# Activity Authority Action Frequency Delegated To
  R = Review, A = Approve, C = Compliance
SP Statewide Planning
1. 20 yr Statewide transportation plan 23 CFR 450.214 R for C As updated Community Planner
2. 3 yr STIP & amendments 23 CFR 450.216, 220 R & A w/ FTA As requested by State (at least biennially) Community Planner
3. Interstate additions & access revisions 23 CFR 470.111, 115(a) R & A or Recommend action to HQ for system to system or new As requested by State Headquarters and/or Design Engineer
4. NHS revisions 23 CFR 470.113, 115(a) R & Recommend action to HQ As requested by State Headquarters
MP Metropolitan Planning
1. Transportation plan for non-attainment metropolitan areas 23 CFR 450.322 R & A Every 3 yrs Community Planner
2. Transportation plan for attainment metropolitan areas 23 CFR 450.322 R for C Every 5 yrs Community Planner
3. Transportation Improvement Plan (TIP) and corollary STIP amendments for non-attainment areas 23 CFR 450.324 - 330(b) R & A As requested by State - at least biennially Community Planner
AQ Air Quality
1. Transportation plan conformity determination for non-attainment areas 23 CFR 450.322(d) R & A Every 3 years Community Planner
2. TIP conformity determination for non-attainment 23 CFR 450.330(b) R & A Every 2 years Community Planner
E Environment
1. Environmental document determination (all other projects) 23 CFR 771.113 R & A As submitted by State Project Manager
2. Final EIS 23 CFR 771.125 R & A As submitted by State DivisionAdministrator
3. Record of Decision (ROD) 23 CFR 771.127 R & A 30 days after publishing final EIS DivisionAdministrator
4. EIS written re-evaluations 23 CFR 771.129 R & A If no action is taken within 3 years after final EIS as submitted by State Project Manager
5. Section 4(f) individual 23 CFR 771.135 R & A As submitted by State Project Manager
6. Section 106 actions 36 CFR 800 R & A As submitted by State Project Manager
7. Implement Mitigation Commitments during PS&E Review 23 CFR 635.309(3)(j) R & A Project by Project Project Manager
DCM Design, Construction, & Maintenance
1. Consultant Agreements, Supplements, and Settlements for Megaproject 23 CFR 172.5 R & A As needed Project Manager
2. Projects Near Airports 23 CFR 620.103 R As requested Project Manager
3. Highway Facility Relinquishment 23 CFR 620.203 R & A As needed Project Manger
4. Design Exception Request 23 CFR 625.3 R & A As needed Project Manager (w/ Design Engineer)
5. Plans, Specifications, & Estimates (PS&E) 23 CFR 630B, 23 CFR 633.102 23 USC 106 R & A Project by project Project Manager
6. Competitive Bidding 23 CFR 635.104, 23 USC 112 R & A As requested Project Manager
7. Use of Public Owned Equipment 23 CFR 635.106 R & A As needed Project Manager
8. Changed Conditions 23 CFR 635.109 R & A As needed Project Manager
9. Concurrence in Award 23 CFR 635.114, 23 USC 112(d) R & A Project by project Project Manager
10. Changes and Extra Work 23 CFR 635.120 R & A As needed Project Manager
11. Claims 23 CFR 635.124 R & A As needed Project Manager
12. Statement of Materials and Labor (NHS projects of $1 million or more) (form FHWA-47) 23 CFR 635.126 Periodically R for C (State prepares and submits to HQ Project by project Project Manager
13. Public Agency Furnished Material 23 CFR 635.407 R As needed Project Manager
14. Utility Agreement 23 CFR 645.113 R & A Project by project Project Manager
15. Railroad Agreement 23 CFR 646.216 R & A Project by project Project Manager
16. Construction Inspection FAPG G 6042.8 R for C As needed Project Manager
17. Project Authorizations/Agreements (PE, Final Design, ROW, Utilities, RR, Force Account) 23 CFR 630 Subpart C Accept As needed Project Manager (w/ Finance Manager)
18. Authorization to Advertise 23 CFR 630.106 and 23 CFR 635.309 R & A Project by project Project Manager
19. Advanced Construction (all projects) 23 CFR 630.705 R & A As needed Project Manager
20. Payroll (all projects) 23 CFR 635.118 R As needed Project Manager
21. Termination of Contract 23 CFR 635.125 R & A As needed Assistant DivisionAdministrator
22. Value Engineering (NHS and $25 million or more) 23 CFR 627 and P.L. 104-59 Sec 303 R for C (State conducts study) Project by project Project Manager (w/ Design Engineer)
23. Bid Opening/Tabulations 23 CFR 635.113 Periodically R for C (State takes action) Per letting Field Operations Engineer
24. Utility Agreement Alternate Procedure 23 CFR 645.119 R & Accept One time Program Operations & EngineeringTeam Leader(w/ ADA)
25. Utility Accommodation Policy 23 CFR 645.215 R & A When changes occur Program Operations & EngineeringTeam Leader(w/ ADA)
26. Railroad Agreement Alternate Procedure 23 CFR 646.220 R & A One time Program Operations & EngineeringTeam Leader(w/ ADA)
PM Pavement & Materials
1. Buy America 23 CFR 635.410 R & A As Needed Project Manager
2. Proprietary Materials 23 CFR 635.411 R & A As Needed Project Manager
3. Warranties 23 CFR 635.413 R & A As Updated Project Manager
4. Convict Produced Materials 23 CFR 635.417 R & A As Needed Project Manager
5. Materials Acceptance 23 CFR 637.207 R & A As Updated Project Manager
6. Quality Control/Quality Assurance Programs 23 CFR 637.207 R & A As Updated Project Manager
7. Sampling and Testing of Materials 23 CFR 637.207 R & A As Updated Project Manager
B Bridge
1. HBRRP eligibility determinations 23 CFR 650 Subpart D R & A Project by project Finance
2. HBRRP discretionary candidate submittals 23 CFR 650 Subpart D R & A Annually by July 1 Bridge Engineer
3. TS & L and PS&E reviews 23 CFR 630, 23 USC 106, and W.O. 11/13/98 memo R & A Project by project Project Manager (w/ Bridge Engineer)
4. Innovative Bridge Research and Construction Program eligibility determination 23 USC 503(b) R & A and submit to HQ Annually (date varies) Bridge Engineer
5. Construction inspections FAPG G 6042.8 R for C As needed Project Manager (w/ Bridge Engineer)
M Mobility/ITS
1. Congestion management system 23 CFR 500.109 R for C As needed/revised by MPO/State Project Manager (w/ ITS Engineer)
2. Conformity with National ITS Architecture FHWA Final Rule dated January 8, 2001 R for C As needed w/PS&E submission (full oversight projects that affect regional integration) Project Manager (w/ ITS Engineer)
3. ITS Life Cycle Cost (>$3 million) and ITS Financing and Operations Plan TEA-21 Section 5210 R for C As needed for projects funded by TEA-21 Sections 5208 and 5209 Project Manager (w/ ITS Engineer)
4. ITS Service Plan TEA-21 Section 5207 Develop As needed ITS Engineer
FM Financial Management
1. Finance Plan & Annual Updates for Megaprojects TEA-21 Section 1308, and associated FHWA Guidance Review & Accept Prior to authorization of construction, and annually thereafter. Division Administrator
2. Project Agreements - including drug free work place and other provisions 23 CFR 630 Subpart C Accept As needed Finance Manager(w/ Project Manager)
3. Fed-aid billing reimbursement of eligible expenditures 23 CFR 140 and 635.122 R & A Weekly Finance Manager
4. Transfer of funds as requested by State 23 USC 104 (c) and 119 (f) R & A As needed Finance Manager
S Safety
1. Work Zone Safety Process review of effectiveness 23 CFR 630.1010 R & A Annually by Sept. 30 Safety Engineer
R/W Right-of Way
1. State R/W Manual changes 23 CFR 710.201 R & A Jan. 1, 2001 & every 3 years thereafter ROW
2. Uniform Relocation Assistance and Real Property Acquisition Report - (OMB Form 2125-0030) 49 CFR 24.9(c) and Appendix B R Every 3 years ROW
3. Requests for waivers 49 CFR 24.204(b) R & A As submitted by State ROW
4. Use of R/W Air Space authorization request (on Interstate system) 23 CFR 710.405 R & A Project by project ROW
5. Access Break / R/W Disposal authorization request (if on Interstate system or fair market value not charged) 23 CFR 710.401 & 409 R & A Project by project ROW
6. Functional Replacement 23 CFR 710.509 Periodically R for C (State takes action) As needed ROW
7. Lead Agency Uniform Act monitoring activities 49 CFR 24.603 R for C As needed ROW
8. Develop R/W oversight agreement 23 CFR 710.201(i) R & A By Jan. 1, 2001 and updated as needed ROW
CR Civil Rights
1. Title VI Plan accomplishments and next year's goals 23 CFR 200.9 R & A Annually by Oct. 1 Civil Rights
2. Title VI Plan update 23 CFR 200.9 R & A As needed or requested by State Civil Rights
3. EEO Contract Compliance review reports (form FHWA 86) 23 CFR 230.409, 230.413 R & A As submitted by State Civil Rights
4. Disadvantaged Business Enterprise (DBE) Program revisions 49 CFR 26.21(b) R & A As needed or as requested by State Civil Rights
5. State's DBE program goals 49 CFR 26.41 R & A Annually by Aug 1 Civil Rights
6. Supportive services funds requests 23 CFR 230.113 R & A As requested by State Civil Rights
7. Annual Contractor Employment Report (Construction Summary of Employment Data (form PR-1392)) 23 CFR 230.121(a) R for C and send to HQ Annually by Sept 25 Civil Rights
8. Report on supportive services (On-the-Job Training (OJT) & DBE) 23 CFR 230.121(e) R for C and send to HQ Quarterly by April15, July 15, Oct 12, and Jan 15 Civil Rights
9. OJT goals & accomplishments 23 CFR 230.111(b) R for C Annually by Jan 30 Civil Rights
10. Report on supportive services (OJT & DBE) 23 CFR 230.111, 113 R for C Quarterly Civil Rights
11. Americans with Disabilities Act Review complaint Voluntary agreement with Justice Dept. Conduct evaluation & correct or recommend action to HQ As requested by HQ Project Manager
Word files can be viewed with the Word Viewer 2003

More Information

Contacts

Jim Sinnette
Office of Program Administration
202-366-0479
E-mail Jim

 
 
This page last modified on 05/11/07
 

FHWA
United States Department of Transportation - Federal Highway Administration