Skip to contentU.S. Department of Transportation, Federal Highway Administration FHWA HomeFeedback
Planning
Previous Home Next

Pennsylvania

Planning Context

The Pennsylvania Department of Transportation (PENNDOT) began an effort in 1997 to redesign the statewide transportation planning and programming processes. According to PENNDOT contacts, these efforts were to a great degree encouraged and supported by the federal emphasis in ISTEA and TEA-21 on comprehensive statewide planning. PENNDOT describes the redesigned process as "the most collaborative and cooperative planning and programming process in the nation" (Pennsylvania's 2003 Transportation Program Financial Guidance).

In a critical early step in redesign of the statewide planning process, PENNDOT organized a series of workshops with the state's fourteen MPOs and six Local Development Districts (LDDs). These workshops allowed State and regional agencies to exchange ideas and set the stage for the redesign.

PENNDOT next established an advisory committee of representatives from the MPOs, LDDs, FHWA, FTA, the public, the State Transportation Commission, and rail, freight, and transit organizations to examine and critique the existing statewide process and to recommend a redesign. The committee supported a longer term and more decentralized process than that previously employed, and recommended that the process have the following characteristics:

The redesign effort resulted in the following "guiding principles" for the planning and programming process:

The redesign resulted in guidance that includes the following procedures:

PENNDOT and its regional partners discuss and update the guidance in annual meetings.

In implementing the revised coordinated process, PENNDOT faces challenges because of the mismatch of State district boundaries to those of the MPOs and LDDs. Other states face similar coordination difficulties.

The Statewide Transportation Planning Process and Financial Planning

Developing the Plan

The current Statewide Long Range Plan, PennPlan Moves! (PennPlan), covers a 25-year period and was finalized in 2000. The plan was developed to incorporate needs and priorities from the MPO and LDD's long-range plans. The directions in PennPlan will be reflected in future updates to the regional and local plans.

PennPlan is a multimodal policy plan, considering long-range trends, needs, and goals for highways and public transit, as well as intercity rail, air travel, and non-motorized modes.

PennDOT publications.

PennPlan was based on extensive public involvement, including contacts with over 2000 citizens. Based on this outreach, PENNDOT identified two high-level priorities for all modes:

  1. Safety
  2. Maintenance

PennPlan identifies ten statewide goals:

  1. Promote safety of the transportation system
  2. Improve the environment
  3. Retain jobs and expand economic opportunities
  4. Make transportation decisions that support land use planning objectives
  5. Maintain, upgrade, and improve the transportation system
  6. Inform and involve the public and improve customer service
  7. Advance regional and corridor-based planning
  8. Develop transportation alternatives and manage demand
  9. Promote smooth, easy connections between transportation alternatives
  10. Ensure accessibility of the system and mobility for everyone

These ten goals provide the basis for two sets of objectives within PennPlan:

  1. Statewide Objectives
    • Identifies 30 objectives.
    • Multiple objectives correspond to each goal.
    • Each objective tracks to one or more of the 10 goals.
    • Each objective has performance measures with quantified targets.
  2. Corridor Level Objectives
    • Identifies 28 corridors of statewide importance (described in PennPlan as concepts rather than in detail).
    • Objectives for each corridor were set in cooperation with MPOs, LDDs, and other regional and local authorities.
    • A primary purpose is to ensure there is continuity for corridors in the plans of neighboring states.
    • The corridors are assessed at a technical level in Trends and Issues Reports.

PennPlan is available on-line.

PENNDOT issues annual reports on achievement of the goals and objectives in PennPlan (see section below on performance measures).

Financial Planning and Fiscal Constraint

The statewide planning priority, as expressed in PennPlan, is to maintain the existing system. Consistent with this priority, the target is to spend 80 percent of statewide funds on maintenance and 20 percent on capacity improvement. Of the total amount of highway funds, the Secretary can allocate up to 20 percent from a discretionary "spike fund" derived from Pennsylvania's portion of federal transportation money. These funds are provided for "spike projects" proposed by the MPOs and LDDs as priority investments that cannot be funded through routine regional funding allocations and would overwhelm other State and local resources.

PENNDOT provides financial guidance to its regional partners for preparing programs and is working on developing guidance for Long Range Plans. The financial guidance is based on the "guiding principles" described above.

PENNDOT also develops an annual Business Plan for its Districts. This plan translates statewide performance measures into strategies for each District.

PENNDOT works with other State and federal agencies to combine transportation resources with those available for other sectors to pursue common goals. PENNDOT representatives provided the example of its interaction with the Pennsylvania Department of Community and Economic Development. Funding from both agencies can be combined to examine community needs and opportunities for development. The agencies undertake collaborative studies on how communities can encourage interaction between land use and transportation decisions.

Priority Setting and Developing the STIP

The Pennsylvania STIP is designed to implement the vision, policies, goals, and objectives of the current Statewide Long Range Plan. As required by TEA-21, PENNDOT produces a four-year STIP, combining the 14 MPO TIPs with projects from the LDDs or rural counties. Projects in the metropolitan TIPs must be included in the STIP to be eligible for State funds. After the Governor endorses the STIP, it goes to USDOT for review and approval; this review includes determination of fiscal constraint as well as air quality conformity for non-attainment areas, including the Philadelphia and Pittsburgh metropolitan areas.

In a parallel but independent process to development of the STIP, PENNDOT is required by the State Legislature to produce a 12-Year Transportation Program that has been in effect for many years. Originally, PENNDOT had a six-year program but when the agency was unable to complete substantial parts of the program because of limited funds, it extended the program to twelve years.

The 12-Year Program:

If required, the 12-Year Program can be amended through action of the State Transportation Commission at its quarterly meetings; the metropolitan TIPs can be amended at the MPO level. MPOs and LDDs amend their TIPs on a monthly basis and the overall program is formally updated every two years. The State does not prepare an annual STIP.

The redesigned collaborative approach to financial planning, including development of the MPO TIPs and LDD programs, is described in the Financial Guidance developed by PENNDOT and the regional agencies. This approach reflects the following:

The Pennsylvania programming process for development of the STIP and TIPs has highway and transit components. The Highway Program includes all Federal and State capital funds anticipated over the four year STIP duration. The programming process includes the following major funding categories:

The Transit Program is a combination of federal, state, and local funds. Federal funds are provided through TEA-21.

Pennsylvania has developed a consistent approach for MPOs to use in developing their TIPs that encourages consistency not only with the statewide planning process, but also with key aspects of the TEA-21 planning requirements. The process, including allocation of financial resources, involves the following steps:

One result of this process, as described by participants in the financial scan, is that PENNDOT allocates about 80 percent of statewide funds relying on decisions made at regional or metropolitan area levels.

PENNDOT uses the technique of "advance construction" (AC) extensively, carrying a balance of $400-$500 million of AC at any time. AC allows states to begin a project using non-federal funds while preserving eligibility for future Federal-Aid funds. FHWA determines that eligible projects technically qualify for Federal-Aid even though present or future Federal funds have not been committed to the projects. After an advance construction project is authorized, the State may convert the project to regular Federal-Aid funding provided these funds are made available for the project. AC provides more flexibility in financing projects and developing financial plans, particularly the STIP, and allows the State to begin construction on additional projects sooner. The PENNDOT projects typically are converted to Federal-Aid annually to match cash flow needs for each year of construction.

The MPO Perspective on Statewide Financial Planning

The federal team visit included discussions with representatives of the Tri-County Regional Planning Commission, the regional planning agency for Cumberland, Dauphin, and Perry Counties, the City of Harrisburg, and Capital Area Transit, and the Harrisburg Area Transportation Study (HATS) the MPO for the Tri-County region. The representatives described how the agencies participate in the statewide planning process and financial planning and prepare the regional TIP. These perspectives provided the federal team with general insights into how Pennsylvania MPOs work with PENNDOT.

The Tri-County RPC and HATS staff described their approach to integrating land use and transportation planning as follows:

The Harrisburg area MPO develops a long-range plan that incorporates county and local plans. This plan is a basis and justification for projects in the MPO's TIP. The planning process:

In describing their evolving relationship with PENNDOT, the Harrisburg area representatives described PENNDOT as responsive both to MPO and statewide needs. The MPOs and other regional agencies play a role as "gatekeepers" in program development, consistent with the earlier reference in this summary.

The representatives described the Harrisburg area process as including the following steps:

The 17 criteria consist of:

This metropolitan planning process, with its links to statewide planning and Federal TEA-21 planning requirements, parallels that described more generally across the State in the STIP development section of this summary.

Use of Performance Measures

PENNDOT and its regional partners make extensive use of performance measures throughout the statewide planning process and financial planning. For example,

PennPlan, the current statewide long-range plan, is based on performance measures. Each objective under each goal has performance measures with quantified targets. For example,

PENNDOT issues annual reports monitoring achievement of the goals and objectives in the PennPlan. The reports present progress in meeting PennPlan's statewide long-range objectives with performance measures, targets, and accomplishments, quantified when appropriate, otherwise in descriptive summaries. The reports also describe progress in meeting corridor objectives from PennPlan.

For example, the 2001 Achievement Report includes the following:

Objective: Adhere to maintenance first policies in allocation of financial resources.

Performance Measure: Percentage of PENNDOT resources expended on maintenance programs and projects.

Target: 80 percent.

Achievement: 78 percent for maintenance, up from 71 percent 2000 and 22 percent for system expansion. Target "not met."

Objective: Achieve goals in updated ITS Plan.

Performance Measure: Number of goals achieved.

Target: Achieve all goals in timely manner.

Achievement: Activities toward five of six goals are underway. Progress toward target on schedule.

Objective: Promote telecommuting as alternative to traditional work travel.

Performance Measure: Percentage of Pennsylvanians who work at home one or more days a week.

Target: Percentage increased annually from 2000 measurement of 18 percent.

Achievement: 37 percent worked at home one or more days per week. Target met.

The reports on annual performance are available on-line.

PENNDOT also develops an annual Business Plan for its Districts, which translates statewide performance measures into strategies for each District.

Observations from Pennsylvania DOT

PENNDOT and MPO participants in the meeting offered the following observations related to financial planning:

Contact

Dennis Lebo
dlebo@state.pa.us
Chief, Program Development
400 North Street, 6th Floor
Harrisburg, PA 17120


FHWA Home | HEP Home | Feedback
FHWA