construction project.

(j) Independent Pedestrian Walkway Construction Project (Independent Walkway Project). A project designation used to distinguish a walkway constructed independently and solely as a pedestrian walkway project from a pedestrian improvement included as an incidental part of a highway construction project.

(k) Incidental Bicycle or Pedestrian Walkway Construction Project (Incidental Feature). One constructed as an incidental part of a highway construction project.

(l) Nonconstruction Bicycle Project. A bicycle project not involving physical construction which enhances the safe use of bicycles for transportation purposes.

(m) Snowmobile. A motorized vehicle solely designed to operate on snow or ice.


§652.5   Policy.

The safe accommodation of pedestrians and bicyclists should be given full consideration during the development of Federal-aid highway projects, and during the construction of such projects. The special needs for the elderly and the handicapped shall be considered in all Federal-aid projects that include pedestrian facilities. Where current or anticipated pedestrian and/or bicycle traffic presents a potential conflict with motor vehicle traffic, every effort shall be made to minimize the detrimental effects on all highway users who share the facility. On highways without full control of access where a bridge deck is being replaced or rehabilitated, and where bicycles are permitted to operate at each end, the bridge shall be reconstructed so that bicycles can be safely accommodated when it can be done at a reasonable cost. Consultation with local groups of organized bicyclists is to be encouraged in the development of bicycle projects.


§652.7   Eligibility.

(a) Independent bicycle projects, incidental bicycle projects, and nonconstruction bicycle projects must be principally for transportation rather than recreational use and must meet the project conditions for authorization where applicable.

(b) The implementation of pedestrian and bicycle accommodations may be authorized for Federal-aid participation as either incidental features of highways or as independent projects where all of the following conditions are satisfied.

(1) The safety of the motorist, bicyclist, and/or pedestrian will be enhanced by the project.

(2) The project is initiated or supported by the appropriate State highway agency(ies) and/or the Federal land management agency. Projects are to be located and designed pursuant to an overall plan, which provides due consideration for safety and contiguous routes.

(3) A public agency has formally agreed to:

(i) Accept the responsibility for the operation and maintenance of the facility,

(ii) Ban all motorized vehicles other than maintenance vehicles, or snowmobiles where permitted by State or local regulations, from pedestrian walkways and bicycle paths, and

(iii) Ban parking, except in the case of emergency, from bicycle lanes that are contiguous to traffic lanes.

(4) The estimated cost of the project is consistent with the anticipated benefits to the community.

(5) The project will be designed in substantial conformity with the latest official design criteria. (See §652.13.)

[49 FR 10662, Mar. 22, 1984; 49 FR 14729, Apr. 13, 1984]



§652.9   Federal participation.

(a) Independent walkway projects, independent bicycle projects and nonconstruction bicycle projects shall be financed with 100 percent Federal-aid primary, secondary or urban highway funds, provided the total amount obligated for all such projects in any one State in any fiscal year does not exceed $4.5 million of Federal-aid funds or a lesser amount apportioned by the Federal Highway Administrator to avoid exceeding the annual $45 million cost limitation on these projects for all States in a fiscal year. The Federal Highway Administrator may, upon application, waive this limitation for a State for any fiscal year. This limitation also applies to projects funded under §652.9(d). This limitation does not apply to projects of the type described in §652.9(c). The FHWA Offices of Direct Federal Programs and Engineering will coordinate projects of the type described in §652.9(d) to ensure that the annual cost limitations will not be exceeded.

(b) Specific eligibility requirements for Federal-aid participation in independent and nonconstruction projects are:

(1) An independent walkway project must be constructed on highway right-of-way or easement, or right-of-way acquired for this purpose. Independent walkway projects may be constructed separately or in conjunction with a Federal-aid highway construction project. Where an independent walkway project is located away from the Federal-aid highway right-of-way, it must serve pedestrians who would normally desire to use the Federal-aid route.

(2) An independent bicycle project may include the acquisition of land needed for the facility, or such projects may be constructed on existing highway right-of-way or easement acquired for this purpose. Independent bicycle projects may include construction of bicycle lanes, paths, shelters, bicycle parking facilities and other roadway and bridge work necessary to accommodate bicyclists.

(3) Nonconstruction bicycle projects must be related to the safe use of bicycles for transportation, and may include safety educational material and route maps for safe bicycle transportation purposes. Nonconstruction bicycle projects shall not include salaries for administration, law enforcement, maintenance and similar items required to operate transportation networks and programs, but may include cost of staff or consultants for development of specific nonconstruction projects.

(c) Bicycle and pedestrian accommodations may also be constructed as incidental features of highway construction projects. These incidental features may be financed with the same type of Federal-aid funds, including funds of the type described in §652.9(d) (except Interstate construction funds) and at the same Federal share payable as a basic highway project. These accommodations are not subject to the funding limitations for independent walkway, independent bicycle and nonconstruction bicycle projects. In the case of the Interstate construction projects, Federal-aid Interstate construction funds may only be used to replace existing facilities that would be interrupted by construction of the project, or to mitigate specific environmental impacts. Interstate 4R funds provided by 23 U.S.C. 104(b)(5)(B) may be used only for incidental features. As incidental features, these accommodations must be part of a highway improvement and must be located within the right-of-way of the highway, including land acquired under 23 U.S.C. 319 (Scenic Enhancement Program).

(d) Funds authorized for Federal lands highways (forest highways, public lands highways, park roads, parkways, and Indian reservation roads which are public roads), forest development roads and trails (i.e., roads or trails under the jurisdiction of the Forest Service), and public lands development roads and trails (i.e., roads or trails which the Secretary of the Interior determines are of primary importance for the development, protection, administration, and utilization of public lands and resources under his/her control), may be used for independent bicycle routes and independent walkway projects. These funds may not be used for nonconstruction bicycle projects.


§652.11   Planning.

Federally aided bicycle and pedestrian projects implemented within urbanized areas must be included in the transportation improvement program/annual (or biennial) element unless excluded by agreement between the State and the metropolitan planning organization.


§652.13   Design and construction criteria.

(a) The American Association of State Highway and Transportation Officials' "Guide for Development of New Bicycle Facilities, 1981" (AASHTO Guide) or equivalent guides developed in cooperation with State or local officials and acceptable to the division office of the FHWA, shall be used as standards for the construction and design of bicycle routes. Copies of the AASHTO Guide may be obtained from the American Association of State Highway and Transportation Officials, 444 North Capitol Street, NW., Suite 225, Washington, DC 20001.

(b) Curb cuts and other provisions as may be appropriate for the handicapped are required on all Federal and Federal-aid projects involving the provision of curbs or sidewalks at all pedestrian crosswalks.




PART 655 -- TRAFFIC OPERATIONS



Subparts A-E [Reserved]


Subpart F -- Traffic Control Devices on Federal-Aid and Other Streets and Highways

655.601   Purpose.
655.602   Definitions.
655.603   Standards.
655.604   Achieving basic uniformity.
655.605   Project procedures.
655.606   Higher cost materials.
655.607   Funding.
Appendix to Subpart F -- Alternate Method of Determining the Color of Retroreflective Sign Materials

Subpart G [Reserved]

Authority: 23 U.S.C. 101(a), 104, 109(d), 114(a), 217, 315, and 402(a); 23 CFR 1.32 and; 49 CFR 1.48(b).



Subparts A-E [Reserved]

Subpart F -- Traffic Control Devices on Federal-Aid and Other Streets and Highways


Source: 48 FR 46776, Oct. 14, 1983, unless otherwise noted.


§655.601   Purpose.

To prescribe the policies and procedures of the Federal Highway Administration (FHWA) to obtain basic uniformity of traffic control devices on all streets and highways in accordance with the following references that are approved by the FHWA for application on Federal-aid projects:

(a) Manual on Uniform Traffic Control Devices (MUTCD), 2000 Millennium Edition, FHWA dated December, 2000. This publication is incorporated by reference in accordance with 5 U.S.C. 552(a) and 1 CFR part 51 and is on file at the Office of the Federal Register, 800 North Capitol Street, NW., Suite 700, Washington, DC. It is available for inspection and copying at FHWA, 400 Seventh Street, SW., Room 3408, Washington, DC 20590, as provided in 49 CFR part 7. The text is also available from the FHWA Office of Transportation Operations' web site at: http://mutcd.fhwa.dot.gov.

(b) Standard Alphabets for Highway Signs, FHWA, 1966 Edition, Reprinted May 1972. (This publication is incorporated by reference and is on file at the Office of the Federal Register in Washington, DC. This document is available for inspection and copying as provided in 49 CFR part 7, appendix D).

(c) Guide to Metric Conversion, AASHTO, 1993. This publication is incorporated by reference in accordance with 5 U.S.C. 552(a) and 1 CFR part 51 and is on file at the Office of the Federal Register, 800 North Capitol Street, NW., Suite 700, Washington, DC. This document is available for inspection as provided in 49 CFR part 7. It may be purchased from the American Association of State Highway and Transportation Officials, Suite 249, 444 North Capitol Street, NW., Washington, DC 20001.

(d) Traffic Engineering Metric Conversion Factors, 1993 -- Addendum to the Guide to Metric Conversion, AASHTO, October 1993. This publication is incorporated by reference in accordance with 5 U.S.C. 552(a) and 1 CFR part 51 and is on file at the Office of the Federal Register, 800 North Capitol Street, NW., Suite 700, Washington, DC. This document is available for inspection as provided in 49 CFR part 7. It may be purchased from the American Association of State Highway and Transportation Officials, Suite 249, 444 North Capitol Street, NW., Washington, DC 20001.

[51 FR 16834, May 7, 1986, as amended at 60 FR 18521, Apr. 11, 1995; 61 FR 29626, June 11, 1996; 62 FR 1373, Jan. 9, 1997; 63 FR 8351, Feb. 19, 1998; 63 FR 33549, June 19, 1998; 64 FR 33753, June 24, 1999; 65 FR 13, Jan. 3, 2000; 65 FR 78958, Dec. 18, 2000]



§655.602   Definitions.

The terms used herein are defined in accordance with definitions and usages contained in the MUTCD and 23 U.S.C. 101(a).


§655.603   Standards.

(a) National MUTCD. The MUTCD approved by the Federal Highway Administrator is the national standard for all traffic control devices installed on any street, highway, or bicycle trail open to public travel in accordance with 23 U.S.C 109(d) and 402(a). The national MUTCD is specifically approved by the FHWA for application on any highway project in which Federal highway funds participate and on projects in federally administered areas where a Federal department or agency controls the highway or supervises the traffic operations.

(b) State or other Federal MUTCD. (1) Where State or other Federal agency MUTCDs or supplements are required, they shall be in substantial conformance with the national MUTCD. Changes to the national MUTCD issued by the FHWA shall be adopted by the States or other Federal agencies within 2 years of issuance. The FHWA Regional Administrator has been delegated the authority to approve State MUTCDs and supplements.

(2) The Direct Federal Program Administrator has been delegated the authority to approve other Federal agency MUTCDs with the concurrence of the Office of Traffic Operations. States and other Federal agencies are encouraged to adopt the national MUTCD as their official Manual on Uniform Traffic Control Devices.

(c) Color specifications. Color determinations and specifications of sign and pavement marking materials shall conform to requirements of the FHWA Color Tolerance Charts. 2 An alternate method of determining the color of retroreflective sign material is provided in the appendix.

2Available for inspection from the Office of Traffic Operations, Federal Highway Administration, 400 Seventh Street, SW., Washington, DC 20590.

(d) Compliance -- (1) Existing highways. Each State, in cooperation with its political subdivisions, and Federal agencies shall have a program as required by Highway Safety Program Standard Number 13, Traffic Engineering Services (23 CFR 1204.4) which shall include provisions for the systematic upgrading of substandard traffic control devices and for the installation of needed devices to achieve conformity with the MUTCD.

(2) New or reconstructed highways. Federal-aid projects for the construction, reconstruction, resurfacing, restoration, or rehabilitation of streets and highways shall not be opened to the public for unrestricted use until all appropriate traffic control devices, either temporary or permanent, are installed and functioning properly. Both temporary and permanent devices shall conform to the MUTCD.

(3) Construction area activities. All traffic control devices installed in construction areas using Federal-aid funds shall conform to the MUTCD. Traffic control plans for handling traffic and pedestrians in construction zones and for protection of workers shall conform to the requirements of 23 CFR part 630, subpart J, Traffic Safety in Highway and Street Work Zones.

(4) MUTCD changes. The FHWA may establish target dates for achieving compliance with changes to specific devices in the MUTCD.

(e) Specific information signs. Standards for specific information signs are contained in the MUTCD.

[48 FR 46776, Oct. 14, 1983, as amended at 51 FR 16834, May 7, 1986]



§655.604   Achieving basic uniformity.

(a) Programs. Programs for the orderly and systematic upgrading of existing traffic control devices or the installation of needed traffic control devices on or off the Federal-aid system should be based on inventories made in accordance with 23 CFR 1204.4, Highway Safety Program Standards. These inventories provide the information necessary for programming traffic control device upgrading projects.

(b) Inventory. An inventory of all traffic control devices is required by Highway Safety Program Standard Number 13, Traffic Engineering Services (23 CFR 1204.4). Highway planning and research funds and highway related safety grant program funds may be used in statewide or systemwide studies or inventories. Also, metropolitan planning (PL) funds may be used in urbanized areas provided the activity is included in an approved unified work program.


§655.605  

Project procedures.

(a) Federal-aid highways. Federal-aid projects involving the installation of traffic control devices shall follow procedures as established in 23 CFR part 630, subpart A, Federal-Aid Programs Approval and Project Authorization. Simplified and timesaving procedures are to be used to the extent permitted by existing policy.

(b) Off-system highways. Certain federally funded programs are available for installation of traffic control devices on streets and highways that are not on the Federal-aid system. The procedures used in these programs may vary from project to project but, essentially, the guidelines set forth herein should be used.


§655.606   Higher cost materials.

The use of signing, pavement marking, and signal materials (or equipment) having distinctive performance characteristics, but costing more than other materials (or equipment) commonly used may be approved by the FHWA Division Administrator when the specific use proposed is considered to be in the public interest.


§655.607   Funding.

(a) Federal-aid highways. (1) Funds apportioned or allocated under 23 U.S.C. 104(b) are eligible to participate in projects to install traffic control devices in accordance with the MUTCD on newly constructed, reconstructed, resurfaced, restored, or rehabilitated highways, or on existing highways when this work is classified as construction in accordance with 23 U.S.C. 101(a). Federal-aid highway funds for eligible pavement markings and traffic control signalization may amount to 100 percent of the construction cost. Federal-aid highway funds apportioned or allocated under other sections of 23 U.S.C. are eligible for participation in improvements conforming to the MUTCD in accordance with the provisions of applicable program regulations and directives.

(2) Traffic control devices are eligible, in keeping with paragraph (a)(1) of this section, provided that the work is classified as construction in accordance with 23 U.S.C. 101(a) and the State or local agency has a policy acceptable to the FHWA Division Administrator for selecting traffic control devices material or equipment based on items such as cost, traffic volumes, safety, and expected service life. The State's policy should provide for cost-effective selection of materials which will provide for substantial service life taking into account expected and necessary routine maintenance. For these purposes, effectiveness would normally be measured in terms of durability, service life and/or performance of the material. Specific projects including material or equipment selection shall be developed in accordance with this policy. Proposed work may be approved on a project-by-project basis when the work is (i) clearly warranted, (ii) on a Federal-aid system, (iii) clearly identified by site, (iv) substantial in nature, and (v) of sufficient magnitude at any given location to warrant Federal-aid participation as a construction item.

(3) The method of accomplishing the work will be in accordance with 23 CFR part 635, subpart A, Contract Procedures.

(b) Off-system highways. Certain Federal-aid highway funds are eligible to participate in traffic control device improvement projects on off-system highways. In addition, Federal-aid highway funds apportioned or allocated in 23 U.S.C. are eligible for the installation of traffic control devices on any public road not on the Federal-aid system when the installation is directly related to a traffic improvement project on a Federal-aid system route.

Appendix to Subpart F of Part 655 -- Alternate Method of Determining the Color of Retroreflective Sign Materials

1. The FHWA Color Tolerance Charts provide that conventional color measuring instruments such as spectrophotometers and tristimulus photoelectric colorimeters should not be used for measurement of retroreflective material colors and that such materials should be evaluated visually using the Color Tolerance Charts and paying strict attention to prescribed illumination and viewing conditions.

2. As an alternate to visual testing, the diffuse day color of retroreflective sign material may be determined in accordance with ASTM E 97, "Standard Method of Test for 45-Degree, 0-Degree Directional Reflectance of Opaque Specimens by Filter Photometry." Geometric characteristics must be confined to illumination incident within 10 degrees of, and centered about, a direction of 45 degrees from the perpendicular to the test surface; viewing is within 15 degrees of, and centered about, the perpendicular to the test surface. Conditions of illumination and observation must not be interchanged.

3. Standards to be used for reference are the Munsell Papers designated in Table 1 or Table II, attached. The papers must be recently calibrated on a spectrophotometer. Acceptable test instruments are:

a. Gardner Multipurpose Reflectometer or Model XL 20 Color Difference Meter,

b. Gardner Model Ac-2a or XL 30 Color Difference Meter,

c. Meeco Model V Colormaster,

d. Hunter lab D25 Color Difference Meter, or

e. Approved equal.

4. Average performance sheeting is identified as Types I and II sheeting and high performance sheeting is identified as Types III and IV sheeting in Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects 3 (FP-79, Section 633).

3This document is available for inspection and copying as prescribed in 49 CFR part 7, appendix D.

                 Table I--Color Specification Limits and Reference Standards, Types I and II Sheeting
--------------------------------------------------------------------------------------------------------------------------------------------------------
                           Chromaticity coordinates\1\ (corner points)       Reflectance
                     ---------------------------------------------------------------- limits (percent
         Color              1        2        3        4       Y) Y      Reference\3\ standard
                     ---------------------------------------------------------------------------------    (munsell papers)
                       x    y    x    y    x    y    x    y  Minium Maximum
--------------------------------------------------------------------------------------------------------------------------------------------------------
White\2\.................................  .305  .290  .350  .342  .321  .361  .276  .308   35    -- 6.3Gy 6.77/0.8.
Red......................................  .602  .317  .664  .336  .644  .356  .575  .356    8    12 8.2R 3.78/14.0.
Orange...................................  .535  .375  .607  .393  .582  .417  .535  .399   18    30 2.5YR 5.5/14.0
Brown....................................  .445  .353  .604  .396  .556  .443  .445  .386    4    9 5.OYR 3/6.
Yellow...................................  .482  .450  .532  .465  .505  .494  .475  .485   29    45 1.25Y 6/12.
Green....................................  .130  .369  .180  .391  .155  .460  .107  .439   3.5    9 0.65BG 2.84/8.45.
Blue.....................................  .147  .075  .176  .091  .176  .151  .106  .113   1.0    4 5 8PB 1.32/6.8.
--------------------------------------------------------------------------------------------------------------------------------------------------------
\1\The four pairs of chromaticity coordinates determine the acceptable color in terms of the CIE 1931 standard colorimetric system measured with
 standard illumination source C.
\2\Silver white is an acceptable color designation.
\3\Available from Munsell Color Company. 2441 Calvert Street, Baltimore. Maryland 21218.
                 Table II--Color Specification Limits and Reference Standards, Types III and IV Sheeting
--------------------------------------------------------------------------------------------------------------------------------------------------------
                           Chromaticity Coordinates\1\ (corner points)       Reflectance
                      ----------------------------------------------------------------   limits
          Color              1        2        3        4     (percent Y) Y   Reference\3\ standard
                      --------------------------------------------------------------------------------    (munsell papers)
                        x    y    x    y    x    y    x    y   Min.  Max.
--------------------------------------------------------------------------------------------------------------------------------------------------------
White\2\..................................  .303   287  .368  .353  .340  .380  .274  .316   27 ...... 5.0PB 7/1.
Red.......................................  .613  .297  .708  .292  .636  .364  .558  .352   2.5   11 7.5R 3/12.
Orange....................................  .550  .360  .630  .370  .581  .418  .516  .394   14   30 2.5YR 5.5/14.
Yellow....................................  .498  .412  .557  .442  .479  .520  .438  .472   15   40 1.25Y 6/12.
Green.....................................  .030  .380  .166  .346  .286  .428  .201  .776    3    8 10G 3/8
Blue......................................  .144  .030  .244  .202  .190  .247  .066  .208    1   10 5.8PB 1.32/6.8.
--------------------------------------------------------------------------------------------------------------------------------------------------------
\1\The four pairs of chromaticity coordinates determine the acceptable color in terms of the CIE 1931 standard colorimetric system measured with
 standard illumination source C.
\2\Silver white is an acceptable color designation.
\3\Available from Munsell Color Company, 2441 Calvert Street, Baltimore, Maryland 21218.


Subpart G [Reserved]



PART 656 -- CARPOOL AND VANPOOL PROJECTS


Sec.
656.1   Purpose.
656.3   Policy.
656.5   Eligibility.
656.7   Determination of an exception.

Authority: 23 U.S.C. 146 and 315; sec. 126 of the Surface Transportation Assistance Act of 1978, Pub. L. 95-599, 92 Stat. 2689; 49 CFR 1.48(b).

Source: 47 FR 43024, Sept. 30, 1982, unless otherwise noted.


§656.1   Purpose.

The purpose of this regulation is to prescribe policies and general procedures for administering a program of ridesharing projects using Federal-aid primary, secondary, and urban system funds.


§656.3   Policy.

Section 126(d) of the Surface Transportation Assistance Act of 1978 declares that special effort should be made to promote commuter modes of transportation which conserve energy, reduce pollution, and reduce traffic congestion.


§656.5   Eligibility.

(a) Projects which promote ridesharing programs need not be located on but must serve a Federal-aid system to be eligible for Federal-aid primary, secondary, or urban system funds depending on the system served. The Federal share payable will be in accordance with the provisions of 23 U.S.C. 120. Except for paragraph (c)(3) of this section, for all purposes of this regulation the term carpool includes vanpool.

(b) Projects shall not be approved under this regulation if they will have an adverse effect on any mass transportation system.

(c) The following types of projects and work are considered eligible under this program:

(1) Systems, whether manual or computerized, for locating potential participants in carpools and informing them of the oppportunities for participation. Eligible costs for such systems may include costs of use or rental of computer hardware, costs of software, and installation costs (including both labor and other related items).

(2) Specialized procedures to provide carpooling opportunities to elderly or handicapped persons.

(3) The costs of acquiring vanpool vehicles and actual financial losses that occur when the operation of any vanpool is aborted before the scheduled termination date for the reason, concurred in by the State, that its continuation is no longer productive. The cost of acquiring a vanpool vehicle is eligible under the following conditions:

(i) The vanpool vehicle is a four-wheeled vehicle manufactured for use on public highways for transportation of 7-15 passengers (no passenger cars which do not meet the 7 -- 15 criteria and no buses); and

(ii) Provision is made for repayment of the acquisition cost to the project within the passenger-service life of the vehicle. Repayment may be accomplished through the charging of a reasonable user fee based on an estimated number of riders per vehicle and the cost of reasonable vehicle depreciation, operation, and maintenance. Repayment is not required under the following conditions:

(A) When vehicles are purchased as demonstrator vans for use as a marketing device. Vehicles procured for this purpose should be used to promote the vanpool concept among employees, employers, and other groups by allowing potential riders and sponsors to examine commuter vans; or

(B) When vehicles are purchased for use on a trial commuting basis to enable people to experience vanpooling first hand. The trial period must be limited to a maximum of 2 months. That part of the user fee normally collected to cover the capital or ownership cost of the van would be eligible for reimbursement as a promotional cost during the limited trial period. As with established vanpool service, all vehicle operating costs must be borne by the user(s) during the trial period.

(4) Work necessary to designate existing highway lanes as preferential carpool lanes or bus and carpool lanes. Eligible work may include preliminary engineering to determine traffic flow and design criteria, signing, pavement markings, traffic control devices, and minor physical modifications to permit the use of designated lanes as preferential carpool lanes or bus and carpool lanes. Such improvements on any public road may be approved if such projects facilitate more efficient use of any Federal-aid highway. Eligible costs may also include costs of initial inspection or monitoring of use, including special equipment, to ensure that the high occupancy vehicle (HOV) lanes designation is effective and that the project is fully developed and operating properly. While no fixed time limit is being arbitrarily prescribed for the inspection and monitoring period, it is intended that this activity be conducted as soon as possible to evaluate the effectiveness of the project and does not extend indefinitely nor become a part of routine facility operations.

(5) Signing of and modifications to existing facilities to provide preferential parking for carpools inside or outside the central business district. Eligible costs may include trail blazers, on-site signs designating highway interchange areas or other existing publicly or privately owned facilities as preferential parking for carpool participants, and initial or renewal costs for leasing parking space or acquisition or easements or restrictions, as, for example, at shopping centers and public or private parking facilities. The lease or acquisition cost may be computed on the demonstrated reduction in the overall number of vehicles using the designated portion of a commercial facility, but not on a reduction of the per-vehicle user charge for parking.

(6) Construction of carpool parking facilities outside the central business district. Eligible costs may include acquisition of land and normal construction activities, including installation of lighting and fencing, trail blazers, on-site signing, and passenger shelters. Such facilities need not be located in conjunction with any existing or planned mass transportation service, but should be designed so that the facility could accommodate mass transportation in the event such service may be developed. Except for the requirement of the availability of mass/public transportation facilities, fringe parking construction under this section shall be subject to the provisions of 23 CFR part 810.106.

(7) Reasonable public information and promotion expenses, including personnel costs, incurred in connection with any of the other eligible items mentioned herein.


§656.7   Determination of an exception.

(a) The FHWA has determined under provisions of 23 U.S.C. 146(b) that an exceptional situation exists in regard to the funding of carpools so as to allow the State to contribute as its share of the non-Federal match essential project-related work and services performed by local agencies and private organizations when approved and authorized in accordance with regular Federal-aid procedures. The cost of such work must be properly valued, supportable and verifiable in order for inclusion as an eligible project cost. Examples of such contributed work and services include: public service announcements, computer services, and project-related staff time for administration by employees of public and private organizations.

(b) This determination is based on: (1) The nature of carpool projects to provide a variety of services to the public; (2) the fact that carpool projects are labor intensive and require professional and specialized technical skills; (3) the extensive use of joint public and private endeavors; and (4) the fact that project costs involve the acquisition of capital equipment as opposed to construction of fixed items.

(c) This exception is limited to carpool projects and therefore is not applicable to other Federal-aid projects. The exception does not affect or replace the standard Federal-aid funding procedures or real property acquisition procedures and requirements, part 712, The Acquisition Function.




PART 657 -- CERTIFICATION OF SIZE AND WEIGHT ENFORCEMENT


Sec.
657.1   Purpose.
657.3   Definition.
657.5   Policy.
657.7   Objective.
657.9   Formulation of a plan for enforcement.
657.11   Evaluation of operations.
657.13   Certification requirement.
657.15   Certification content.
657.17   Certification submittal.
657.19   Effect of failure to certify or to enforce State laws adequately.
657.21   Procedure for reduction of funds.

Appendix to Part 657 -- Guidelines To Be Used in Developing Enforcement Plans and Certification Evaluation

Authority: Sec. 123, Pub. L. 95-599, 92 Stat. 2689; 23 U.S.C. 127, 141, and 315; 49 U.S.C. 31111, 31113, and 31114; sec. 1023, Pub. L. 102-240, 105 Stat. 1914; and 49 CFR 1.48(b)(19), (b)(23), (c)(1), and (c)(19).

Source: 45 FR 52368, Aug. 7, 1980, as amended at 62 FR 62261, Nov. 21, 1997, unless otherwise noted.

Note: The recordkeeping requirements contained in this part have been approved by the Office of Management and Budget under control number 2125-0034.


§657.1   Purpose.

To prescribe requirements for administering a program of vehicle size and weight enforcement on Federal-aid (FA) highways, including the required annual certification by the State.


§657.3   Definition.

Enforcing or enforcement means all actions by the State to obtain compliance with size and weight requirements by all vehicles operating on the FA Interstate, primary, urban, and secondary systems.


§657.5   Policy.

Federal Highway Administration (FHWA) policy is that each State enforce vehicle size and weight laws to assure that violations are discouraged and that vehicles traversing the highway system do not exceed the limits specified by law. These size and weight limits are based upon design specifications and safety considerations, and enforcement shall be developed and maintained both to prevent premature deterioration of the highway pavement and structures and to provide a safe driving environment.


§657.7   Objective.

The objective of this regulation is the development and operation by each State of an enforcement process which identifies vehicles of excessive size and weight and provides a systematic approach to eliminate violations and thus improve conditions.


§657.9   Formulation of a plan for enforcement.

(a) Each State shall develop a plan for the maintenance of an effective enforcement process. The plan shall describe the procedures, resources, and facilities which the State intends to devote to the enforcement of its vehicle size and weight laws. Each State plan must be accepted by the FHWA and will then serve as a basis by which the annual certification of enforcement will be judged for adequacy.

(b) The plan shall discuss the following subjects:

(1) Facilities and resources. (i) No program shall be approved which does not utilize a combination of at least two of the following listed devices to deter evasion of size and weight measurement in sufficient quantity to cover the FA system: fixed platform scales; portable wheel weigher scales; semiportable or ramp scales; WIM equipment.

(ii) Staff assigned to the program, identified by specific agency. Where more than one State agency has weight enforcement responsibility, the lead agency should be indicated.

(2) Practices and procedures. (i) Proposed plan of operation, including geographical coverage and hours of operation in general terms.

(ii) Policy and practices with respect to overweight violators, including off-loading requirements for divisible loads. In those States in which off-loading is mandatory by law, an administrative variance from the legal requirement shall be fully explained. In those States in which off-loading is permissive administrative guidelines shall be included.

(iii) Policy and practices with respect to penalties, including those for repeated violations. Administrative directives, booklets or other written criteria shall be made part of the plan submission.

(iv) Policy and practices with respect to special permits for overweight. Administrative directives, booklets or other written criteria shall be made part of the plan submission.

(3) Updating. Modification and/or additions to the plan based on experience and new developments in the enforcement program. It is recognized that the plan is not static and that changes may be required to meet changing needs.


§657.11   Evaluation of operations.

(a) The State shall submit its enforcement plan or annual update to the Office of Motor Carriers in the FHWA division office by July 1 of each year. However, if a State's legislative or budgetary cycle is not consonant with that date, the FHWA and the State may jointly select an alternate date. In any event, a State must have an approved plan in effect by October 1 of each year. Failure of a State to submit or update a plan will result in the State being unable to certify in accordance with §657.13 for the period to be covered by the plan.

(b) The Office of Motor Carriers in the FHWA division office shall review the State's operation under the accepted plan on a continuing basis and shall prepare an evaluation report annually. The State will be advised of the results of the evaluation and of any needed changes either in the plan itself or in its implementation. Copies of the evaluation report and subsequent modifications resulting from the evaluation shall be forwarded through the Regional Director of Motor Carriers to the Washington, D.C., Headquarters office.

[59 FR 30418, June 13, 1994]



§657.13   Certification requirement.

Each State shall certify to the Federal Highway Administrator, before January 1 of each year, that it is enforcing all State laws respecting maximum vehicle size and weight permitted on what, prior to October 1, 1991, were the Federal-aid Primary, Secondary, and Urban Systems, including the Interstate System, in accordance with 23 U.S.C. 127. The States must also certify that they are enforcing and complying with the ISTEA freeze on the use of LCV's and other multi-unit vehicles. The certification shall be supported by information on activities and results achieved during the preceding 12-month period ending on September 30 of each year.

[59 FR 30418, June 13, 1994]



§657.15   Certification content.

The certification shall consist of the following elements and each element shall be addressed even though the response is negative:

(a) A statement by the Governor of the State, or an official designated by the Governor, that the State's vehicle weight laws and regulations governing use of the Interstate System conform to 23 U.S.C. 127.

(b) A statement by the Governor of the State, or an official designated by the Governor, that all State size and weight limits are being enforced on the Interstate System and those routes which prior to October 1, 1991, were designated as part of the Federal-aid Primary, Urban, and Secondary Systems, and that the State is enforcing and complying with the provisions of 23 U.S.C. 127(d) and 49 U.S.C. 31112 Urbanized areas not subject to State jurisdiction shall be identified. The statement shall include an analysis of enforcement efforts in such areas.

(c) Except for Alaska and Puerto Rico, the certifying statements required by paragraphs (a) and (b) of this section shall be worded as follows (the statements for Alaska and Puerto Rico do not have to reference 23 U.S.C. 127(d) in (c)(2), or include paragraph (c)(3) of this section):

I, (name of certifying official), (position title), of the State of _______ do hereby certify:
(1) That all State laws and regulations governing vehicle size and weight are being enforced on those highways which, prior to October 1, 1991, were designated as part of the Federal-aid Primary, Federal-aid Secondary, or Federal-aid Urban Systems;

(2) That the State is enforcing the freeze provisions of the Intermodal Surface Transportation Efficiency Act of 1991 (23 U.S.C. 127(d) and 49 U.S.C. 31112); and

(3) That all State laws governing vehicle weight on the Interstate System are consistent with 23 U.S.C. 127 (a) and (b).

(d) If this statement is made by an official other than the Governor, a copy of the document designating the official, signed by the Governor, shall also be included in the certification made under this part.

(e) A copy of any State law or regulation pertaining to vehicle sizes and weights adopted since the State's last certification and an analysis of the changes made. Those laws and regulations pertaining to special permits and penalties shall be specifically identified and analyzed in accordance with section 123 of the Surface Transportation Assistance Act of 1978 (Pub. L. 95-599).

(f) A report of State size and weight enforcement efforts during the period covered by the certification which addresses the following:

(1) Actual operations as compared with those forecast by the plan submitted earlier, with particular attention to changes in or deviations from the operations proposed.

(2) Impacts of the process as actually applied, in terms of changes in the number of oversize and/or overweight vehicles.

(3) Measures of activity -- (i) Vehicles weighed. Separate totals shall be reported for the annual number of vehicles weighed on fixed scales, on semiportable scales, on portable scales, and on WIM when used for enforcement.

(ii) Penalties. Penalties reported shall include the number of citations or civil assessments issued for violations of each of the following: Axle, gross and bridge formula weight limits. The number of vehicles whose loads are either shifted or offloaded must also be reported.

(iii) Permits. The number of permits issued for overweight loads shall be reported. The reported numbers shall specify permits for divisible and nondivisible loads and whether issued on a trip or annual basis. Permits issued for excess height, length, or width need not be reported except where issued for the overwidth movement of a divisible load.

[59 FR 30418, June 13, 1994, as amended at 62 FR 10181, Mar. 5, 1997]



§657.17   Certification submittal.

(a) The Governor, or an official designated by the Governor, shall submit the certification to the Office of Motor Carriers in the FHWA division office prior to January 1 of each year.

(b) The Office of Motor Carriers in the FHWA division office shall forward the original certification to the Associate Administrator for Motor Carriers and one copy to the Office of Chief Counsel. Copies of appropriate evaluations and/or comments shall accompany any transmittal.

[59 FR 30418, June 13, 1994]



§657.19   Effect of failure to certify or to enforce State laws adequately.

Beginning January 1, 1981, if a State fails to certify as required by this regulation or if the Secretary determines that a State is not adequately enforcing all State laws respecting maximum vehicle sizes and weights on FA highways notwithstanding the State's certification, the FA highway funds apportioned to the State for the next fiscal year shall be reduced by an amount equal to 10 percent of the amount which would otherwise be apportioned to the State under 23 U.S.C. 104, and/or by the amount required pursuant to 23 U.S.C. 127.


§657.21   Procedure for reduction of funds.

(a) If it appears to the Federal Highway Administrator that a State has not submitted a certification conforming to the requirements of this regulation, or that the State is not adequately enforcing State laws respecting maximum vehicle size and weight, including laws applicable to vehicles using the Interstate System with weights or widths in excess of those provided under 23 U.S.C. 127, the Federal Highway Administrator shall make in writing a proposed determination of nonconformity, and shall notify the Governor of the State of the proposed determination by certified mail. The notice shall state the reasons for the proposed determination and inform t