Location |
Washington, DC |
Project Sponsor / Borrower |
District Department of Transportation (DDOT) |
Program Areas |
|
Fiscal Year Approved |
Fiscal Year 2011 |
Mode |
Bridge |
Description |
The Eleventh Street Bridge Project is replacing the existing twin bridges that carry I-295 over the Anacostia River in the southeast quadrant of the District. Three new bridges are being constructed and improvements being made to the interchanges at both ends, including adding missing movements to and from the north onto the Anacostia Freeway (I-295/DC 295). The project will:
|
Cost |
Total project cost: $309.2 million
|
Funding Sources |
Federal funds:
Local funds:
|
Project Delivery / Contract Method |
Design-Build |
Private Partner |
Design-builder: Skanska/Facchina |
Project Advisors / Consultants |
Phoenix Capital Partners, LLP - Financial Advisor |
Lenders |
Bondholders |
Duration / Status |
Construction began December 2009; expected completion summer 2013 |
Financial Status |
Closed |
Innovations |
|
Related Links / Articles |
DDOT Project Website |
Contacts |
Bryon Johnston |
1 Of this total, $454.3 represents TIFIA Eligible Project Costs.
2 Railroad Rehabilitation & Improvement Financing